Field

Structural form

Trusses, cables and arches: the shapes that carry load by geometry rather than by bulk.
A Pratt truss of 6 panels. A Pratt truss under equal panel-point loads. The joint equilibrium equations were assembled and solved; 10 members came out in tension, 9 in compression and 2 carrying nothing.

The triangle that cannot fold, and everything built out of it

A square of pinned bars is a mechanism. A triangle is not, and that single fact is the reason trusses exist and the reason they look the way they do.

The cable and the arch are the same curve. The shape a cable takes under a uniform load is a parabola, and it carries that load in pure tension. Reflected, the identical curve carries the same load in pure compression, which is what an arch is.

The shape that carries itself, and the arch that is its reflection

Hang a chain and it takes the one shape that carries its load in pure tension. Turn the shape upside down and it carries the same load in pure compression. That is what an arch is.

Chord force against truss depth. The force in a truss chord for a fixed bending moment, against the depth of the truss. The relationship is a reciprocal: the chords form a couple whose lever arm is the depth, so a shallow truss pays for it steeply.

Depth is the cheapest strength there is

Doubling the depth of a truss halves its chord forces without adding a gram of material to the chords. Nothing else in structural design is that cheap, and almost every structure has already spent it.

The funicular polygon for five loads. The shape a string takes under 5 point loads, with a vertex at every load and a constant horizontal component of 27.9 throughout. The end segments carry the most — 38.6 against 28.0 in the flattest one — because they are steepest.

The polygon that finds the shape

A hanging string under five loads has no smooth curve in it — it has five vertices and six straight segments, and every slope in it is a running sum divided by one number.

A three-pinned arch, rise 2.6 on span 9. A three-pinned arch under a uniform load. One moment equation about the crown hinge gives a horizontal thrust of 23.37, with no stiffness and no assumption about the section. The thrust line lands on the axis everywhere, so there is no bending anywhere in the arch.

The hinge put in on purpose

An arch with two pinned feet cannot be solved by statics. Add a third hinge at the crown — deliberately weakening it — and the whole structure falls out of one moment equation.

A portal frame swaying under 20 kN. A portal frame pushed sideways, solved by the stiffness method because statics cannot divide the load between two columns. The base shears come out at 10.0 and 10.0 and add to the applied 20; the peak moment is 22.2. The sway is drawn hugely exaggerated, and the moment diagram is plotted on each member's tension face.

The frame that leans, and what stops it

A rectangle of pinned bars folds flat. Make the corners rigid instead of adding a diagonal and it does not — which buys an unobstructed opening and costs bending in every member of it.

A line of thrust, and the masonry it has to stay inside. An arch ring of 9% of the span in thickness, rising 28% of the span, under its own weight as a uniform load. Any horizontal thrust between 3.85 and 5.23 puts a line of compression entirely inside the masonry, so the arch stands — and which of them it actually takes is not decided by statics. The two extremes are drawn: the minimum-thrust line, which rides high at the crown and low at the haunches, and the maximum-thrust line, which does the opposite.

The line that must stay inside

A masonry arch does not stand because its shape is right. It stands because some line of compression can be drawn inside the stonework — any one will do, and there are infinitely many to choose from.

The joints are not pins, and this is what that costs. A 4-panel Pratt truss solved twice on the same stiffness matrix: once with a moment release at every member end, which is the pin-jointed idealisation, and once with the joints continuous, which is what welding them produces. The axial forces are the same to within a per cent; the bending the second solution adds is worst in member 0, where the bending stress reaches 24.3% of the axial stress. Members are shaded by that ratio.

The joint that is not a pin

Every truss drawn as a line diagram is analysed as though its joints were frictionless pins. Almost none are. The bending that follows is called secondary, which is a claim about size — and the claim is checkable.

Take that one away and the load finds another route. A 6-panel pratt truss under 20 kN at each top node, before and after member 2 is removed. The load redistributes. The worst-affected survivor now carries 2.03 times what it did, and four members that carried nothing before are now working. Whether that is survival depends on how much spare capacity was there, which is a different question from whether the frame was strong enough.

The structure that survives losing a member

Every check in this collection asks what a structure carries. None of them asks what is left when part of it is gone — and two frames with the same members, the same weight and the same factor of safety can answer that question completely differently.

A two-way slab is a one-way slab as soon as it is not square. The share of the load carried by the strips spanning the short way, against the ratio of the sides. The two families of strips cross at the centre and must deflect equally there, and a strip's deflection goes as the fourth power of its span — so at a ratio of 1.33 the short strips already take 76% and at 2 they take 94%. The panel drawn here is 6 × 8 m, a ratio of 1.33, and its short strips take 76.0%. Two-way action is worth having at a ratio of one and worth almost nothing by two.

The slab that spans both ways

A panel supported on four sides sends its load in two directions at once, and the share is decided by a fourth power — so a panel a third longer than it is wide has already stopped being a two-way slab in any useful sense. What it does at collapse is a different calculation with a different answer.

Two shapes that are the wrong way up for each other. Deflected shapes of a 20-storey building under a uniform wind, drawn to the same scale. The wall alone bends: its shape is flattest at the base and steepest at the top, reaching 146 mm. The frame alone shears: it is steepest at the base where the storey shear is largest, reaching 140 mm. Tied together at every floor they reach 58 mm — less than a quarter of either, and less than the 72 mm two springs in parallel would give, because each is stiff exactly where the other is not.

How a tall building stands still

A shear wall bends and a framed tube shears, and the two deflected shapes are the wrong way up for each other. Tie them together at every floor and the pair is stiffer than the sum of their stiffnesses — because near the base the wall holds the frame back and near the top the frame holds the wall.

The props decide where the stress ends up. Bottom-fibre stress in the steel of a 12 m composite beam carrying 12 kN/m of wet concrete and 18 kN/m afterwards. Unpropped, the bare steel takes the first stage alone and reaches 292 MPa; propped, the finished composite section takes everything and reaches 186 MPa — a ratio of 1.57. 62% of the unpropped beam's final stress was locked in before the slab was structural at all. The deflections differ by 1.73 times for the same reason, and no drawing of the finished beam distinguishes the two.

The structure that was never complete

Every analysis in this collection is of a finished structure loaded once. Real ones are built in pieces, and each piece carries whatever was present at the moment it became structural — so the stress in a member depends on when it arrived, which appears nowhere on any drawing.

The further it deflects, the harder it pulls back. Total load against midspan sag for a 30 m cable of 1000 mm² prestressed to 500 kN, carrying 5 kN/m. The cubic H³ − T₀H² − w²L²EA/24 = 0 was bisected at every point of the curve, so the sag at the full 150 kN is 0.740 m rather than the 1.125 m the flat-cable formula WL/8T₀ gives — the straight dashed line, which is the tangent to this curve at the origin and nothing more. Its slope is the initial stiffness 8T₀/L = 133.3 kN/m; at the marked point the tangent has reached 341.2 kN/m, 2.56 times as stiff, and the horizontal component of the tension has risen from 500 kN to 760 kN. Nothing about the steel changed. The geometry got better at the job.

The stiffness that comes from the shape

A cable has no bending stiffness whatever, and it still holds up a roof. What resists the load is the change of its own geometry, so its stiffness is a function of the tension already in it — and prestress buys stiffness that no change of material could.

The hoops change their mind at an angle no proportion chose. The two membrane forces of a spherical dome of radius 30 m under 3 kN/m² of surface, taken from the crown to a base at 60°. The free body for the meridional force is the cap above a cone of half-angle φ, and vertical equilibrium of it gives N_φ = −wR/(1 + cos φ) directly: -45.0 kN/m at the crown falling to -60.0 at the base, compression everywhere. Equilibrium normal to the surface then gives the hoop force, which starts at -45.0 kN/m and reaches 15.0 — it changes sign, and the angle at which it does was found here by bisecting N_θ rather than quoted: 51.827292°. Setting N_θ = 0 gives cos²φ + cos φ − 1 = 0, so cos φ is (√5 − 1)/2, the reciprocal of the golden ratio — an identity the bisection reproduces to nine decimals, which is worth seeing done rather than taken on trust, because it is too pretty to be believed on sight. Below that parallel the hoops are in tension, which masonry has none of, and that is where every old dome is cracked.

The surface that carries by being curved

A flat plate spends its thickness on a lever arm of a few millimetres. Curve the same sheet and the load is carried in the surface itself, at a thirtieth of the thickness — and the entire bill is presented at the edges.

The depth is decided by how far it moves, not by what it can carry. A column carrying 6000 kN landing 3 m into a 12 m transfer member. The free body is the member itself, cut under the column: M = P·a(L − a)/L = 13500 kNm, with 4500 kN of shear on one side of the cut and 1500 on the other. At an allowable stress that moment asks for 1.94 m of depth — the dashed outline — and keeping the settlement it causes inside the floors' own bending asks for 2.55 m, which is the member drawn solid. 31% more depth is bought by nothing the strength calculation can see. The depth grows as √(P·a), so four times the load is exactly twice the depth, and depth in a transfer member is a storey nobody occupies.

