Structural form

The thrust that never reaches the ground

Every arch on this site has ended at the same sentence — the foundation is where an arch is really decided. A tie changes the sentence without changing the arithmetic: the horizontal force is still there, still the same size, and it now closes on itself through a bar at deck level.

Assumes The hinge put in on purpose, The shape that carries itself, and the arch that is its reflection and One support too many, and what it costs to know.

An arch works by pushing outwards. That is not a side effect of the shape, it is the shape: the funicular of a uniform load is a parabola, and the horizontal component of the force running along it is constant and equal to wL2/8fwL^2/8f everywhere.

Which means the whole design of an arch is a question about what happens at the springings, and for most of the history of the form the answer was rock. A tied arch answers it differently. Run a bar between the two springings, let the thrust close on itself through that bar, and the bearings see nothing but weight — so the whole assembly reacts like a simply supported beam and can sit on two pads, or on a barge, or be lifted in overnight.

The tie is a redundancy, so its stiffness decides the thrust. Thrust and rib bending for a 60 m tied arch of 0.15 rise ratio, against the stiffness of its tie. Cut the tie and the structure is a curved simply supported beam, so the tie force is the one redundant and the force method gives it: with a rigid tie the answer is 2227 kN, within 1.0 per cent of the funicular wL²/8f, and the shortfall is the arch's own axial shortening. A real tie stretches 68 mm and returns 2166 kN — 2.7 per cent of the flexibility is the tie — and whatever thrust the arch does not get, it carries as bending: 760 kNm at 30 m. A tenth of the tie stiffness is not a tenth of the problem; it is a different structure.
Fig. 1 Thrust and rib bending for a 60 m tied arch of 0.15 rise ratio, against the stiffness of its tie. With a rigid tie the thrust is 2,227 kN, within one per cent of the funicular wL2/8fwL^2/8f; with the real tie it is 2,166, and the 61 kN of thrust the arch did not get arrives as 760 kNm of bending in the rib.

Which free body produced the number

Cut the tie. What is left is an arch on a pin and a roller — a curved simply supported beam, statically determinate, carrying the load entirely in bending because nothing is stopping the springings from spreading.

So the tie force is the single redundant, and the force method gives it directly. The tie stretches by XL/EAtX L/EA_t; the arch, pushed apart by a unit pair, spreads by ∫y2 ds/EI\int y^2\,ds/EI plus a smaller axial term; and the load, acting on the cut structure, spreads it by ∫M0y ds/EI\int M_0 y\,ds/EI. Setting the total movement to zero,

H=∫M0yEI ds∫y2EI ds+∫cos⁡2ϕEA ds+LEAtH = \frac{\displaystyle\int \frac{M_0 y}{EI}\,ds}{\displaystyle\int \frac{y^2}{EI}\,ds + \int \frac{\cos^2\phi}{EA}\,ds + \frac{L}{EA_t}}

With a rigid tie and an inextensible rib that expression returns wL2/8fwL^2/8f exactly, which is worth pausing on: the funicular thrust, arrived at from compatibility rather than from statics, with no assumption anywhere that the arch is carrying no bending. It comes out that way because a parabolic arch under a uniform load has M0∝yM_0 \propto y, and the integral in the numerator becomes the integral in the denominator times wL2/8fwL^2/8f.

Three flexibilities, and the tie is the smallest of them

The denominator has three terms, and reading their sizes is the whole design.

For the arch here the bending term is 1.11×10−31.11\times10^{-3}, the rib’s own axial shortening is 1.03×10−51.03\times10^{-5}, and the tie is 3.16×10−53.16\times10^{-5}. The tie contributes 2.7 per cent of the flexibility, and takes 2.7 per cent off the thrust.

That is the sense in which a tied arch is “nearly” a true arch, and it is also the trap. The tie is three times more flexible than the rib’s own shortening — the term nobody computes for a true arch either — so the ordinary shortcut of taking H=wL2/8fH = wL^2/8f is out by three per cent here, and everything it is out by lands in one place.

