Concept

Differential shortening — where it appears

The difference in axial shortening between two vertical elements at different stresses, which tilts the floors between them and peaks at mid-height. Its load-driven part is a parabola with its maximum near mid-height, and only the part arriving after a floor is set shows up as a tilt in the finished building.

Named by 14 essays across 3 fields — each of them below, with the objects they name alongside it.

Two differences up the same building, peaking in different places. Differential shortening between a perimeter column and the core of a 40-storey building, plotted up the height. The part driven by load peaks at level 20 — exactly half way up, because a floor near the top has almost nothing built above it to shorten what is beneath, and a floor near the bottom has almost nothing beneath it to shorten. The part driven by shrinkage does not care what is above it at all and accumulates all the way to the roof. Their sum is worst at level 40, at 43 mm, which across a 9 m bay is a floor out of level by one in 208.

The columns are shorter than the core

Every column in a tall building gets shorter as the building is built on top of it, and the core beside it gets shorter by a different amount. The floors between them tilt by the difference — and the difference is largest exactly half way up, because a floor near the top has almost nothing built above it and a floor near the bottom has almost nothing beneath it.

deflection · Differential shortening
How much of a deflection belongs to the beam. The share of the total deflection that is the beam's own bending, against the stiffness of what it sits on. A 8 m beam on two supports under a uniform load: on rigid supports every millimetre is the beam's, and the share falls away as the supports soften until almost none of it is. The beam drawn beside this figure sits at 51% — so 49% of what it does is happening somewhere a beam calculation never looks. The two flexibilities are in series, which means the softer one governs and stiffening the other buys nothing.

The deflection that belongs to the support

A beam calculation answers a question about a beam sitting on things that do not move. Real ones sit on bearings, on other beams and on columns that shorten, and every one of those is a spring in series with the member — so a deflection is the sum of two things and only one of them is a property of the beam.

deflection · Support flexibility
A couple applied to the core, and two columns to make it. A 20-storey core with one outrigger at 59% of its height. The arm is stiff in bending and the perimeter columns are stiff in tension and compression, so between them they resist the core's rotation at that level — a couple of 35283 kNm here, carried as a 294 kN pair in the columns at 120 m centres. The compatibility is one equation: the core's rotation at that level, less what the couple takes back out of it, equals the rotation the arm and its columns allow. The top drift falls from 360 mm to 74, which is 80% of it, and the base moment from 73500 to 38217 kNm. The deflected shape is drawn hugely exaggerated: the real top drift is about one five-hundredth of the height.

The arm that makes the columns work

The perimeter columns of a tall building are already there, already carrying gravity, and already the furthest thing from the centre. They take almost none of the overturning, because a floor slab transmits shear and not moment — and one storey-deep arm at the right height changes that by nearly a half.

structures · Outrigger
The props decide where the stress ends up. Bottom-fibre stress in the steel of a 12 m composite beam carrying 6 kN/m of wet concrete and 9 kN/m afterwards. Unpropped, the bare steel takes the first stage alone and reaches 146 MPa; propped, the finished composite section takes everything and reaches 93 MPa — a ratio of 1.57. 62% of the unpropped beam's final stress was locked in before the slab was structural at all. The deflections differ by 1.73 times for the same reason, and no drawing of the finished beam distinguishes the two.

The section that changed while it was being loaded

A stress is computed from a moment and a section modulus. When part of the moment arrived while the section was a different shape, there is no single section modulus to divide by — the stresses add and the properties do not, and two identical finished beams can differ by half again in stress with nothing on the drawing to say which is which.

sections · Staged section
The least reliable number in the material decides the answer, briefly. What a twenty per cent error in the concrete's tensile strength does to a computed deflection, against how far past cracking the beam is. Well past the cracking moment it does almost nothing — at 1.9 times M_cr the spread is 56 per cent — because the section is nearly fully cracked and the interpolation has run out. Just above cracking it does everything: at 1.19 times M_cr the same twenty per cent moves the deflection by 3658 per cent. Tensile strength is the property with the widest scatter and the least direct test, and a beam designed to sit near its cracking moment has put the answer on it.

The curvature nobody applied

Concrete shrinks as it dries, by about half a millimetre in every metre. In a symmetrically reinforced member that is a shortening and nothing else. In a member with more steel in one face than the other — which is every beam and every slab — the steel holds one side back and the section bends, with no load on it at all.

deflection · Shrinkage curvature
A tie is worth all of itself and a strut is not, which is worth nine per cent. The same 20 floors carried two ways, with every member drawn at the width its own force requires. Hung, the loads accumulate upward, so the largest hanger is at the top: 18.0 MN at 355 N/mm² with no buckling reduction of any kind. On columns they accumulate downward and the largest column is at the bottom, at the same force — but every column above it is understressed by its own slenderness, worst at the top where a 900 kN column still has to be 4.8 × 10³ mm² to reach χ = 0.529. Over the height the hangers total 0.002 m³ of steel against 0.002: a saving of 9.0 per cent, which is the average χ and nothing else.

