Concept

Support settlement — where it appears

A movement imposed at a support, which a determinate structure absorbs without force and an indeterminate one answers with moments proportional to its own stiffness. The moments it causes are proportional to the flexural rigidity, so a stiffer structure is punished harder for the same movement — the opposite of every intuition that carrying load gives.

Named by 18 essays across 4 fields — each of them below, with the objects they name alongside it.

A three-pinned arch, rise 2.6 on span 9. A three-pinned arch under a uniform load. One moment equation about the crown hinge gives a horizontal thrust of 23.37, with no stiffness and no assumption about the section. The thrust line lands on the axis everywhere, so there is no bending anywhere in the arch.

The hinge put in on purpose

An arch with two pinned feet cannot be solved by statics. Add a third hinge at the crown — deliberately weakening it — and the whole structure falls out of one moment equation.

structures · Arch
Where the peak moment goes when a restraint is added. The same uniformly loaded beam with three sets of restraints, and the bending moment in each. Adding restraint moves moment from mid-span to the supports and lowers the peak — but only the first case can be solved by statics.

One support too many, and what it costs to know

Add a redundant restraint and the load has two routes to the ground. Equilibrium cannot say how it splits, and the answer turns out to depend on stiffness — which is a different kind of question.

deflection · Indeterminacy
3 continuous spans against 3 simple ones. The bending moment in a continuous beam whose support 1 has settled by 0.01. Three curves: the moment the load causes, the moment the settlement causes on its own — dashed, peaking at 73.5, and in equilibrium with no applied load at all — and their sum, which is what the beam carries, peaking at 73.5 against 24.5 without the settlement. The settlement field is proportional to EI: a stiffer beam is punished harder for the same movement, which is the opposite of every intuition load-carrying gives.

The support that moved

A redundant structure knows things statics cannot see. Settle one support by ten millimetres and a complete set of bending moments appears — in equilibrium with no load at all, and larger for a stiffer beam.

deflection · Indeterminacy
The depth is decided by how far it moves, not by what it can carry. A column carrying 6000 kN landing 3 m into a 12 m transfer member. The free body is the member itself, cut under the column: M = P·a(L − a)/L = 13500 kNm, with 4500 kN of shear on one side of the cut and 1500 on the other. At an allowable stress that moment asks for 1.94 m of depth — the dashed outline — and keeping the settlement it causes inside the floors' own bending asks for 2.55 m, which is the member drawn solid. 31% more depth is bought by nothing the strength calculation can see. The depth grows as √(P·a), so four times the load is exactly twice the depth, and depth in a transfer member is a storey nobody occupies.

The column that stops

A load path that runs straight to the ground costs almost nothing. Interrupting one costs depth in proportion to the square root of the load times the distance it is moved — and the interruption's own deflection becomes the settlement of everything standing on it.

structures · Transfer structure
Two differences up the same building, peaking in different places. Differential shortening between a perimeter column and the core of a 40-storey building, plotted up the height. The part driven by load peaks at level 20 — exactly half way up, because a floor near the top has almost nothing built above it to shorten what is beneath, and a floor near the bottom has almost nothing beneath it to shorten. The part driven by shrinkage does not care what is above it at all and accumulates all the way to the roof. Their sum is worst at level 40, at 43 mm, which across a 9 m bay is a floor out of level by one in 208.

The columns are shorter than the core

Every column in a tall building gets shorter as the building is built on top of it, and the core beside it gets shorter by a different amount. The floors between them tilt by the difference — and the difference is largest exactly half way up, because a floor near the top has almost nothing built above it and a floor near the bottom has almost nothing beneath it.

deflection · Differential shortening
How much of a deflection belongs to the beam. The share of the total deflection that is the beam's own bending, against the stiffness of what it sits on. A 8 m beam on two supports under a uniform load: on rigid supports every millimetre is the beam's, and the share falls away as the supports soften until almost none of it is. The beam drawn beside this figure sits at 51% — so 49% of what it does is happening somewhere a beam calculation never looks. The two flexibilities are in series, which means the softer one governs and stiffening the other buys nothing.