The column that stops

A load path that runs straight to the ground costs almost nothing. Interrupting one costs depth in proportion to the square root of the load times the distance it is moved — and the interruption's own deflection becomes the settlement of everything standing on it.

The shear goes round the corner instead of across it. A 6-panel Vierendeel girder, 12 m by 1500 mm, under 100 kN at mid-span. There is no diagonal in it, so each panel's 50 kN of shear is carried as bending in the chords: the curves drawn along them are the chord moments, and every one passes through zero at the middle of its own panel. The local moment is the panel shear times the panel length over four, 25.0 kNm, and it adds to an axial force of 200 kN from the global moment at the same point. The girder deflects 6.20 mm against 3.18 mm for the same members triangulated — 1.95 times — and 68% of that movement is chord bending that a diagonal would have removed entirely.

The truss with no diagonals

A rectangle without a diagonal is a mechanism, so a Vierendeel girder makes its corners rigid instead. The shear a diagonal would have carried as axial force now travels as bending in the chords, and bending is a far more expensive way to move a force.

A cable alone goes to a kink, and a kink is not a road. A point load of 1000 at mid-span of a 900 m suspended deck. The upper shape is the cable with no girder at all: two straight lines meeting under the load, because a cable takes the funicular shape of whatever is on it and the funicular of a point load is a kink — 0.0083 radians of it here. The lower shape is the same cable with the girder present, peaking at 1.125 against the bare cable's 1.873. The girder is not carrying the load — it takes only 17% of it — it is spreading it, over a characteristic length of √(EI/H) = 183 m, and what reaches the cable is spread over that length rather than arriving at a point.

The deck is not there to carry the load

A cable takes the shape of whatever is on it, which is exactly the problem — under a point load its shape is a kink, and a kink is not a road. The stiffening girder exists to spread the load until what reaches the cable is something the cable's own shape is right for.

The same sheet, twice, and a factor of ten thousand. A 3000 mm developed width of 3 mm sheet, covering 2400 mm in plan — so the legs sit at 36.9° and the fold is 300 mm deep. Flat, its second moment about its own mid-plane is 6750 mm⁴, which spans nothing. Folded, it is 67.50×10⁶ — 10000 times as much, which is exactly the depth in thicknesses squared. The material is identical, the plan cover has fallen by 20%, and the only thing that changed is where the material sits. What limits it is buckling of the leg: at this leg length the flat between the folds goes at 27 N/mm², well below the steel's 275.

Folded until it spans

A flat sheet has a second moment of area of B·t³/12 and will not span anything. Folded, the same material has B·t·h²/12, and the gain is exactly the fold depth over the thickness, squared — a ratio with no material in it and no width in it.

A frame with no plane to be drawn in. The tetrahedron, solved: three equations at every free joint, one axial force in every member. Members drawn heavy carry more; tension and compression are separated by the sign that came back from the solve rather than by inspection. The count is m + r = 12 against 3j = 12, which makes it exactly determinate, and joint equilibrium closes to 1.8e-15.

Three equations at every joint

A plane truss is determinate when m + r = 2j. A space frame needs 3j, and that one changed digit is why a cube of twelve bars is six mechanisms short while looking perfectly solid — and why every three-dimensional frame ever built is made of triangles in several planes at once.

Two centres, and the distance between them is a torque. A storey 30 by 18 m with its walls drawn heavy, pushed in one direction by 1000 kN. The force acts through the centre of mass and the storey turns about the centre of rigidity — the stiffness-weighted centroid of the walls, at x = 15.0 m — and the distance between the two is an eccentricity of 0.00 m before the 5% that has to be assumed anyway. The table below the plan splits each wall's force into its direct share and its torsional one. Torsion relieves the walls near the centre of rigidity and loads the far ones, so the wall in trouble is not the wall carrying the most: west wall is asked for 8% more than its direct share, and the walls at right angles to the push carry 19 kN each with nothing applied along them at all.

The corner that moves most

A lateral force is shared out in proportion to stiffness only if it passes through the centre of rigidity, which is not the centre of the plan and not the centre of mass. The distance between the two is a torque, and the wall that pays for it is the one furthest away and carrying least.

Whether the floor shares the load out by stiffness or by area. The share of a uniform storey force taken by each of three equally stiff walls, against the stiffness of the floor plate that spans between them. A plate far stiffer than the walls translates almost rigidly, every wall deflects the same and the share is the ratio of stiffnesses — 60% to the middle wall here, the same as everyone else. A plate far softer than the walls behaves as a continuous beam over them and the middle wall takes 33%. Neither end is the tributary-area answer of 50%, which assumes a plate that is both soft and discontinuous over the wall, and which nothing here ever reaches.

The floor is a beam lying down

A floor plate spans horizontally between the walls that resist a lateral load, carries a distributed inertia load, and has chords, a web and a span-to-depth ratio like any other beam. Its stiffness decides whether the walls share the load by their stiffness or by the area of floor nearest them — and the familiar tributary answer turns out to be neither limit.

Two null spaces of one matrix, and the count is their difference. Two pin-jointed frames, each with the forces it can carry with nothing applied to it drawn on its bars — tension one colour, compression the other, thickness in proportion. That force set is the null space of the equilibrium matrix; a mechanism is the null space of its transpose; and Maxwell's count b + r − 2j is the difference of their dimensions and knows neither of them separately. A square with both diagonals has s = 1 and m = 0. Two bars in a straight line has s = 1 and m = 1 with a count of 0, so the count is satisfied by a frame that both folds and can be prestressed — and the prestress stiffness is positive, which is why a tensioned pair of collinear bars is stiff at all.

The forces that are there with nothing applied

Maxwell's count is the difference between two dimensions, and it knows neither of them separately. A frame can satisfy it exactly and still both fold and be prestressable — and when it does, the second of those is what stops the first.

A couple applied to the core, and two columns to make it. A 20-storey core with one outrigger at 59% of its height. The arm is stiff in bending and the perimeter columns are stiff in tension and compression, so between them they resist the core's rotation at that level — a couple of 35283 kNm here, carried as a 294 kN pair in the columns at 120 m centres. The compatibility is one equation: the core's rotation at that level, less what the couple takes back out of it, equals the rotation the arm and its columns allow. The top drift falls from 360 mm to 74, which is 80% of it, and the base moment from 73500 to 38217 kNm. The deflected shape is drawn hugely exaggerated: the real top drift is about one five-hundredth of the height.

The arm that makes the columns work

The perimeter columns of a tall building are already there, already carrying gravity, and already the furthest thing from the centre. They take almost none of the overturning, because a floor slab transmits shear and not moment — and one storey-deep arm at the right height changes that by nearly a half.

Every path to the ground goes through the link. A braced bay 8 m by 4 m whose two diagonals stop 800 mm apart instead of meeting. The storey shear reaches the ground through the diagonals, and the vertical components they deliver to the beam have to pass through the segment between them: the link carries 47% of the applied shear as a shear force, at a lever arm short enough that its ends reach 0 kNm while the rest of the beam carries 0. The deflected shape drawn is the solved one, magnified — the real drift under this load is 0.008 mm. Everything outside the link is designed to stay elastic while the link is yielding, which is what makes the mechanism a choice rather than a hope.

The part that is meant to be weak

A braced frame is stiff and has nowhere to yield. A moment frame yields everywhere and is soft. Move the two diagonals a metre apart along the beam and the whole storey shear has to pass through the segment between them — which keeps most of the stiffness and puts every yielding in one member the designer chose.

The split is where buckling puts it. A branching column carrying 400 kN to two points 3.0 m apart, over 9.0 m. Every member is drawn at the thickness it needs: the area is the larger of N/σ and what Euler asks of a strut of that length, and 3 of 3 members here are sized by buckling rather than by strength. The split sits at 57% of the height, which is where the total volume is least — 51% less than the fan of straight struts that carries the same load with the same stresses.

The tree that strength does not ask for

A branching column carries a roof on many points and reaches the ground on one. Size every member by its stress and the optimum tree turns out to have no trunk at all — the best answer is a fan of straight struts from the base. Put buckling in and the trunk appears, at 57 per cent of the height.

The corner columns take what the middle ones did not. Axial stress in the columns across one flange face of a 30 by 40 m framed tube, at the base. Plane sections says the flat line: every column on the face at the same distance from the neutral axis, therefore at the same stress. The solved distribution is the curve — 69.4 N/mm² at the corner against 18.2 in the middle, a ratio of 3.81. The middle columns lag because the only route the axial force has into them is the in-plane shear of the spandrel frame, bay by bay from the corner. The face is carrying its resultant on an effective width of 51 per cent, and the tube deflects as though its second moment were 72 per cent of the gross.