Hung from the top, and nine per cent lighter

A tie is worth its full strength and a strut is not, so hanging the floors of a building from a hat truss ought to be an obvious economy. It is a real one, it is measurable, and it is nine per cent of the steel — shrinking as the building gets taller, which is the opposite of what the argument sounds like.

structures · Hung structure
The columns and the core shorten apart for decades. For a 200 m concrete building built a storey every week, its perimeter columns at 12 N/mm² and its core at 6 at the base, with an outrigger at 149 m of 1.0 × 10⁸ kN·m a radian: how much the columns (solid) and the core (dashed) have shortened below the outrigger's level, and the difference between them (heavy), in mm, against the years since the first storey was cast, on a log scale. When the building tops out, in week 55, the difference is 7.0 mm; after fifty years it is 30.5. 77% of the difference arrives after the frame is finished — creep under the finishes and the floors above, and the thick columns' slower drying, most of which comes after the core's thinner walls have done theirs.

The arm connected late

An outrigger is often left unconnected until a concrete building is finished, so that the columns and the core can shorten by their different amounts without it. Most of their difference has not happened yet. Three-quarters of fifty years' differential shortening arrives after the frame tops out, and an arm connected then ends up carrying 3.5 MN of it — 60 per cent of what the design wind puts into the same arm, permanently, and in the same direction on both sides of the core. The connection date is the largest load the arm has, and a stiffer arm collects it faster than it collects the wind.

structures · Outrigger
A joint that gives way to creep, two ways. For a 200 m concrete building built a storey every week and fitted out over six months, with an outrigger at 149 m of 1.0 × 10⁸ kN·m a radian connected on day 385: the force in one arm over the years, in MN, connected rigidly, through a friction joint that slides at 2.00 MN, and through a viscous damper of time constant 10 days; dotted, the 5.80 MN the design wind puts into the same arm. Rigid, the arm collects 3.48 MN. The friction joint lets it collect 2.00 MN, reached after 3.7 years, and holds it there for the rest of its life. The damper lets it collect at most 0.08 MN, while the building is being fitted out, and 0.00 after fifty years.

The arm that slips on purpose

An outrigger connected to a concrete building at topping out goes on collecting the columns' and the core's differential shortening for fifty years. The obvious cure is a joint that lets the arm move under the slow force and holds under the fast one. A friction joint cannot do it — once creep has brought it to its slip load it has nothing left on one side of the core, and a joint strong enough to hold the wind is never reached by the creep at all. A viscous damper can, because its force depends on how fast it is pushed rather than how far.

structures · Outrigger
The best compensation is less than the prediction. For every floor of a 40-storey building of 3.6 m storeys, its perimeter columns at 12 N/mm² and its core at 6 under the finished load, cast a floor every seven days, with 25 per cent of the load arriving as finishes 90 days after the frame is complete and creep coefficient 2.2, from its fit-out to thirty years, with the creep anywhere within ±30 per cent of the design value: the largest amount any floor stands high (dashed) and stands low (light), and the worse of the two (solid), against the share of its predicted thirty-year movement each floor is set high by. Uncompensated, a floor ends 31.9 mm low; compensated in full, a floor stands 16.0 mm high at its fit-out; the worst is smallest, 11.0 mm, at 0.79 of the prediction, where level 40 standing high 0 days after its fit-out under creep ×0.70 balances level 33 standing low after thirty years under creep ×1.30.

The floor that is level on one date

Each floor of a tall concrete building is set high by the amount its columns are predicted to drop against the core, so that it arrives level. Counted in time, the drop does not peak at mid-height and stop at the roof: the worst floor of a forty-storey building is level 31, the roof moves 24 mm, and half the movement is still to come when the floors are fitted out. Set high by all of the prediction, a floor is level on one date thirty years away and 16 mm high at handover. With the creep known to ±30 per cent, setting it high by about four fifths of the prediction makes the worst floor's error 11 mm instead of 16. And none of it changes what the partitions see.

deflection · Differential shortening
Each new set of shims gives back the creep since the last. The creep force in one arm of a 200 m concrete building built a storey every week and fitted out over six months, with an outrigger at 149 m of 1.0 × 10⁸ kN·m a radian connected on day 385, over fifty years on a logarithmic axis: connected and left (dashed), adjusted once at 1 years, and adjusted at 1, 3 and 10 years, the arm's force falling to nothing at each adjustment; the design wind's 5.80 MN dotted. Left alone the arm ends at 3.48 MN. Adjusted once it ends at 2.58; adjusted at 1, 3 and 10 years it never holds more than 1.40 and ends at 0.91.

