Axial shortening — where it appears
Named by 9 essays across 3 fields — each of them below, with the objects they name alongside it.
The columns are shorter than the core
Every column in a tall building gets shorter as the building is built on top of it, and the core beside it gets shorter by a different amount. The floors between them tilt by the difference — and the difference is largest exactly half way up, because a floor near the top has almost nothing built above it and a floor near the bottom has almost nothing beneath it.
The deflection that belongs to the support
A beam calculation answers a question about a beam sitting on things that do not move. Real ones sit on bearings, on other beams and on columns that shorten, and every one of those is a spring in series with the member — so a deflection is the sum of two things and only one of them is a property of the beam.
The thrust that never reaches the ground
The arches so far have all ended at the same sentence — the foundation is where an arch is really decided. A tie changes the sentence without changing the arithmetic: the horizontal force is still there, still the same size, and it now closes on itself through a bar at deck level.
The arch that gets shorter
A parabolic arch under a uniform load is funicular, so the perfect solution gives it no bending at all. Then the rib shortens under its own thrust by a tenth of a per cent, and every kilonewton-metre of moment the arch will ever carry comes from that.
The springings that make shortening worse
Fixing an arch at its springings is the stiffer, cheaper and usual way to build one in concrete, and it makes the arch six times as sensitive to its own shortening. The thrust it loses acts at the elastic centre, two thirds of the way up, so the moment lands at the springings as well as the crown, twice as large and the other way round — at the section the fixed arch is designed at, not away from it.
The abutment that spreads before it turns
A fixed arch is fixed only if its abutments hold still, and they have two ways not to. Turning releases the springing moment, but slowly: an abutment has to be a hundred times the rib's EI/L to hold nine tenths of it, and a footing on stiff clay under a slender concrete rib already is. Spreading does the opposite. The rib's own shortening is worth 13.6 mm of spread, so an abutment that gives 7 mm a side under the thrust doubles every secondary moment in the arch — and a footing on dense sand gives 8.
The jacks the arch forgets
Jack a fixed concrete arch's abutments apart before the crown is closed, by exactly the gap its thrust and its footings open on the day, and the springings start with no moment at all. A century later they carry 173 kN·m — half as much again as the 112 the jacks were set to remove. The thrust's own moment never relaxes; the jacks' correction does, as the rib creeps; and shrinkage and the ground's consolidation arrive after the jacks have gone. No single setting cancels movements that run on different clocks.
The column that shortens on every cycle
A column hinge bent back and forth by an earthquake carries its share of the building's weight the whole time. In elastic–perfectly plastic steel an I-section at three tenths of its squash load, cycled to three times its first-yield curvature each way, comes back from every cycle shorter by eight yield strains, and goes on doing so: it never settles. The flange that yields in compression shortens, and the other flange, carrying its part of the column's load, never reaches yield in tension to pull it back. A rectangle of the same area shortens a fifth as fast, and the overturning that swings the column's load up and down hardly matters. The weight and the curvature make the ratchet between them.
The floor that is level on one date
Each floor of a tall concrete building is set high by the amount its columns are predicted to drop against the core, so that it arrives level. Counted in time, the drop does not peak at mid-height and stop at the roof: the worst floor of a forty-storey building is level 31, the roof moves 24 mm, and half the movement is still to come when the floors are fitted out. Set high by all of the prediction, a floor is level on one date thirty years away and 16 mm high at handover. With the creep known to ±30 per cent, setting it high by about four fifths of the prediction makes the worst floor's error 11 mm instead of 16. And none of it changes what the partitions see.
Named alongside it
The objects these essays reach for when they reach for this one.
ArchThrustCreepSupport settlementDifferential shorteningFunicularImposed deformationIndeterminacyServiceabilityAbutmentConstruction sequenceElastic centre