The corner columns take more than their share

A framed tube is a hollow cantilever, and a hollow cantilever's flange ought to be uniformly stressed. It is not, and the reason is that the only route the axial force has into a column in the middle of a face is the in-plane shear of the frame — one bay at a time, from the corner inwards.

The tie is a redundancy, so its stiffness decides the thrust. Thrust and rib bending for a 60 m tied arch of 0.15 rise ratio, against the stiffness of its tie. Cut the tie and the structure is a curved simply supported beam, so the tie force is the one redundant and the force method gives it: with a rigid tie the answer is 2227 kN, within 1.0 per cent of the funicular wL²/8f, and the shortfall is the arch's own axial shortening. A real tie stretches 68 mm and returns 2166 kN — 2.7 per cent of the flexibility is the tie — and whatever thrust the arch does not get, it carries as bending: 760 kNm at 30 m. A tenth of the tie stiffness is not a tenth of the problem; it is a different structure.

The thrust that never reaches the ground

The arches so far have all ended at the same sentence — the foundation is where an arch is really decided. A tie changes the sentence without changing the arithmetic: the horizontal force is still there, still the same size, and it now closes on itself through a bar at deck level.

The windward guy tightens, the leeward one gives way. A 120 m mast on three guy levels, at a wind of 3 N/mm, with the deflection drawn 0.54 times its true size. The guys start at 160 kN each and end at 259 against 95, 299 against 83, 221 against 112 kN. The leeward guys still carry a real force — the lowest keeps 28 per cent of its partner's tension — and supply almost none of the restraint, because their tangent modulus has fallen to 54 per cent of the steel's. The mast top moves 100 mm, its worst bending moment is 554 kNm at 40 m, and it is carrying 801 kN of axial load that nothing but the guys put there.

Held by something that goes soft

A guy is a cable, so it has no stiffness of its own — what resists a mast's movement is the guy's geometry changing, and how much of that there is depends on the tension already in it. Wind pushes the mast towards the leeward guy, which is the one losing tension.

A fan, and where its forces go. Half a cable-stayed bridge: a tower 70 m above a deck, 12 stays reaching out over 200 m, and a uniform 200 kN/m on the deck. Each stay is drawn at a weight proportional to the force in it, from 3427 kN at the innermost to 10090 kN at the outermost — the outer stay carries the same vertical share and is far flatter, so it carries far more. The deck's shading is its own accumulated compression, 61905 kN at the tower, which is 1.55 times the load being lifted and is the horizontal half of every stay force added up. Nothing in this drawing is a catenary: every stay is straight and every one of them is a spring.

The cable that is a spring

A suspension bridge's cable is a funicular — it takes the shape the load gives it, and the deck's job is to make the load one that shape is right for. A stayed deck is not that at all. Its cables are straight, each reaches the deck at one point, and every one of them behaves as an inclined spring.

Held up by a pressure nobody can feel. An air-supported roof of 60 m span and 9 m rise. The membrane has no bending stiffness whatever, so the only thing that can hold it in tension is a pressure difference, and the pressure has to exceed the load per unit plan area and nothing else: 0.25 kN/m² of fabric plus 0.6 of snow is 0.85 kN/m², so 1.19 kN/m² does it — 1190 pascals, which is 1.17 per cent of an atmosphere and 121 millimetres of water. Ears do not notice it. A door does: at 2.1 kN on an ordinary leaf, the building needs an airlock rather than a handle. And the whole of it arrives at the foundation as 3365 kN of uplift — 17.9 kN on every metre of perimeter — which is the bill the pressure's smallness conceals.

Held up by the air inside

A membrane has no bending stiffness at all, so the only thing that can hold it in tension is a pressure difference. The pressure needed to hold up a roof is smaller than the pressure a closed door makes — and the same pressure arrives at the foundation as hundreds of tonnes of uplift.

The line, and the stone it has to stay inside. A masonry pier 9 m high, 1.6 m thick at the top and battered 12% on its outer face, taking a thrust of 40 kN per metre of run at 25° to the horizontal. The line drawn through it is the locus of the resultant on each horizontal cut: everything above the cut is the free body, and the resultant's position is the moment divided by the vertical force. The dashed pair is the middle third, inside which no tension is implied anywhere on the joint. The line stays inside the stone throughout and reaches the base at 0.503 m from the centre, against a half-width of 1.34 m — but outside the middle third, so part of the base joint is open and the toe is carrying a triangle. Nothing about the strength of the masonry appears anywhere in this figure, and that is the point.

The weight that makes it safer

Every load in this collection makes a structure worse. A pinnacle does not. A masonry pier fails when the line of compression leaves the stonework, and adding weight at the top rotates that line back towards the vertical without adding anything the pier cannot carry — so the stone is not being strengthened, it is being aimed.

Four ways to make a cell resist being racked, and one that is not one. One cell of a grid shell under the membrane shear it has to carry, by the four mechanisms available for carrying it, with the racking each produces over a 30 m span under 1.2 kN/m² of asymmetric load. A serviceability limit of span/250 is 120 mm. Four pin-jointed bars in a quadrilateral have no in-plane shear stiffness whatever — the cell folds, and the answer is not a large deflection but a mechanism. Rigid nodes carry the shear by bending the members over a cell, which smears to 12EI/s³ and comes to 0.35% of what a continuous sheet of the same stretching stiffness gives: 1205 mm, ten times the limit. One diagonal per cell, or a third member direction, carries it axially instead and lands within a factor of two of the sheet. That is the whole difference between a grid shell and a row of arches.

A shell only if the grid takes shear

A curved surface carries load in its own plane at a fraction of the material a flat one needs, and every gridshell ever built is an attempt to buy that with members instead of with a surface. The attempt succeeds or fails on one property nobody draws — whether four bars meeting at a corner can resist being racked — and a pinned quadrilateral grid cannot resist it at all.

Three ways to move the same column, and they are not close. The same 2000 kN moved 3 m across 14 m, built three ways and drawn to one scale. The deep beam is 1.14 m of concrete, 24.1 tonnes, and settles 60.6 mm in the long term. The storey-deep truss takes the same moment as a couple at 3.6 m centres, so its chords carry M/h and it weighs 2.6 tonnes — a fifth of the beam — while settling 15.8 mm, and it does not creep. The wall is 72.8 tonnes and hardly moves at all, 1.71 mm, of which 36% is shear rather than bending — which is what a member as deep as it is long always does, and is why beam theory does not describe one. A wall as a deep beam is the stiffest of the three by a factor of 35.4.

The same span, four ways

A beam, a truss, an arch and a cable can all cross the same gap under the same load, and the choice between them is usually described as a matter of judgement or of taste. It is neither. Each carries the load by a different mechanism, each mechanism has a different exponent, and an exponent decides the ordering at every span rather than at some spans.

The corner columns take what the middle ones did not. Axial stress in the columns across one flange face of a 36 by 36 m framed tube, at the base. Plane sections says the flat line: every column on the face at the same distance from the neutral axis, therefore at the same stress. The solved distribution is the curve — 78.5 N/mm² at the corner against 13.4 in the middle, a ratio of 5.88. The middle columns lag because the only route the axial force has into them is the in-plane shear of the spandrel frame, bay by bay from the corner. The face is carrying its resultant on an effective width of 45 per cent, and the tube deflects as though its second moment were 64 per cent of the gross.

The columns that lean

A framed tube carries its wind load by bending the spandrel beams between its columns, and it does it badly — the corner columns take nearly six times what the middle ones do. Tilt the columns instead, so the perimeter is triangulated, and the same shear is carried axially. The concentration falls to 1.21 and the tube recovers most of the stiffness the plan said it had.

Two curvatures of opposite sign, which is what makes it a structure. A cable net over a 36 m square, drawn as the two families of cables that are also the two rulings of the surface. One family sags and carries downward load by hanging; the other rises and carries upward load — wind uplift, and a load reversal anywhere — by the same mechanism upside down. Neither can do anything alone. A single family of cables is a mechanism: it changes shape freely under any load pattern it was not tensioned for, and the shape it moves to is decided by the load rather than by the designer. Put the two together and each is the other's restraint, but only if they are pulled against one another first — the pretension of 520 kN in the sagging family and 715 in the hogging one is a self-equilibrating state that exists with no load on the roof at all, and it is what turns two mechanisms into one structure. The curvatures are drawn four times their true value: a real net of this span sags 2.2 m over 36, which is flatter than it looks anywhere.

Two curvatures of opposite sign

A single family of cables is not a structure. It is a mechanism that takes whatever shape the load asks for, and it will do that under any load pattern it was not tensioned for. Cross it with a second family curved the other way, pull the two against each other, and the pair becomes stiff — with no bending anywhere and no material property involved in the stiffness at all.