The arm that is reset by hand

An outrigger connected to a concrete building at topping out collects the core's and the columns' differential creep for fifty years, 3.48 MN in each arm against a design wind of 5.80. A damper lets the creep through and stops the wind, but it is a machine. The older answer is a joint closed with shims and opened every few years to take the creep out. Three visits, at one, three and ten years, hold the arm below 1.40 MN, and spaced like the creep they do it with roughly equal thicknesses of shim each time. Evenly spaced, the same three visits hold 2.48. And a visit that is missed costs exactly the creep it was there to remove.

structures · Outrigger
The survey knows the creep once most of the floors are set. The doubt about the creep of a 40-storey building cast a floor every seven days, its creep known to ±30 per cent, as the half-width of its 95% band, after a survey of every floor set by then — each read to a standard error of 1.0 mm — against the floor it is made after: from the survey alone (drawn at 100% where it is larger), and combined with the design's ±30%; beside them, the share of the building's floors still to be cast, which are all a survey can correct. The survey alone beats the design's doubt only after floor 25, with 38% of the floors still to cast; the combined doubt halves after floor 31, with 23% still to cast.

The survey that arrives after the floors

A tall building's lower storeys start shortening months before its upper floors are cast, so a survey every ten floors should tell the creep the building really has and let the floors still to come be set for it. It does tell it, to a millimetre's precision, after the twenty-fifth floor. By then most of the floors whose height it was meant to correct are already set, and the floor that ends furthest from level is the one no survey can help.

deflection · Differential shortening
Take the load off and the bars pull the concrete into tension. The concrete's stress at the moment the sustained load comes off, negative in tension, against the steel ratio. From 12 MPa, a column at 1% is left at -1.8 MPa, at 2% at -3.0, at 4% at -4.5. A tensile strength of 3 MPa is drawn; plain concrete returns to nothing, with no load and no stress.

The bars that take the column over

Steel does not creep and concrete does, so a reinforced column's concrete slowly hands its load to the bars, with nothing on the outside having changed. Bars carrying a seventh of the load on the first day carry more than a third after fifty years, the column shortens a quarter less than plain concrete would, and the column-to-core difference that a tower has to be built around can be closed or even reversed by the steel alone. And if the load is ever taken away, the bars that took it over pull the concrete into tension and crack it, with nothing on the column at all.

deflection · Differential shortening
The concrete's stress as the load comes off, quickly and slowly. The concrete's stress in a column with 2.0% of steel, loaded to 12 MPa at 28 days and unloaded after 10.0 years: at once, over a month and over a year. Held, it has fallen to 7.88 MPa as the bars took load. Unloaded at once it goes to −2.93; over a month, −2.62; over a year, −2.36. At 55 years of age all three stand near −2.20.

The column that cannot be unloaded slowly enough

A heavily reinforced concrete column that has carried its load for ten years has handed much of it to its bars, and when the load is taken away the bars, still squeezed, pull the concrete into tension. Taking the load off slowly lets the concrete creep under that tension as it arises, so it seems a slow enough programme could keep any column uncracked. It cannot. Slowness takes a fifth off the peak, and decades later every column arrives at the same tension however it was unloaded — past the concrete's strength above 3.3 per cent of steel.

deflection · Differential shortening
Visits when the force says, against visits on dates. The creep force in one arm of the late-connected outrigger over fifty years: re-shimmed at 1, 3, 10 years, never above 1.40 MN; re-shimmed whenever a load cell reads 1.40 MN, 3 visits, at 12 months, 4.1 years, 22.7 years; and whenever it reads 0.58 MN, a tenth of the design wind, 8 visits, the first three at 5 months, 7 months, 1.1 years.

The arm that calls for its own visit

An outrigger connected to a concrete building collects the core's and the columns' differential creep, and re-shimming its joint every few years lets that force go. Dates on a drawing are a guess at how fast the building will creep. A load cell in the joint replaces the guess: re-shim whenever it reads 1.40 MN and three visits, at one, four and twenty-three years, hold the arm there whatever the building does. A building that creeps 60 per cent more than predicted needs a fourth visit; the dated schedule lets it reach 2.30 MN. Holding a tenth of the wind takes eight visits, three in the first thirteen months, and a contractor who can come within weeks.

structures · Outrigger

Named alongside it

The objects these essays reach for when they reach for this one.

CreepConstruction sequenceOutriggerServiceabilityShrinkageRelaxationAxial shorteningCamberCoreTall buildingAge-adjusted effective modulusCompatibility

All concepts