The shape the thrust would have if nothing gave at all is the funicular the load itself draws — a line that carries its load in pure compression and needs no bending stiffness anywhere. Every departure from it is paid for in moment, and the moment is the difference between the two lines. Of the three departures on this page, the rib’s own shortening is the one that has nothing to do with the tie, and it is worth pricing alone before the tie is put back.

A tenth of a per cent of the thrust is all of the moment. The thrust a two-hinged arch loses to its own axial shortening, against rise-to-span. The flexibility equation's denominator has two terms — ∫y²ds/EI for bending and ∫cos²θ ds/EA for shortening — and their ratio is about (15/8)(i/f)², the square of the radius of gyration over the RISE. The loss is a little more than that ratio, because the released rib also shortens under its own shear, and at the 10 per cent rise drawn it is 0.11 per cent of the thrust, which sounds like a rounding error and is not: a parabolic arch under a uniform load is funicular, so the rigid solution has NO crown moment at all, and the 0.11 per cent that the rib shortening removes from the thrust leaves 29 kNm behind. The correction that is a tenth of a per cent of the thrust is a hundred per cent of the bending. At a two per cent rise the loss is 2.6 per cent, because a shallow arch's thrust is enormous and its lever arm is not.
Fig. 2 The thrust a two-hinged arch loses to its own axial shortening, against rise-to-span. At the tenth-span rise drawn it is 0.10 per cent of the thrust, which reads as a rounding error and is not one: a parabolic arch under a uniform load is funicular, so the rigid solution has no crown moment at all, and the 0.10 per cent removed leaves 28 kNm of bending behind it. The correction that is a tenth of a per cent of the thrust is a hundred per cent of the bending. At a two per cent rise the loss is 2.6 per cent, because a shallow arch’s thrust is enormous and its lever arm is not.

Whatever thrust the arch does not get, it carries as a moment

That is the sentence the whole form turns on, and it is exact rather than approximate. The moment in the rib at any station is

M(x)=M0(x)−H y(x)M(x) = M_0(x) - H\,y(x)

so if HH were the funicular value the moment would be zero everywhere. It is not, and the shortfall multiplies the arch’s own ordinate: 61 kN of missing thrust times a 9 m rise gives 550 kNm at the crown, and the computed peak is 760 — more, because the rib with its tie cut is itself shortened by the part of its shear that runs along it.

Against the free moment wL2/8wL^2/8 of 20,250 kNm, that is 3.8 per cent — small, and not nothing. It is the moment the rib is sized for, and most of it exists only because the tie stretched 68 mm.

Make the tie ten times softer and the arithmetic runs away in exactly the way the expression predicts: the thrust falls to 1,736 kN and the peak moment rises to 4,625 kNm — a factor of six in the design moment for a factor of ten in a bar nobody looks at twice.

A slender tie is also worse than its area suggests, because a tie that sags between its hangers has a geometric stiffness as well as a material one and the geometric part is a function of the tension already in it. So the factor of ten is not a hypothetical: it is what a slack tie hands the rib.

The tie is a redundancy, so its stiffness decides the thrust. Thrust and rib bending for a 60 m tied arch of 0.15 rise ratio, against the stiffness of its tie. Cut the tie and the structure is a curved simply supported beam, so the tie force is the one redundant and the force method gives it: with a rigid tie the answer is 2227 kN, within 1.0 per cent of the funicular wL²/8f, and the shortfall is the arch's own axial shortening. A real tie stretches 548 mm and returns 1736 kN — 22.0 per cent of the flexibility is the tie — and whatever thrust the arch does not get, it carries as bending: 4625 kNm at 30 m. A tenth of the tie stiffness is not a tenth of the problem; it is a different structure.
Fig. 3 The same arch with a tie a tenth as stiff, and nothing else altered. The tie now stretches 548 mm rather than 68 and supplies 22.0 per cent of the flexibility rather than 2.7, so the thrust falls from the rigid-tie 2,227 kN to 1,736 — and the 491 kN the arch does not get arrives as 4,625 kNm of bending at midspan, against 760. A tenth of the tie stiffness is not a tenth of the problem. It is a different structure, and it is a structure whose rib is sized by a bar somebody specified without looking.