Two drawings of one deck, and they are not the same structure. A 112 m viaduct on five supports, articulated two ways. Above, the fixed point is at the left abutment: the far end has to be given 45 mm of movement, and the friction of every sliding bearing runs one way, so the fixed support takes 660 kN before any wind or braking is applied. Below, the fixed point is at the middle pier: the largest joint halves to 22 mm and the friction now cancels across the fixed point, leaving 0 kN. The movement arrows are drawn at 900 times the scale of the deck, because a 45 mm movement on a 112 m span is thinner than the line the deck is drawn with. Nothing about the deck, the loads or the ground has changed between the two.

Where the structure is allowed to move

One drawing decides how big every movement joint on a bridge is and where every horizontal force goes, it takes an afternoon, and it appears on no calculation sheet. Move the fixed point from an abutment to the middle pier and the largest joint halves and the horizontal force on that support drops from the whole of the friction to none of it.

The two braces balance until one of them buckles. An inverted-V brace after the compression member has gone. While both braces are elastic they carry equal and opposite forces and their vertical components cancel on the beam above, which is why the beam in a chevron bay is usually sized for gravity alone. The compression brace buckles at 445 kN and then sheds most of what it was carrying — 30% is left here — while the tension brace goes on to yield at 1065. The difference between the two vertical components is 659 kN, applied at the middle of the span with no help from either brace, and it asks the beam for 1317 kNm against the 200 kNm the gravity load asks for — 6.6 times as much. The beam drawn does not: 1517 kNm against a capacity of 731. The force is not a load case anybody applies; it is what the frame leaves behind on its way to the state it will actually be in.

The force the brace leaves behind

Two braces meeting under a beam carry the storey shear as a tension and a compression whose vertical components cancel, so the beam above sees nothing. They cancel only while both braces are elastic. Once the compression brace buckles it sheds most of its force, the tension brace goes on to yield, and the difference is a point load at midspan that nobody applied.

The prop load is decided by the digging, not by the hole. Prop forces in a 12 m excavation propped at 3 levels, with the force each prop reaches at any stage of the sequence drawn thick and the force the finished arrangement gives it drawn thin. The pale dots are the individual stages. The middle prop reaches 214 kN while the dig is at 9.5 m and finishes at 88 — a factor of 2.44 between the two, and the larger one is not in the final analysis anywhere. Terzaghi and Peck's apparent pressure diagram, a rectangle of 49.4 kN/m², reproduces the total of the staged maxima to 2% — which is what it is: an envelope of measured prop loads, back-figured into a pressure, and a shape nothing on a wall is ever loaded with.

Every prop has its own worst day

A braced excavation has no finished state worth analysing. It is dug in stages, a level of props goes in at each stage, and a prop's force is largely fixed the moment it is installed — so the force to design it for is the largest it sees during a sequence that appears on no calculation sheet, and which for the middle prop here is nearly two and a half times what the finished arrangement gives.

The group is not weaker; it is very much softer. A 3 × 3 pile cap on the left, with each pile's share of 9.0 MN and 4.5 MNm in meganewtons — N/n plus M·y/Σy², the same three terms in the same order as a bolt group under an eccentric load and a section under biaxial bending. The corner piles take 1.25 times the average and a pile added at the centroid would change that by nothing at all, because it adds to neither second moment. On the right is the effect a bolt group cannot have: the piles share ground, so the stress bulbs overlap and the group settles 3.9 times as much as a single pile at the same load per pile, rising to 14.2 for 144 of them. The capacity check everyone makes — block failure against the sum of the piles — comes out at 4.54 here and does not govern at all. The check nobody tabulates is the one that does.

Nine piles, and four times the settlement

A pile cap divides its load between its piles by the same three terms a bolt group uses and a section under biaxial bending uses. What a bolt group does not have is neighbours it shares ground with — and the group effect that matters is not the strength check everybody makes, but a stiffness effect nobody tabulates.

The lining that carries less for being weaker. Bending moment and hoop thrust in a circular lining, against the lining's own bending stiffness, both as fractions of the free-ring values. The ground arrives already stressed — 500 kPa vertically and 300 horizontally at K₀ = 0.6 — and the difference between them tries to squash the hole into an ellipse. A lining stiff enough to refuse absolutely collects the whole distortion pressure, p₂R²/3 = 300 kNm/m; one flexible enough to go with the ground collects nothing, because there is no curvature change left to resist. The thrust is the flat line: it comes from the mean stress rather than the difference, so it does not move at all. Putting 8 joints in this ring drops the moment to 34% of the solid one and leaves the thrust exactly where it was, which is why a segmental lining is jointed and why the intuition carried over from a beam is inverted here.

The lining that is stronger for being weaker

A tunnel lining is not loaded. The ground arrives already stressed and the hole wants to squash into an ellipse; the lining's only job is to refuse, and how much moment it collects depends entirely on how hard it refuses. Make it stiffer and it takes more. Make it flexible — put joints in it, make it thin — and it takes almost none, while the hoop thrust it carries does not move at all.

A tie is worth all of itself and a strut is not, which is worth nine per cent. The same 20 floors carried two ways, with every member drawn at the width its own force requires. Hung, the loads accumulate upward, so the largest hanger is at the top: 18.0 MN at 355 N/mm² with no buckling reduction of any kind. On columns they accumulate downward and the largest column is at the bottom, at the same force — but every column above it is understressed by its own slenderness, worst at the top where a 900 kN column still has to be 4.8 × 10³ mm² to reach χ = 0.529. Over the height the hangers total 0.002 m³ of steel against 0.002: a saving of 9.0 per cent, which is the average χ and nothing else.

Hung from the top, and nine per cent lighter

A tie is worth its full strength and a strut is not, so hanging the floors of a building from a hat truss ought to be an obvious economy. It is a real one, it is measurable, and it is nine per cent of the steel — shrinking as the building gets taller, which is the opposite of what the argument sounds like.

The abutment force is the sag turned upside down. A 100 m ribbon carrying 35 kN/m at a sag of 2.0 per cent of its span. H = wL²/8f, so the horizontal force at each abutment is 21875 kN — 6.25 times the entire weight of the deck, and five times what a suspension bridge of the same span and weight at a tenth would have needed. The curve is a reciprocal and it has no flat part: halving the sag doubles the force, at any sag. What stops a designer flattening it further is not the ribbon, which is in tension and cannot buckle. It is what the ground at each end will take, and at 6.25 deck-weights that is usually rock or a very large anchor block.

The deck that is its own cable

Every other cable structure hangs something from the cable. A stressed ribbon hangs nothing — the walking surface is the catenary, laid at a fiftieth of the span rather than a tenth, because a footbridge has to be walkable. That one decision hands the abutments six and a quarter times the entire weight of the bridge.

The summer that is worse than the one before it. The earth pressure behind an integral abutment, summer by summer, as a multiple of the at-rest value it started at. A 60 m deck expands by 10.8 mm at each end and pushes the abutment into the backfill. Granular soil under cyclic strain densifies, so the same movement next year needs a higher pressure to achieve, and K climbs from 0.38 toward 0.96 — a factor of 2.49 on the force, reached after about a century. The design load on an integral abutment describes the bridge's whole life rather than a load case, and it is the only load in this collection that gets larger because time has passed rather than because something was added.

The summer that is worse than the last

An expansion joint is a hole in a deck that leaks salt water onto the bearings underneath it. Remove it and the thermal movement does not go away — it goes into the soil behind the abutment, twice a day for a hundred and twenty years, and granular soil under cyclic strain gets denser.

Cross the hangers and the chords stop bending. The same tied arch, the same sixteen hangers, the same load on half the span — hung vertically and hung as a network. Vertical hangers make the two chords a Vierendeel frame, which has no truss action at all, so a partial load is carried by bending: 3316 kNm in the tie and 6234 in the arch. Inclined hangers can carry the shear between the chords axially, and the same load gives 686 and 831 — factors of 4.8 and 7.5. The thrust is identical in both, because that is decided by the span and the rise and nothing else.

Cross the hangers and the bending goes

A tied arch with vertical hangers is a Vierendeel frame with a curved top chord — it has no truss action at all, so a load on half the span is carried by bending. Incline the hangers so they cross and the same two chords become a truss.

Every section is hogged and sagged before the bridge exists. The bending moment envelope of a launched deck, section by section along its own length, taken over every position of the launch. In service each section has one sign; during the launch 100 per cent of them see both, because each passes over every pier and through every span on its way out. The worst launch moment is 42568 kNm against 40500 in service, and with no launching nose at all it would be 185977. That is why a launched bridge is a constant-depth box with symmetric flanges: the design case is not a load, it is a history.