The deflection that belongs to the support

A beam calculation answers a question about a beam sitting on things that do not move. Real ones sit on bearings, on other beams and on columns that shorten, and every one of those is a spring in series with the member — so a deflection is the sum of two things and only one of them is a property of the beam.

deflection · Support flexibility
The tie is a redundancy, so its stiffness decides the thrust. Thrust and rib bending for a 60 m tied arch of 0.15 rise ratio, against the stiffness of its tie. Cut the tie and the structure is a curved simply supported beam, so the tie force is the one redundant and the force method gives it: with a rigid tie the answer is 2227 kN, within 1.0 per cent of the funicular wL²/8f, and the shortfall is the arch's own axial shortening. A real tie stretches 68 mm and returns 2166 kN — 2.7 per cent of the flexibility is the tie — and whatever thrust the arch does not get, it carries as bending: 760 kNm at 30 m. A tenth of the tie stiffness is not a tenth of the problem; it is a different structure.

The thrust that never reaches the ground

The arches so far have all ended at the same sentence — the foundation is where an arch is really decided. A tie changes the sentence without changing the arithmetic: the horizontal force is still there, still the same size, and it now closes on itself through a bar at deck level.

structures · Tied arch
How stiff an abutment has to be to count as fixed. The shortening moments in a 60 m parabolic concrete rib at a 6 m rise (EI 420,000 kN·m²) under 60 kN/m as shares of the fixed rib's, against the rotational stiffness of each springing as a multiple of EI/L on a logarithmic scale: at the springings (solid, −112 kN·m when fixed) and the crown (dashed, 58 kN·m fixed, 29 two-hinged). The springing moment is half the fixed value at kθ = 11.3 EI/L and nine tenths at 102 EI/L; at EI/L itself it is 8 per cent. The crown moment never falls below the two-hinged rib's 51 per cent of the fixed value.

The abutment that spreads before it turns

A fixed arch is fixed only if its abutments hold still, and they have two ways not to. Turning releases the springing moment, but slowly: an abutment has to be a hundred times the rib's EI/L to hold nine tenths of it, and a footing on stiff clay under a slender concrete rib already is. Spreading does the opposite. The rib's own shortening is worth 13.6 mm of spread, so an abutment that gives 7 mm a side under the thrust doubles every secondary moment in the arch — and a footing on dense sand gives 8.

deflection · Rib shortening
The deck moves the frames' feet, and the chord goes with them. A chord 24 m long, EI 2.52 × 10¹² N·mm², held by U-frames of 1,400 N/mm every 4 m, carrying 930 kN, in plan, sideways movements drawn 6 times the scale of the length: each frame's foot pushed 7.5 mm inward by its cross-girder's rotation under the deck (arrows), the chord's movement under that push alone (solid), and under the worst bow alone, four half-waves at 12.0 mm (dashed). The chord follows the push, and under its compression goes a little further — 9.1 mm at its middle frames against the 7.5 mm the feet moved — because a chord 24 m long is far softer sideways than the frames holding it; the frames that carry most are the end ones, beside the chord's fixed ends.

The frames the deck pushes first

A half-through girder's U-frames are the ends of the cross-girders that carry its deck. Load the deck and every cross-girder sags, its ends rotate, and every frame's foot swings inward by millimetres before the compression chord has asked the frames for anything. It looks like a second imperfection on top of the chord's bow. It is a much weaker one: the frames all move together and the chord simply goes with them, so a 7.5 mm push adds 1.4 kN to frames that the bow loads with 13.6, and stiffer frames make it smaller, not larger. What the push leaves is mostly in the frames' own members, not in what they ask of the chord.

stability · Continuous restraint
A jack set for the first day is wrong by the last. The secondary moment over the first interior support of a five-span beam of 16 + 16 + 16 + 16 + 16 m prestressed with 2,400 kN on a parabolic tendon, built from both ends towards a closure bay, against the creep coefficient: not jacked; jacked at closure by the whole of what the order took, 183 kN·m there; jacked by 0.60 of it, so as to reach the at-once moment at a creep coefficient of 2.0; and by 0.89, so that the shortfall on the day and the overshoot at the end are equal; dotted, stressed at once, 344. On the day and at 2.0: not jacked, 161 and 302; jacked by the whole, 344 and 372; for the end, 271 and 344; balanced, 324 and 365.