The rise ratio decides everything, including the tie

H=wL2/8fH = wL^2/8f is a division, and the thing being divided by is the rise. Halve the rise and the thrust doubles; and the tie, whose force is the thrust, doubles with it.

At the 0.15 rise ratio drawn — 9 m on a 60 m span — the tie carries 2,166 kN, which at 234 N/mm² is a bar of 9,300 mm². At a rise ratio of 0.075 the same load needs a tie of nearly twice that, and at 0.05 the tie is the largest member in the structure by a wide margin.

That is the trade a tied arch makes visible in a way a true arch does not. A shallow true arch delivers its enormous thrust to a foundation, where it is somebody else’s problem and is usually absorbed; a shallow tied arch delivers it to a bar, where it has to be paid for in steel at a rate proportional to 1/f1/f. The tie turns the rise ratio from an architectural decision into a priced one.

The tie is a redundancy, so its stiffness decides the thrust. Thrust and rib bending for a 60 m tied arch of 0.07 rise ratio, against the stiffness of its tie. Cut the tie and the structure is a curved simply supported beam, so the tie force is the one redundant and the force method gives it: with a rigid tie the answer is 4324 kN, within 3.9 per cent of the funicular wL²/8f, and the shortfall is the arch's own axial shortening. A real tie stretches 123 mm and returns 3889 kN — 10.1 per cent of the flexibility is the tie — and whatever thrust the arch does not get, it carries as bending: 2750 kNm at 30 m. A tenth of the tie stiffness is not a tenth of the problem; it is a different structure.
Fig. 4 The same 60 m arch at half the rise — 4.5 m, a rise ratio of 0.07 — with the same load and the same tie. The rigid-tie thrust rises from 2,227 kN to 4,324, and the tie carries 3,889 kN rather than 2,166, so the bar is nearly twice the area for no change anybody would call structural. The tie is now 10.1 per cent of the flexibility rather than 2.7, because the arch’s own bending flexibility fell faster than the tie’s did, and the rib’s design moment is 2,750 kNm rather than 760. Flattening an arch is cheap in a drawing and expensive in the one member whose force is the thrust.

The thrust the tie is sized against is not a number at one place. It is the same constant running along the whole of the arch, which is what makes the funicular the funicular.

A three-pinned arch, rise 1.8 on span 12. A three-pinned arch under a uniform load. One moment equation about the crown hinge gives a horizontal thrust of 450.00, with no stiffness and no assumption about the section. The thrust line lands on the axis everywhere, so there is no bending anywhere in the arch.
Fig. 5 The thrust itself, along the arch. Its horizontal component is constant — that is what makes the funicular the funicular — and the constant is wL2/8fwL^2/8f, which is the number the tie is sized for and the number a flat arch makes large.

The rib is still a column

Removing the foundation problem does not remove the other one. An arch rib carries its thrust as an axial compression along its whole length, and a slender member in compression along a curve is a column that happens to be curved.

For a tied arch the in-plane buckling question is nearly the same as for a two-hinged arch of the same geometry, because the tie holds the span in both. The out-of-plane question is not: a tied arch is often a pair of ribs leaning inwards with bracing between them, or a single rib with nothing at all, and out of plane it has the tie for company at deck level and free length above.

The governing check on most tied arches is therefore lateral rather than in-plane, which is not obvious from anything in the two-dimensional analysis above and is why the ribs on real ones lean towards each other.

There is a best rise, and it is not the tallest arch. The dimensionless buckling load wcr L³/EI of a two pinned parabolic rib, against its rise divided by its span. A flat arch buckles at almost nothing because the same load generates an enormous thrust in it; a very tall one buckles at less than its best because the rib has become long. The maximum is at f/L = 0.28, where the coefficient reaches 49.7, and the curve is flat enough on either side that anything from about 0.15 to 0.4 is within a tenth of it. At the rise drawn the coefficient is 39.5 and the mode is antisymmetric. Nothing here is read off a table: each point is the smallest eigenvalue of the rib's own stiffness against the geometric stiffness its own thrust produces.
Fig. 6 The rib as a column. The thrust the tie was introduced to contain is also the axial force that buckles the member carrying it, so a shallow arch is doubly punished: more thrust into the tie, and more compression in the rib that has to carry it round a flatter curve.