Every section was somewhere else

A bridge pushed out over its piers subjects each of its cross-sections to a history rather than to a load case. Every one passes over every support and through every span, so the design envelope is the envelope of envelopes — and no in-service condition produces it.

Every level added is a longer span, not a shorter one. Steel per square metre of floor against the number of levels in the hierarchy, for a 12 m bay with a deck that can span 3.0 m. A bending level's weight per unit area is 3ρqrL/8σ — it contains the SPAN and not the spacing — so breaking a floor into more levels cannot make the members lighter by making them closer together. It adds one more system, and the last system always spans the whole bay: a second level costs 52 per cent more steel than one, and a third 107 per cent. The structural zone grows with it, 730 mm to 1346 mm. Hierarchy is not an economy, it is a way of reaching, and it is paid for in both currencies at once.

Every level is a longer span

A floor is a hierarchy — deck to joists to beams to girders — and the reason usually given is that breaking a long span into short ones saves material. A bending level's weight per square metre contains its span and not its spacing, so it does not.

A closed force polygon. The forces on a joint, laid tip to tail. Equilibrium is the statement that the polygon closes, and the gap when it does not is the out-of-balance force, to scale.

One drawing solves the whole truss

The method of joints solves a truss one joint at a time, and each solution is thrown away as soon as the next begins. Drawn instead of computed, the joints share their edges — every member's force appears once in a single figure, and the figure's own closure is the check.

A Pratt truss of 8 panels. A Pratt truss under equal panel-point loads. The joint equilibrium equations were assembled and solved; 14 members came out in tension, 13 in compression and 2 carrying nothing.

Halving the panel buys a shorter strut

Subdividing a truss into more panels of the same span and depth barely changes the chord forces, because the couple that carries the moment has not moved. What it changes is the length of every compression member, and a buckling capacity goes as the inverse square of a length.

3 continuous spans against 3 simple ones. The bending moment in a continuous beam, solved by the stiffness method, drawn over the moment in the same spans made simply supported. The peak sagging moment falls from 28.1 to 18.0, and a hogging moment of 22.5 appears over the supports where there was none.

The chord is a continuous beam

A truss analysis reports one number per member, and for a chord running through eight panels that number is an axial force with no bending in it. The chord is a single piece of steel spanning between its own nodes, and anything landing between them bends it.

Influence line for the shear force at x = 10.5. The shear force at one fixed station, plotted against the position of a unit load walking across the span. The beam was re-solved at 301 load positions. The worst position is x = 10.56, giving 0.560.

Two diagonals, one of which is absent

A truss diagonal is sized for the shear in its panel, and near mid-span that shear changes sign depending on where the load stands. A member that can only pull cannot carry the reversed case, so the panel gets a second diagonal — and at any instant one of the pair is not there.

The shear goes round the corner instead of across it. A 6-panel Vierendeel girder, 21 m by 6000 mm, under 300 kN at mid-span. There is no diagonal in it, so each panel's 150 kN of shear is carried as bending in the chords: the curves drawn along them are the chord moments, and every one passes through zero at the middle of its own panel. The local moment is the panel shear times the panel length over four, 131.3 kNm, and it adds to an axial force of 263 kN from the global moment at the same point. The girder deflects 109.09 mm against 6.53 mm for the same members triangulated — 16.70 times — and 98% of that movement is chord bending that a diagonal would have removed entirely.

The frame is a girder stood on end

Every unbraced building frame is a Vierendeel girder turned through ninety degrees, and the identification is not an analogy — it is the same equations with the axes swapped. Which means the frame inherits results that read as absurd for a building — more bays is stiffer, a wider building is not, and doubling one section property halves the sway.

Removing each member in turn. Every member of a 8-panel pratt truss removed one at a time, with the worst demand on the survivors plotted against the member removed. Four of the 35 leave a mechanism — the bars drawn to the top of the frame — and for those there is no redistribution to compute, because there is no structure left. The rest redistribute, and the worst of them asks a survivor for 2.04 times what it carried before. A single number for robustness does not exist: it depends on which member goes.

A determinate truss has no robustness at all

Remove any one of a Warren truss's thirty-one members and what is left is a mechanism. Not weakened — gone, with no set of forces that holds the load in any position. Robustness is not a property a structure has by degree; it is bought by adding members that carry nothing until something else stops carrying, and a truss without them has none of it to measure.

The same bridge by the two theories it might have been designed by. Deck moment along a 500 m suspended span with half of it loaded, computed twice. Elastic theory treats the deck as a beam and applies the cable's extra tension as an upward load: 80.1 MN·m. Deflection theory keeps the cable's total tension acting on the deck's own deflected shape — a geometric stiffness — and returns 56.3, which is 30 per cent less. The extra cable tension is very nearly the same in both (6.20 against 6.11 MN), so nothing about the cable is in the difference: it is entirely the H·v″ term the older theory drops.

The tension that was left out

A suspension bridge's deck sits on a cable pulling hard along it, and a member with a large tension in it is stiffened by that tension. Leaving the term out of the deck's own equilibrium is what elastic theory does, and on a long span it asks for fourteen times the girder.

What the second, third and fourth arms are worth. Top drift removed against the number of outriggers, each arrangement at its own optimum levels, on a 40-storey core 200 m tall. One arm at 59 per cent of the height removes 82.3 per cent of the drift. A second, with both moved to 35 and 71, takes it to 91.6 — a gain of 9.3 points, which is half of what was left. The third is worth 3.0 and the fourth 1.5, and each one costs a storey of the building's most valuable height.

What the second arm is worth

One outrigger at its best height removes five sixths of a tall core's drift, which sounds like the end of the argument. A second removes half of what is left, a third half of that, and each of them costs a storey of the most valuable floor area in the building — so the question is not where to put an outrigger but how many the arithmetic still justifies.

The same bridge, anchored to the ground and to itself. The deck's bending moment under the live load, for a 500 m suspension span with a 50 m sag, a deck of EI 1.03 × 10¹² N·m², 100 kN/m of dead load and 20 kN/m of live load on half the span. Anchored to the ground, the deck carries at most 56.3 MN·m, because the cable's whole tension works on its deflected shape. Anchored to the deck's own ends, 83.0 MN·m — 1.47 times as much, and a little more than Rankine's elastic theory, 80.1, which leaves the tension out altogether. The deck's compression acts on the same deflected shape as the cable's tension, with the opposite sign, and cancels it.

The bridge that pays for its own anchorage

A suspension bridge's deck is light because the cable's tension works on its deflected shape and stiffens it. Tie the cable to the ends of the deck instead of to the ground and the deck must carry the same pull as a compression — which acts on the same deflected shape with the opposite sign and cancels the stiffening exactly. A self-anchored bridge is designed by the theory the long suspension bridge was invented to escape, and the price grows as the square of the span.

A load on one span moves the other. The change in level along two 100 m spans of stressed ribbon at a sag of 2.00 per cent, carrying 35 kN/m, when 20 kN/m of live load is added to the left-hand span, with a rigid pier (dashed) and with a pier of 200,000 kN/m (solid). With a rigid pier the loaded span sags a further 195 mm and the other does not move. With a pier of 200,000 kN/m the pier top leans 25 mm towards the load, the loaded span sags 358 mm and the unloaded span rises 191 mm; the pier carries 4,953 kN of the 9,440 kN a rigid pier would.

The pier that carries only the difference

A stressed ribbon continued over a pier pulls on it from both sides, and under its own weight the two pulls cancel. Load one span and they do not: the pier is asked for the difference, nearly ten meganewtons for a crowd on one of two hundred-metre spans. Whether it gives it depends on its stiffness against a number the ribbon supplies itself, and whatever the pier does not carry, the ribbon turns into movement — a third of a metre of extra sag in the loaded span and a fifth of a metre of rise in the empty one.

Three members after a diagonal goes. The forces in three members of the counter-braced truss when the diagonal 9–2, carrying 242 kN, is removed instantaneously, with 2 per cent damping, over one and a half of the damaged truss's first periods (0.57 s); dashed, the static force each settles to. The counter-diagonal 1–10 goes from −112 kN to −354 kN and peaks at −491 kN, 1.57 times its change. The bottom chord 3–4 ends exactly where it started, 750 kN, and on the way peaks at 1,115 kN. The bottom chord 2–3 settles lower, at 556 kN, after a first swing the other way, to 905 kN.

The factor of two belongs to one mode

A member that fails suddenly hands its force to the structure around it all at once, and the convention is to double the static answer: a load applied suddenly to a spring overshoots to twice its static deflection. A truss is not one spring. Take a diagonal out of a counter-braced truss in an instant and some members swing to three times their change of force, one swings the wrong way first, and a bottom chord whose force does not change at all passes through half as much again as it carries — because every mode overshoots by two, at its own time, and a member is a sum of modes.