The jack that creep carries past the mark

A continuous beam built from both ends towards a closure bay keeps less secondary moment at its supports than the same beam stressed all at once, and creep gives back three-quarters of the difference over the years. Bridge builders do not always wait: before the closure is cast, the supports can be lowered on jacks so that the beam starts with the moments it would have had. Jacked by the whole difference, it does start there — and creep, which goes on returning the staged deficit while it relaxes the jacked correction, carries it past them, by a seventh of what was jacked. Jacked by 0.89 of the difference, it starts a ninth short and ends a ninth over. And it takes a jack at every interior support: with fewer, the moment goes to the wrong places.

internal-forces · Secondary prestress
The middle reaction is a dimension, read off in millimetres. The middle reaction under dead load of a Pratt truss continuous over two 24.0 m spans, 3.0 m deep, carrying 60 kN of dead load at each interior bottom joint, against the height of its middle bearing above the level drawn, cut to the continuous list (solid) and as two simple spans (dashed). At the drawn level the continuous list lands with 572 kN, the analysis's value, and the simple-span list with 480 kN, the two spans' own share. Every millimetre the bearing stands high adds 2.6 kN: 10 mm high, 598 kN; 10 mm low, 545; the simple-span list's 92 kN shortfall is the bearing 35 mm low.

The pier's share is cut into the members

A truss continuous over a middle support has one reaction that statics cannot find, and the lengths its members are cut to decide it. Cambered to land level under its dead load on three bearings, a two-span truss puts 572 kN on its pier; cambered span by span, as two simple trusses, the same members on the same bearings put 480 kN there and carry the dead load with no moment over the pier at all. The list chooses the moment diagram. And a millimetre of shop tolerance on every member moves the pier's share as much as a bearing set fourteen millimetres out of level, so a reaction the design depends on has to be set by a jack rather than by a drawing.

deflection · Camber
Under a moving pattern of load the hinged beam gives nothing away. The greatest and least moment at each point over every arrangement of 15 kN/m on whole spans, with 20 kN/m everywhere. Continuous, 152 and -184 kN·m; with hinges at 0.25 of a span, 171 and -161. The largest moment of either kind is 184 and 171.

Two hinges let in and nothing lost

Continuity is usually sold as the reason to avoid hinges: a continuous beam shares its moment over the supports, and a chain of simple spans wastes it. Heinrich Gerber's 1866 bridge showed that the choice is not between those two. Put two hinges in the right places and the beam becomes statically determinate, a support can settle as far as it likes without moving a single moment, and under a pattern of moving load the largest moment comes out lower than the continuous beam's. What has been spent is something a moment diagram does not show: if one of those hinges fails, there is no other way for the load to reach the ground.

internal-forces · Continuity
One pier settles, and the size of the group hardly matters. The largest moment anywhere under the full 35 kN/m with one pier settled, the worst pier chosen, for twelve 7 m spans as simple spans, in continuous groups of two and three, and continuous throughout, EI 100,000 kN·m². At 15 mm, 214, 260, 245 and 260 kN·m; at 40 mm, 214, 337, 367 and 392.

What the joints in a viaduct are for

A long viaduct is usually built as continuous groups of three or four spans with a movement joint between them, and the grouping is often explained as a compromise between continuity's economy and a chain of simple spans' indifference to settlement. Computed, settlement does not take part in the compromise: two spans continuous already feel a sinking pier as the whole viaduct would. Nor does robustness, much. What the joints are for is the movement of the deck, and what the group's size buys is the moment of the traffic.

internal-forces · Continuity
The thrust as the springings spread. The horizontal thrust of a semicircular arch of 10 m span over its least thrust at rest, against the springings' spread as a share of the span, up to collapse, for rings of 0.11, 0.15 and 0.2 of the radius. The thrust rises to 1.02, 1.34, 1.89 times its value at rest at spreads of 0.4%, 6.2%, 13.7% of the span.