Which mode it goes in is the part that decides the bracing, and it is not the one the word buckling suggests.

The arch does not squash; it leans. The first two buckling modes of the same rib, drawn against its undeformed shape at an exaggeration of a few hundred. The first, at wcr L³/EI = 39.5, is antisymmetric: one half rises while the other falls and the crown moves sideways. The second, at 89.9, is symmetric — the whole rib settling. The two differ by a factor of 2.28, which is why an arch is braced against sideways movement of its crown rather than against the load it is carrying, and why a tied arch with a single hanger at midspan is doing nothing for the mode that governs it.
Fig. 7 The first two buckling modes of the same rib, drawn against its undeformed shape at an exaggeration of a few hundred. The first, at wcrL3/EI=39.5w_{cr}L^3/EI = 39.5, is antisymmetric — one half rises while the other falls and the crown moves sideways. The second, at 89.9, is symmetric: the whole rib settling. The factor of 2.28 between them is why an arch is braced against sideways movement of its crown rather than against the load it is carrying, and why a tied arch with a single hanger at midspan is doing nothing at all for the mode that governs it.

The load case the tie cannot help with

Under a uniform load the arch is close to its funicular and the tie is doing something simple. Put the load on half the span and neither is true.

M0M_0 is no longer proportional to yy, so no value of HH makes the moment vanish, and the best the tie can do is remove the average. The computed peak moment goes from 760 kNm to 2,820, at the quarter point rather than the crown, and the thrust halves to 1,083 kN because half the load produces half the numerator.

A tied arch is therefore designed by its unsymmetric load case, not by its full one — which is the same discovery a continuous beam makes about pattern loading, reached from the other direction. The full load is the case the shape was chosen for, and the case the shape was chosen for is never the one that governs.

The structural response is the network arch: hangers that cross each other instead of hanging vertically, so that an unsymmetric load is carried by a truss action between rib and tie rather than by bending in either. That converts the problem from one about moment into one about which hangers go slack, which is a different and more tractable question.

It is worth being clear about what the design quantity then is. A structure tuned to one load pattern is being asked about all of them, and the envelope of what it must carry is not a state the structure is ever in — the 2,820 kNm at the quarter point and the 760 at the crown belong to two different arrangements of the same load, and no single analysis produces both at once.

The comparison that is the reason for the whole form

The expression for HH prices something else, for free: a support that moves.

For a true two-hinged arch, a spread δ\delta at the springings takes δ\delta divided by the arch’s own flexibility off the thrust. For the steel rib here that is 22 kN for a 25 mm spread — one per cent, and no cause for concern.

Make the same arch a hundred times stiffer, which is what building it out of stone does, and the same 25 mm takes 100 per cent of the thrust away. The arch does not lose a per cent of its thrust; it stops being an arch.

That is the finding worth carrying furthest here, and it is the opposite of the intuition. Vulnerability to foundation movement is not a property of slenderness — it belongs to stiffness, because a stiff structure develops large forces for small movements, and the force it develops for a movement it did not want is the force it loses.

A line of thrust, and the masonry it has to stay inside. An arch ring of 10% of the span in thickness, rising 30% of the span, under its own weight as a uniform load. Any horizontal thrust between 4.29 and 5.85 puts a line of compression entirely inside the masonry, so the arch stands — and which of them it actually takes is not decided by statics. The two extremes are drawn: the minimum-thrust line, which rides high at the crown and low at the haunches, and the maximum-thrust line, which does the opposite.
Fig. 8 What losing the thrust looks like in a masonry arch. The thrust line has to stay inside the stonework, and reducing HH raises it at the crown until it does not. This is the mechanism by which spreading abutments open the cracks that every old arch bridge has, and it is a stiffness effect rather than a strength one.

And a tied arch is immune to all of it. The tie holds the span, the bearings are free to slide, and a foundation that moves 25 mm — or 250 — changes nothing at all in the structure above it. That is the argument for the form on soft ground, and it is a different argument from the one about being able to lift it into place.