The ratio stops growing and the twist does not. For a 30 × 18 m floor with a torsional radius of 10.6 m (0.35 of its length), against the distance of the centre of rigidity from the plan's middle as a share of the length, with the accidental eccentricity of 5 per cent of the plan: solid, the codes' ratio of the worst edge's displacement to the average of the two edges; dashed, the worst edge's displacement over the translation of a plan with no eccentricity. Dotted, the thresholds 1.2 and 1.4. The ratio rises to 1.76 at an eccentricity of 0.30 of the length and then falls, to 1.72 at 0.45; the edge's movement rises the whole way, from 1.20 to 4.83. The core-and-façade plan, at 0.14, reads 1.63 and moves 1.98.

A measure of twist that divides by the twist

The seismic codes decide whether a building is torsionally irregular by one ratio: the worst edge's displacement over the average of the two edges'. For a plan with no natural eccentricity that ratio is exactly how much further the corner moves than a plan without torsion would. For an eccentric plan it is not, because the twist moves the average as well as the corner, and the ratio divides one by the other. It saturates: at a torsional radius a third of the plan's length it never passes 1.76, however far the stiffness is moved off-centre, while the corner's movement keeps growing past four times. Past a point a more eccentric plan reads more regular, and the amplifier the codes build from the ratio inherits its ceiling.

One quantity, three names. The middle braced bay's share of the storey force (solid) and one end bay's (dashed), for a 48 by 12 m plate, 200 mm of concrete, spanning two 24 m bays between three braced bays of 100,000 kN/m each, under 40 kN/m, against a factor on the plate's stiffness as built, on a logarithmic scale. The share moves continuously from 61 per cent, a continuous plate on unyielding supports, to 33 per cent, the rigid plate. Left of 0.02 (shaded) ASCE 7 calls the plate flexible and assigns tributary shares, 50 per cent to the middle; the plate there actually gives it 59 per cent at the boundary. Right of 1.54 (shaded) EN 1998-1 calls it rigid and assigns stiffness shares, 33 per cent; at that boundary the plate gives 37. The plate as built, factor 1, gives 38 per cent to the middle and 31 to each end.

Rigid by one code and not by the other

A floor plate between shear walls shares its storey force out in proportions that move continuously with its stiffness, from a continuous beam's to a rigid body's. The codes put it in one of two boxes and use a different model in each. ASCE 7 and EN 1998-1 draw their boxes' edges a hundred times apart in plate stiffness, each at a point where its own licensed model already misstates the middle wall by about a tenth — and an ordinary 200 mm slab sits in the gap between them.

The cable pays the factor the plateau saved. The force a beam of two 8.0 m spans over the column, 600 mm deep, plastic moment 800 kN·m, its far ends held against rotation and against spreading (plastic collapse load 400 kN) reaches after a sudden loss divided by the load it carries — the dynamic factor — against that load as a share of the plastic collapse load. Below the plateau the beam is a linear spring and the factor is 2. On the bending plateau it falls to 1.18 at 0.90 times the collapse load, because a flat resistance does its work at full strength from the start. Past it the beam becomes a cable, whose resistance is again straight, and the factor climbs back: 1.73 at 1.5 times, 1.88 at 2, 1.97 at 3.

The cable that pays the factor back

A frame that loses a column carries the floor across the gap first by bending and then, as the beam sags, as a cable. The hope is that a path which stiffens as it deflects needs less than the factor of two a suddenly loaded spring does. On the bending plateau it does — 1.18 at nine tenths of the collapse load. But past one depth of sag the cable is a straight line again, and the factor climbs straight back toward two: 1.73 at one and a half times the collapse load. And the connections are asked for a tenth of a radian on the way.

One span hung, the other still bare tendon. The level along two 100 m spans at a sag of 2.00 per cent, 35 kN/m finished and 3.0 kN/m of bare tendon, the tendons at 1100 N/mm² when finished, with the deck hung on the left span only (solid) and as finished (dashed), on a pier of 200,000 kN/m. The hung span sags 2.04 m and pulls 21,442 kN; the bare tendon beside it sags 0.20 m and already pulls 18,363 kN, because it was cut 455 mm shorter than the span so as to carry its share when finished. The pier is asked for the difference, 3,080 kN, and leans 15 mm towards the hung span — against 4,953 kN under 20 kN/m of crowd on one finished span.

The tendon that pulls before the deck arrives

A stressed ribbon is hung one span at a time, and the obvious fear is the stage at which one span carries its deck and the next does not: the pier between them asked for a whole span's thrust. It is not asked for that, because tendons cut to the finished length are already stretched across the empty span and pulling. For two 100 m spans at a fiftieth, the rigid pier's stage force is 4,109 kN against a crowd's 9,440 — unless the tendons were sized generously, when the stage overtakes the crowd.

The slab carries what the collector does not, beside the bay. The plate's shear flow just beside the same brace line, along it: the rule's uniform 40 kN/m (dashed); with a 150 mm concrete slab (solid), concentrated beside the bay — 132 kN/m on average over the bay's 6 m, 3.3 times the rule's, with peaks at the bay's ends that grow as the mesh is refined, because a stiff support ending in a plate is a stress singularity — and little elsewhere; with a steel deck of shear stiffness 10,000 kN/m (dotted), close to uniform. Each curve adds up to the line's 960 kN.

The collector the slab does not need

A floor delivers its storey force to a short braced bay through a collector, a member along the brace line that gathers the floor's shear and carries it to the bay. The rule that sizes it assumes the floor hands over its shear uniformly along the whole line. A concrete slab does not: it is so stiff in shear that it sends most of its load straight into the bay, the collector carries about a quarter of the rule's force, and the slab beside the bay works at more than three times the rule's shear. A steel deck is the other way round. The rule is right for one floor, and safe for the other only while the slab stays uncracked.

The pier reads the difference between the two spans' temperatures. Contours of the pier force between two 100 m spans at a sag of 2.00 per cent with the deck hung on one, the tendons at 1,100 N/mm² when finished, on a pier of 200,000 kN/m, every half meganewton, over the warming of the hung span's tendons (across) and of the bare tendon's (up) since they were cut. With neither warmer the pier carries 3,080 kN; warming the bare tendon 30 °C alone gives 4,126 kN, the hung span alone 2,342 kN, and both together 3,392 kN. The contours are straight and parallel: the pier gains 35 kN for each degree the bare tendon warms and loses 25 for each degree the hung span does, so a warming both share moves it only 30 per cent as far as the same warming on the bare tendon alone, and what the pier feels is mostly how much warmer one span's strand is than the other's.

The strand in the sun beside the strand in the shade

Halfway through hanging a stressed ribbon, one span is a sagging cable full of segments and the next is bare tendon stretched nearly straight, and the pier between them carries the difference of their pulls. A warm day takes tension off both — and at the flat sag a ribbon is laid at, the hung span is so nearly all stretch that it loses three quarters of what the bare one does. What moves the pier is not the weather but the shade: strand in the sun beside strand under concrete, 35 kN on the pier for every degree between them. No sun slackens the bare tendon. The hour does change something else, which is the level the joints are cast at.

However heavy the chord, ordinary posts cap its share. The heavy chord's share of the shear in a panel of uniform shear in a Vierendeel girder of 2 m panels, 1.5 m deep, against how many times stiffer it is than the light chord, from the one-panel model (lines) and from a whole girder (dots). Splitting by second moment (dashed) runs from 0.5 towards 1. With posts as stiff as the light chord the share is 0.54 at a ratio of 4 and still only 0.55 at 30; posts 4, 16 and 100 times stiffer reach 0.65, 0.80 and 0.93 at 30. The posts, not the chord, set the ceiling. The dots are a twenty-panel girder at its sixth panel, far from both support and load: with ordinary posts 0.50, 0.53, 0.56, 0.60, 0.65, 0.69 at ratios of 1, 2, 4, 10, 20, 30. They follow the model until the heavy chord's own second moment becomes a noticeable part of the girder's — 31 per cent at a ratio of 30 — and it starts to carry the global moment by bending as a beam.

The heavy chord the posts will not let work

A Vierendeel girder carries its shear as bending in its two chords, and when one chord is four times as stiff as the other the obvious rule gives it four fifths of the shear. With posts as stiff as the light chord it takes 0.56. The heavy chord's end moments have to be carried round each joint by a post, the post bends, and the heavy chord turns with its joints instead of bending between them. No amount of extra steel in that chord takes its share past 0.55 in the middle of a long girder; only the posts can, and they have to be about 150 times as stiff as the light chord to make the rule come true.

The arm goes in almost the same place whatever shape the wind is. The share of the tip drift removed by one outrigger on a 200 m core of bending stiffness 1.2 × 10¹⁰ kN·m² carrying 6,000 kN of wind in all, with an outrigger of 1.0 × 10⁸ kN·m per radian, against the outrigger's level as a share of the height, for the three profiles of the same total wind. uniform: best at 0.745 of the height, removing 45.6 per cent; power law: best at 0.749 of the height, removing 45.9 per cent; triangle: best at 0.757 of the height, removing 46.4 per cent. The curves lie almost on one another: the triangle, with three quarters of its load in the upper half against the uniform wind's half, moves the best level up by 1.2 per cent of the height.