The arch that pushes harder as it spreads

A masonry arch whose abutments move apart does not fall when they first move. It cracks at its crown and its haunches, turns into a mechanism of three hinges, and keeps standing while its crown drops — and the thrust it puts on the abutments that are already giving way rises. A semicircle of 10 m with a ring 0.15 of its radius survives 626 mm of spread, pushing a third harder at the end than at the start, and collapses only when the thrust reaches the outer edge of its springing.

structures · Arch
The spread ring at its point-load capacity. A semicircular arch of 10 m span with a ring 0.15 of its radius, its springings 313 mm apart, 0.50 of the 626 mm at which it collapses under its own weight, drawn to scale with a point load at 0.25 of the span. The line of thrust is drawn at the largest load the ring carries, 29.8 kN a metre width, 0.126 of its weight: it passes through hinges 30.0°, 85.0°, 142.5° from the left springing and reaches the extrados at 180.0°, where the fourth hinge would open.

The wheel on an arch that has spread

A masonry arch whose springings have moved apart still stands, and its thrust has risen. It has not grown stronger. A semicircle of 10 m span with a ring 0.15 of its radius carries 52.8 kN a metre on its quarter span before its springings move, and 29.8 kN at half the spread that would bring it down. A point load and a spread spend one reserve, the thrust the far springing can take, and the spread spends it first.

structures · Arch
Two doubtful piers settle: groups of three, joints over them, or each in a pair. Twelve 7 m spans under the full 35 kN/m, the fifth or the eighth pier settling, whichever is worse, the largest moment anywhere. At 40 mm: groups of three 367 kN·m, joints over the doubtful piers (groups of 5, 3, 4) 315, each doubtful pier in the middle of a two-span pair (4, 2, 1, 2, 3) 230, continuous throughout 373, simple spans 214. With no settlement, 172, 184, 214, 181 and 214.

The doubtful pier belongs in the middle of a pair

A viaduct's designer who knows which piers stand on poor ground can put a movement joint over each of them, and the joint helps: with either of two piers settling 40 mm, twelve spans grouped to put joints over them carry 315 kN·m where groups of three carry 367. Putting each doubtful pier in the middle of a two-span pair does far better, 230, because a pair's hogging is the thing a settling middle pier relieves. Under the full load, until its pier has sunk 35 mm, a pair is no worse than two simple spans, and it pays for that with the traffic envelope that groups of three were chosen for.

internal-forces · Continuity
Rounds of the jacks: one pier at a time, or all together. The largest pier error as a share of the landed one, the mean of 40 fabrications, against rounds of the jacks — a round being every jack operated once: one pier at a time from the left, 0.49, 0.20, 0.15 after one, two and three rounds; all together from one set of readings, using the truss's own lift matrix, 0.00 after one; using the matrix of a truss whose web does not stretch, 0.30, 0.11, 0.04.

The second pier undoes the first

A truss continuous over one pier has its reaction set by one jack: lift until the load cell reads the design value, pack the bearing, done. Over three piers the jacks argue. Lifting one pier a millimetre hands 85 per cent of what it gains to the pier beside it, so jacking each pier to its own design reaction in turn leaves half the error after a full round and still a seventh after three. The error that will not go is the one the piers share, which lifting them all together barely moves. Read every pier once and solve for all the lifts together, and one round of the jacks does what ten rounds one at a time cannot.

deflection · Camber
Doubtful piers that may rise or settle, by how much. Twelve 7 m spans under the full 35 kN/m, the fifth and eighth piers each moving anywhere between rising and settling by the amount on the axis, the largest moment over every combination. At ±40 mm: continuous 518 kN·m, groups of three 465, joints over the doubtful piers 335, each in a pair 459, simple spans 214.

The pier that may rise belongs under a joint

A pier that may only settle is best put in the middle of a two-span pair, whose hogging a settlement relieves before it adds to anything. A pier on swelling clay, or over a culvert that may be relieved of its fill, may rise instead, and then the pair is the worst place for it: 40 mm of heave puts 459 kN·m into a pair that would have carried 230 for the same settlement. The place that is gentle both ways is the end of a group, under a movement joint. With the doubtful piers' movement known in size but not in sign, joints over them carry 335 kN·m where pairs carry 459 and groups of three 465 — and nothing with the same traffic envelope does better.

internal-forces · Continuity

Named alongside it

The objects these essays reach for when they reach for this one.

IndeterminacyAxial shorteningCompatibilityPattern loadingRobustnessContinuityContinuous beamCreepHorizontal thrustImposed deformationMovement jointServiceability

All concepts