The tie can be jacked, and the rib moment disappears

The 760 kNm has two sources. The tie stretched 68 mm, and that took 61 kN of thrust; the rib itself shortened, and that took another 23 kN, which even a tie that could not stretch at all would have lost. Shorten the tie by enough and both go.

That is not a rhetorical move; it is a construction operation, and the arithmetic for it is already on this page. An imposed shortening e0e_0 of the tie raises the thrust by ΔH=e0/∑f\Delta H = e_0/\sum f, so restoring the 84 kN between the real thrust and the funicular one takes

e0=ΔH∑f=84,400 N×1.149×10−3 mm/N=97 mm.e_0 = \Delta H \sum f = 84{,}400\ \text{N} \times 1.149\times10^{-3}\ \text{mm/N} = 97\ \text{mm}.

Seventy of those millimetres undo the tie’s own stretch — the same equation read in the opposite direction — and the other twenty-seven undo the rib’s. Jack the tie 97 mm shorter before locking it off, and the arch sits at its funicular thrust of 2,250 kN with no bending in the rib at all under uniform load.

The price is 3.9 per cent more force in the tie, which is 3.9 per cent more tie. The return is the whole of the rib’s symmetric design moment. That is an unusually good trade, and it is why the tie of a real arch is very often stressed rather than merely bolted — the same operation a bridge closure uses, choosing which self-stress state a redundant structure will carry rather than accepting whichever one fit and sequence hand over.

Two things bound it, and both should be said in the same breath as the offer.

It does nothing for the case that governs. The half-span moment of 2,820 kNm is unsymmetric, so no value of HH removes it — jacking cancels the part of the moment proportional to yy and leaves the rest untouched. A rib designed for 2,820 is not made smaller by a jack.

And the 97 mm does not stay 97 mm. A steel tie relaxes slightly, a concrete deck acting as the tie creeps considerably, and the jacking is done at whatever temperature the day supplied. So the imposed shortening is a quantity with a tolerance and a drift, and the design has to be safe across both — which is the ordinary condition of every prestressed structure and the reason the transfer state is checked as its own load case.

Sun on the rib and shade on the tie

A tied arch on sliding bearings expands freely, so a uniform temperature change puts no force anywhere in it — the whole assembly grows and the bearings take up the movement. The case that does something is the differential: the rib in the sun above the deck, the tie in the shade beneath it.

Fifteen degrees of difference over 60 m is an imposed length change of

e0=α ΔT L=12×10−6×15×60,000=10.8 mme_0 = \alpha\,\Delta T\,L = 12\times10^{-6} \times 15 \times 60{,}000 = 10.8\ \text{mm}

and it goes through the same expression as the jack:

ΔH=10.81.149×10−3=9.4 kN\Delta H = \frac{10.8}{1.149\times10^{-3}} = 9.4\ \text{kN}

— 0.43 per cent of the thrust, and 84 kNm of rib moment against the 760 the tie’s own stretch produces. Even at thirty degrees of differential it is under a per cent.

The reason it is so small is the same reason the tie mattered so little in the first place: the denominator is dominated by the arch’s bending flexibility, 1.11×10−31.11\times10^{-3} against the tie’s 3.16×10−53.16\times10^{-5}. The structure is soft against spreading, so an imposed movement costs it almost nothing.

That is the finding of the previous section arriving from the other side, and it is worth having both halves in view at once. A flexible arch loses a little thrust to its tie and shrugs off temperature and settlement; a stiff one keeps its thrust and is destroyed by a movement of the same size. Flexibility is what converts an imposed displacement into a small force, and stiffness is what converts it into a large one — the whole of what an imposed deformation does is decided by the stiffness of whatever is resisting it, and never by the size of the movement alone.

Where the model stops

The analysis is linear and the geometry is the undeformed one. A tie stretching 68 mm on a 60 m span lowers the crown, which reduces the rise, which raises the thrust required, which stretches the tie further. The second-order correction is a per cent or two here and grows with the tie’s flexibility; a network arch with a slender tie deserves a geometrically nonlinear check.

The hangers are ignored entirely. They are treated as delivering the deck load to the rib as a smooth line load, which is right for many closely spaced hangers and wrong for the eight or ten a real bridge has. Discrete hangers put a sawtooth of local bending into both rib and tie, and a hanger that goes slack changes the structure rather than the loading.