The arm that ignores the shape of the wind

The outrigger arithmetic is usually done for a wind that is the same at every height, and real wind is not: it grows with height, and an earthquake's first mode loads a building as a triangle. The natural guess is that a load concentrated towards the top moves the best place for the arm. It barely does. Put the same total wind on a 200 m core as a uniform load, a power-law wind and a triangle, and the best level moves by just over one per cent of the height. What moves is the force in the arm — half as much again under the triangle — and how far the top goes, while the arm's own stiffness shifts its best level thirty times as far as the wind's shape does.

A hanger that would push is a hanger that is not there. The force in each hanger of a tied arch of 100 m span and 17 m rise on 32 crossed hangers, carrying 60 kN/m of dead load over the span and 120 kN/m of live load over its left half, against the hanger's position along the tie. Solved as though every hanger could push (pale bars), 4 come out in compression, the worst at 185 kN. Solved with those hangers taken out until no remaining one is compressed (dark bars), 8 are slack — more than the linear solution has in compression, because each hanger that goes passes its share to its neighbours and some of them follow.

The deck that keeps the hangers in the truss

Crossing the hangers of a tied arch turns it from a frame that bends into a truss that does not, as long as every hanger is pulling. A hanger cannot push, and under a load on half the span some of them would have to. Solved as it really is — with those hangers taken out, and the ones that follow them — the arch keeps the linear answer exactly until the live load on half its span is about equal to its own dead weight, and past that the tie's moment doubles and then quadruples. The arch's own weight is the pretension nobody had to apply, and a heavier deck is a stiffer network.

A crossed hanger swings through nearly all of its force. The largest and smallest force in each crossed hanger of a tied arch of 100 m span and 17 m rise on 32 hangers, with 60 kN/m of dead load and a live load of 60 kN/m running on from either end, each bar running from the one to the other. The worst range is 678 kN, from 49 to 727, in hanger 11; the largest force anywhere is 756 kN. 6 of the 32 go slack at some stage, and the worst range is 90% of the largest force anywhere: the live load's shear passes through the crossed hangers as through a truss's web, and swings them from nearly nothing to nearly their most.

The hangers that carry the shear twice

Crossing a tied arch's hangers turns them into the web of a truss, which is why the tie stops bending. It also means a live load's shear passes through them, so as a load runs on from either end each crossed hanger swings from nearly nothing to nearly its most: on a 100 m arch the worst swings through 678 kN, 90% of the largest force in any hanger, where a vertical hanger swings through 194, half of its own. More dead load raises the force and leaves the range alone. The arrangement that is best for strength is the one that hands its hangers to fatigue.

The columns and the core shorten apart for decades. For a 200 m concrete building built a storey every week, its perimeter columns at 12 N/mm² and its core at 6 at the base, with an outrigger at 149 m of 1.0 × 10⁸ kN·m a radian: how much the columns (solid) and the core (dashed) have shortened below the outrigger's level, and the difference between them (heavy), in mm, against the years since the first storey was cast, on a log scale. When the building tops out, in week 55, the difference is 7.0 mm; after fifty years it is 30.5. 77% of the difference arrives after the frame is finished — creep under the finishes and the floors above, and the thick columns' slower drying, most of which comes after the core's thinner walls have done theirs.

The arm connected late

An outrigger is often left unconnected until a concrete building is finished, so that the columns and the core can shorten by their different amounts without it. Most of their difference has not happened yet. Three-quarters of fifty years' differential shortening arrives after the frame tops out, and an arm connected then ends up carrying 3.5 MN of it — 60 per cent of what the design wind puts into the same arm, permanently, and in the same direction on both sides of the core. The connection date is the largest load the arm has, and a stiffer arm collects it faster than it collects the wind.

A load between the posts racks the panel it stands in. Elevation of a Vierendeel girder of six 2 m panels, 1.5 m deep, its deck chord as stiff as its other chord and its posts, the load standing in the middle of its second panel; the racked shape exaggerated, the unloaded girder faint. The panel the load stands in carries most of its shear, and the deck chord there bends both as a Vierendeel chord and as a beam between its posts: 38 kN·m against 27 with the load at mid-span. The posts either side carry 56 and 11 kN·m, and the heaviest post 56.

The load that visits every panel

A Vierendeel girder checked for a load at mid-span is checked for one position of a load that, on a bridge, stands everywhere in turn. Crossing it, a 100 kN load puts 1.7 times the mid-span check's moment into the end panels' chords, loads the middle post that a central load leaves idle, and makes the deck chord a beam between its posts in every panel where its share of the shear is small. Equal chords stay the stiffest arrangement; a vehicle whose axles span a panel cannot stand in the middle of one.

A joint that gives way to creep, two ways. For a 200 m concrete building built a storey every week and fitted out over six months, with an outrigger at 149 m of 1.0 × 10⁸ kN·m a radian connected on day 385: the force in one arm over the years, in MN, connected rigidly, through a friction joint that slides at 2.00 MN, and through a viscous damper of time constant 10 days; dotted, the 5.80 MN the design wind puts into the same arm. Rigid, the arm collects 3.48 MN. The friction joint lets it collect 2.00 MN, reached after 3.7 years, and holds it there for the rest of its life. The damper lets it collect at most 0.08 MN, while the building is being fitted out, and 0.00 after fifty years.

The arm that slips on purpose

An outrigger connected to a concrete building at topping out goes on collecting the columns' and the core's differential shortening for fifty years. The obvious cure is a joint that lets the arm move under the slow force and holds under the fast one. A friction joint cannot do it — once creep has brought it to its slip load it has nothing left on one side of the core, and a joint strong enough to hold the wind is never reached by the creep at all. A viscous damper can, because its force depends on how fast it is pushed rather than how far.

A stiff floor shares by stiffness, a soft one by distance. The share of a brace line's force that reaches its soft bay, against the other bay's stiffness over the soft bay's on a logarithmic scale, for a 48 by 24 m floor carrying 40 kN per metre of span, each brace line 960 kN, with a 6 m braced bay of 200 kN/mm at one end of each line and a 6 m bay 10 times as stiff — for three floors (dashed: a rigid floor, which shares by stiffness, and the tributary half). With the other bay ten times as stiff the rigid floor gives the soft bay 9%; the concrete slab 16%, the cracked slab 30% and the steel deck 37%.

The floor that feeds two bays

A brace line with a braced frame at one end and a core wall ten times as stiff at the other is analysed one of two ways. As a rigid floor, which shares the line's force between the bays by their stiffness and gives the frame 9%. Or as a flexible floor, which gives each bay the half of the line nearest it, 50%. Solved as a membrane, an uncracked concrete slab gives the frame 16%, the same slab cracked 30%, and a steel deck 37%. The floor does not send its shear to the nearer bay; a stiff floor sends it to the stiffer one. The frame's design force depends on which state the floor is in when the storey force arrives, by more than a factor of two.

A haunch moves the worst stress range to its toe. The stress range up the height of the first interior post of a Vierendeel girder of six 2 m panels, 1.5 m deep, every member of the same section (I = 117 × 10⁶ mm⁴, W = 780 × 10³ mm³), crossed by a 100 kN load, over one crossing: the plain post (dashed), and the post with 250 mm haunches 2.00 times as deep at both corners (solid); with the constant-amplitude limits 52.3 MPa for detail category 71 (dotted). Plain, the range is 78.3 MPa at the corner. Haunched, it is 43.3 at the corner and jumps to 61.2 at the toe, 250 mm along the post — the largest anywhere in it, 61.2.

The corner that counts its crossings

As a load crosses a Vierendeel girder, the moment at a post's corner changes sign when the load passes that post. A static check reads the peak, and the peak says the posts beside the supports work twice as hard as the middle one. Fatigue reads the range, and the range says every interior post works the same. A haunch at the corner lowers the corner's range and moves the worst of it to the haunch's toe — so a deeper haunch soon buys nothing, a longer one keeps paying, and a toe two detail categories worse than the corner cancels the haunch outright.

The range belongs to the truss. The worst hanger force range against the tie's largest moment in a tied arch of 100 m span and 17 m rise on 32 crossed hangers of 3,000 mm² bar, 60 kN/m of dead load and 60 kN/m of live load run on from either end, as the hangers' stiffness runs from four times a plain bar's to a fiftieth of it (dots), and for the same arch on vertical hangers (the lone dot). Softening the crossed hangers walks the bridge from 678 kN of range and 316 kN·m of tie moment to 557 and 1,154; vertical hangers sit at 194 and 3,505. The line bends nowhere near the vertical arch's point: a soft network is still a truss.