The tie is treated as an axially loaded bar. On most tied arches it is the deck, which is also carrying traffic in bending and is far stiffer than a bar of the same area — a deck that stiffens the structure it is hung from is the whole of the stiffened-girder argument, and it applies here with the tension added.

And the rib is prismatic. Real ribs are deeper at the springings, which raises ∫y2/EI\int y^2/EI where yy is smallest and changes the numbers by a few per cent in a direction the integral will take without complaint.

The member with no second chance

The tie carries 2,166 kN in tension, permanently, and it is the only member in the structure whose loss is unsurvivable. Everything else in a tied arch has an alternative path; the tie has none, because it is the alternative path — it exists to close a force that would otherwise go to the ground.

Two consequences follow, and neither is in the analysis.

It is a fatigue detail rather than a strength one. A tie under permanent tension with traffic on the deck sees a stress range at every axle, at a connection to the arch springing that is one of the most heavily worked details on any bridge. The load that never came near failing anything is the governing case for it, and the calculation that decides its size is a count of cycles rather than a strength check.

And it is made of several ties. Real tied arches use multiple strands, or a box girder acting as the tie, or a deck in parallel with a bar — not because the arithmetic asks for it, but because a single-load-path member carrying two hundred tonnes for a hundred years is a category of thing that engineering does not build. That decision is invisible in every equation on this page.

Three details, and no material anywhere on the plot. Stress range against cycles to failure for three detail categorys — 160, 90, 36 N/mm² at two million cycles. The lines are parallel because they share a slope of three, and the spread between them is a factor of 4.4 in stress and therefore 88 in life. Nothing on this plot depends on the strength of the steel: the same detail in a grade twice as strong lies on the same line. At a stress range of 80 N/mm² the lives are 160: 3.5e+7, 90: 2.8e+6, 36: 1.8e+5 cycles. The knee in each line is the constant-amplitude limit, past which the slope becomes five.
Fig. 9 The curve the tie is really designed by. A member at a permanent tension with a small live component is exactly where a fatigue check overtakes a strength one, and the tie of an arch is the clearest example of it in this collection.

What the pictures cannot show

The thrust in the first figure is a number on an axis. What it is on site is a force of 2,166 kN — two hundred and twenty tonnes — running along a bar at the deck, in tension, permanently, for the life of the structure.

That is a member with no redundancy. Every other force in the arch has somewhere else to go if a member is lost; the tie does not, and a tied arch with a single tie is a structure with a single point of failure that no diagram on this page draws attention to. Real ones have multiple ties, or a tie made of many strands, or a deck acting as the tie in parallel with it — and the reason is not visible anywhere in the analysis, because the analysis has no term for what happens if the answer stops existing.

The assumption the figure rests on

The tie is assumed to be straight, and to stay straight.

It is the one assumption here that gets broken routinely. A tie at deck level carries the deck’s own weight between hangers, so it sags; sag reduces its axial stiffness by the geometric mechanism a cable’s stiffness is made of; and reduced axial stiffness raises the flexibility term that this essay has shown is the whole design. On a bridge where the tie is the deck, the sag is negligible and the assumption is safe. On a roof truss where the tie is a slender rod spanning forty metres between two ends, it is not — and the honest model is not a bar with a lower modulus but a cable, whose stiffness depends on the tension the analysis is trying to compute.

Which is the last thing the form is worth stating as. A tied arch is a cable turned upside down with a bar joining its ends, and the bar is doing exactly what an anchorage does for the cable: holding the two ends apart at a fixed distance while the shape carries the load. Everything on this page follows from how nearly fixed that distance is.

What this makes readable

Essays that name this one as a prerequisite.

Named alongside this one

Essays reaching for the same objects. Nobody chose these; they are what the concept index makes visible.

What links here

Every essay whose body links to this one.

The objects this essay names

Each one links to every other essay that touches it.

ArchAxial shorteningBending momentCompatibilityDeckFlexibilityForce methodFunicularHangerLoad arrangementRedundancySupport settlementThrustTieTied arch