The hanger that cannot be made soft enough

A network arch's crossed hangers swing through nearly all their force as traffic passes, because they are the web of a truss. Make them softer — a spring at each anchorage — and the tie ought to take back some of the shear and the hangers' ranges ought to fall. They hardly do. A tenth of the stiffness takes 6 per cent off the worst range and adds a third to the tie's bending; a fiftieth takes 18 per cent off and multiplies the tie's bending by 3.7. The range belongs to the truss and leaves only when the truss does, which vertical hangers show at 194 kN against 678 and eleven times the bending. So the hanger is sized for its range, eight times the area its strength needs, and the stiffness that comes with it costs the range nothing.

Double the span and the deck is nearly three times nearer buckling. The factor on its own dead load at which a stayed deck buckles, against the main span, on logarithmic axes, for a deck of 0.50 × 10¹² N·m² under 150 kN/m with stays every 15 m from towers 0.40 of the half-span tall. At 300 m it is 40.7; at 600 m, 14.7; at 1,000 m, 6.9; at 2,000 m, 2.3. Beyond 600 m the line falls with a slope of 1.53; it crosses ten, below which a design has to follow the deck's deflections into its forces, at 805 m.

The deck the stays squeeze

Every stay of a cable-stayed bridge pulls the deck towards its tower, and the deck carries all those pulls as a compression that is largest at the tower — 95 MN in a 1,000 m span under 150 kN/m. The stays hold it up and hold it straight, as springs under a strut. The compression grows with the square of the span and the springs soften with it, so the factor on its own weight at which the deck would buckle falls as the span to the power one and a half: 41 at 300 m, 6.9 at 1,000 m, 2.3 at 2,000 m. A deck four times stiffer only doubles it, and the long stays' sag, which softens them for traffic, hardly enters.

Each new set of shims gives back the creep since the last. The creep force in one arm of a 200 m concrete building built a storey every week and fitted out over six months, with an outrigger at 149 m of 1.0 × 10⁸ kN·m a radian connected on day 385, over fifty years on a logarithmic axis: connected and left (dashed), adjusted once at 1 years, and adjusted at 1, 3 and 10 years, the arm's force falling to nothing at each adjustment; the design wind's 5.80 MN dotted. Left alone the arm ends at 3.48 MN. Adjusted once it ends at 2.58; adjusted at 1, 3 and 10 years it never holds more than 1.40 and ends at 0.91.

The arm that is reset by hand

An outrigger connected to a concrete building at topping out collects the core's and the columns' differential creep for fifty years, 3.48 MN in each arm against a design wind of 5.80. A damper lets the creep through and stops the wind, but it is a machine. The older answer is a joint closed with shims and opened every few years to take the creep out. Three visits, at one, three and ten years, hold the arm below 1.40 MN, and spaced like the creep they do it with roughly equal thicknesses of shim each time. Evenly spaced, the same three visits hold 2.48. And a visit that is missed costs exactly the creep it was there to remove.

More hangers, each swinging through less. Each hanger's force range, plotted at its mid-point along the span, for a tied arch of 100 m span and 17 m rise on 32, 64, 96 crossed hangers of 3,000 mm² bar at 60°, 60 kN/m of dead load and 60 kN/m of live load run on from either end. 32 hangers: the worst 678 kN, the mean 528; 64 hangers: the worst 369 kN, the mean 273; 96 hangers: the worst 241 kN, the mean 184.

More hangers, and the same steel

A network arch's crossed hangers are the web of a truss, and a live load's shear passes through them, so every hanger swings through nearly all of its force. The obvious cure is more hangers, each crossing more of its neighbours, so that every section's shear is shared among more diagonals. It works hanger by hanger — three times the hangers, a third of the range — and not at all in total: the hangers' fatigue steel, sized for their ranges, is set by the shear the arch carries and barely changes with how many hangers it is divided among. What more hangers buy is elsewhere.

The flatter the ribbon, the more the casting temperature matters. For two 100 m spans of a stressed ribbon under 35 kN/m on a pier of 200,000 kN/m, one span's joints cast 20 °C warmer than the other's: the force left on the pier as a share of the force a crowd of 20 kN/m on one span puts there, against the ribbon's sag as a percentage of its span. At a sag of 1 per cent the casting leaves 82 per cent of a crowd (1,902 kN against 2,316); at 2 per cent, 14 per cent; at 3, 3 per cent; at 4, 1 per cent.

The span cast in the afternoon

A stressed ribbon's joints are cast on whatever day the programme reaches them, and a span cast on a warm afternoon sets around strand that has lengthened in the sun. It cools that night as a concrete band eleven times stiffer than the strand, and the band does not stretch back as the strand would have. On a ribbon with a sag of 2 per cent, a span cast 20 °C warmer than its neighbour ends 72 mm higher than it was set and leaves 713 kN on the pier between them — a seventh of what a crowd on one span puts there. On a flatter ribbon the same afternoon costs more than the crowd. The difference between the two spans is the strand's flexibility against the band's, and only the elastic part of it differs; the part that comes from the sag is the same for both.

Lightened where it reverses, and the range follows. The stress range each post's corner sweeps over one crossing of a Vierendeel girder of six 2 m panels, 1.5 m deep, its chords all of one section (I = 117 × 10⁶ mm⁴, W = 780 × 10³ mm³), crossed by a 100 kN load: uniform posts, posts sized to their peaks, and posts sized to both their peaks and their ranges. Uniform, every interior corner ranges 76.1 to 78.3 MPa. Sized to peaks, the middle post's range is 150.8 MPa and its neighbours' 101.6, against the uniform girder's worst of 78.3. Sized to both, no corner exceeds 78.3 MPa.

The post sized by what it must survive

A Vierendeel girder's posts are usually all one section, and a crossing load gives them peaks that differ by a factor of two and ranges that barely differ at all. Size each post to its peak and the steel falls by a quarter — and the middle post, lightened to two-fifths of the chords, sweeps twice the stress range the whole girder used to, and lasts a seventh as long. Size each post to its range instead and the girder needs less steel than the uniform one, not more, because the posts that can be lightened are the ones at the ends.

A floor's robustness belongs to its joints until they break, and to its slab after. For a floor whose interior column is lost, two 8 m-span beams crossing over it (each collapsing at 400 kN) and a slab 16 m square over the four bays round it: the largest floor load a sudden loss can be held at, as a multiple of the two beams' collapse load, against how far the beams' connections can turn before they fracture, for no mesh and for 142, 252 and 393 mm² a metre. No mesh: 0.94 at 0.03 radians and 1.19 at 0.07; 142 mm²: 0.94 at 0.03 radians and 1.29 at 0.07; 252 mm²: 1.50 at 0.03 radians and 1.81 at 0.07; 393 mm²: 2.26 at 0.03 radians and 2.56 at 0.07.

The slab that catches what the joints let go

When an interior column is lost, the beams that crossed over it sag into cables and the slab over the four bays round it sags with them, into a membrane hanging from the floor that did not lose anything. Whether the floor's robustness belongs to its steelwork or to its concrete turns on one number with no span in it: the slab's mesh only starts to carry its full tension when the beams' ends have turned through about 0.09 radians, more than any ordinary joint can follow. So the membrane arrives after the joints have gone. And then it catches the floor — a metre down, alone — and with an ordinary mesh it holds half as much again as the beams could.

The dynamic ratio peaks where the modes couple, and falls where the static one climbs. The standards' ratio, the larger edge's displacement over the average of the two edges', for a 30 × 18 m floor swaying with a period of 0.5 s, against Ω, the torsional radius over the floor's radius of gyration, for natural eccentricities of 2.1 and 4.2 m: from a static push at the centre of mass (dashed) and from a response spectrum combined by CQC (solid); the dotted lines are 1.2 and 1.4. At 2.1 m, static 2.05 at Ω = 0.5 falling to 1.08 at 2; dynamic 1.08 at 0.5, highest at 1.42 near Ω = 1.15, and 1.10 at 2. At 4.2 m, static 2.46 at Ω = 0.5 falling to 1.15 at 2; dynamic 1.17 at 0.5, highest at 1.55 near Ω = 1.20, and 1.19 at 2.

The floor that twists in its own time

Seismic design standards flag a twisting floor by the ratio of its worst edge's movement to the average of its two edges', and a static push saturates that ratio. Give the floor mass and shake it, and it sways and twists in two modes that share the motion. A response-spectrum analysis then reads the same ratio from combined peaks — and gives a different verdict on a third of the plans tried. Floors torsionally stiffer than they sway read worse than a push says, because the coupled modes put twist at the edges. Floors torsionally flexible read better, because combining the modes keeps how far each edge moves and forgets which way, so a twisting floor's two edges both look large.

All essays