Shrinkage — where it appears
Named by 29 essays across 6 fields — each of them below, with the objects they name alongside it.
The deflection that arrives three years late
A concrete beam that passes every check on the day it is built goes on deflecting for a decade, and ends up three times where it started. Nothing about the load changed, and nothing about the strength was ever in question.
The strain that was imposed, and the stress that leaked away
Multiply a restrained shrinkage strain by the modulus and the answer is three times the tensile strength — which predicts that every restrained concrete member ever cast has cracked. Most have not, and the reason is that the material creeps while it is being stressed.
The columns are shorter than the core
Every column in a tall building gets shorter as the building is built on top of it, and the core beside it gets shorter by a different amount. The floors between them tilt by the difference — and the difference is largest exactly half way up, because a floor near the top has almost nothing built above it and a floor near the bottom has almost nothing beneath it.
The curvature nobody applied
Concrete shrinks as it dries, by about half a millimetre in every metre. In a symmetrically reinforced member that is a shortening and nothing else. In a member with more steel in one face than the other — which is every beam and every slab — the steel holds one side back and the section bends, with no load on it at all.
The gap nobody computed
A movement joint is sized by adding up everything the structure will do to it, and the deflection calculation — the only term anybody computes carefully — is usually the smallest one in the list. The largest is a construction tolerance, which is not a structural quantity at all, and the sum of the extremes is nearly twice what treating them as independent would ask for.
The steel the concrete asks for
Every other bar in a concrete member is there because of an action. This one is there because of the member itself — enough steel that the cracked section can carry more than the moment that cracked it, so that the first crack is not also the failure. The requirement contains no load, and both of its consequences run the wrong way round.
The same steel, and a wider crack
A crack's width is the distance between cracks times the strain the steel carries over that distance. Neither of those is decided by how much reinforcement there is. The spacing is a bond length, so it goes as the bar diameter; the strain is set by the stress in the steel. Two arrangements of identical steel can differ by a factor of two in crack width, and the one that wins is the one with more, smaller bars.
The limit that depends on a date
Total deflection can nearly always be met, and on a long span it is met with camber. The limit that actually decides the member is the other one — the deflection occurring after the brittle finishes are built — and camber does nothing for it whatever, because it is subtracted from both terms of a difference. The same beam passes or fails on the day the partitions went up.
The strength that is never used
Concrete's tensile strength appears in no bending calculation, no column calculation and no shear calculation with links in it. The whole design philosophy is that it cracks and the steel takes over. And it decides where nearly every transition in the subject sits — when a section cracks, how much minimum steel it needs, how far a bar has to be lapped, what a member without links can carry, and how wide a crack opens.
The stress that leaks away
Creep makes a load's deflection grow and an imposed strain's stress shrink, and the second is why restrained concrete does not crack as often as an elastic calculation says. The same material property runs both ways, and which way it runs depends on whether the structure was given a force or a movement.
The bay that is cast last
A wall cast on a base cracks in a way the steel controls: more movement gives wider cracks, and reinforcement decides how many. A bay cast between two walls that have already hardened cracks in a way that has nothing to do with how much movement there was — and the threshold that separates a controlled crack from a single wide one is a quantity of steel rather than a limit on anything.
The creep that belongs to the member
A creep coefficient is quoted for a concrete, and half of it is not a property of the concrete. It is the member drying out, and drying goes through the surface — so one mix creeps a quarter more in a thin slab than in a deep beam, gets there years sooner, and in saturated air forgets its size altogether.
The slab that dries from one face
A creep coefficient is one number for a member, and a member drying through one face does not have one. Give every depth its own humidity and the section a strain profile it cannot deliver, and two things follow that no single coefficient contains — a six-metre slab lifts eleven millimetres at its edges with nothing on it, and its top surface is past cracking before it has been loaded.
The prestress the member takes back
A tendon is stretched, locked off against the concrete, and then has to hold that extension while the concrete underneath it shortens by itself. Fifteen per cent of the force goes, most of it to creep, and how much goes is decided by the shape of the member and the air it stands in rather than by anything about the steel.
The slab that shrinks onto a finished beam
A precast beam with an in-situ slab cast on it is one member made of two concretes, and they do not age together. The slab's shrinkage is nearly the same whenever it is poured; what changes is how much shrinking the beam has left to share it with. Cast the slab at six weeks and it takes a ninth of the soffit's precompression away over thirty years. Cast it at a year and it takes a quarter, and goes into tension itself.
The angle made in the casting yard
A bridge bearing is designed for the rotation of the beam it carries, and the rotation is listed as a sum of load, temperature, creep and a tolerance. Followed through the life of a pretensioned beam, the largest term is none of those. It is the upward turn the prestress gives the beam's ends in the casting yard, before any bearing exists, and under every load the beam will ever carry its ends still point up.
The pier that bends the wrong way
Two precast beams are made continuous over a pier by a joint cast with the deck, and the joint is designed for the hogging moment a continuous beam has there. Thirty years later it is sagging, by more than the moment that cracks its underside, because the beams were still cambering upward when they were joined. Whether that happens is decided by two dates — when the beams were cast and when the joint was — and the deck's shrinkage, which pulls the other way, is not enough to stop it.
The jacks the arch forgets
Jack a fixed concrete arch's abutments apart before the crown is closed, by exactly the gap its thrust and its footings open on the day, and the springings start with no moment at all. A century later they carry 173 kN·m — half as much again as the 112 the jacks were set to remove. The thrust's own moment never relaxes; the jacks' correction does, as the rib creeps; and shrinkage and the ground's consolidation arrive after the jacks have gone. No single setting cancels movements that run on different clocks.
The arm connected late
An outrigger is often left unconnected until a concrete building is finished, so that the columns and the core can shorten by their different amounts without it. Most of their difference has not happened yet. Three-quarters of fifty years' differential shortening arrives after the frame tops out, and an arm connected then ends up carrying 3.5 MN of it — 60 per cent of what the design wind puts into the same arm, permanently, and in the same direction on both sides of the core. The connection date is the largest load the arm has, and a stiffer arm collects it faster than it collects the wind.
The slab that shrinks away from the wall
A basement wall propped by its ground-floor slab before it is backfilled keeps the roller's pressure, and its slab takes it. Then the slab dries. Two millimetres of shrinkage at each end — about a year for a 30 m slab indoors — and a slab that only bears on the wall has let go of it, leaving a stem designed as propped to carry 2.6 times the base moment it was given. Tying the slab into the wall to stop that makes it worse: the slab goes on shrinking and pulls, and the base moment passes the free cantilever's.
The joint cast over the pier
Two pretensioned beams made continuous over a pier by a joint cast with the slab have ends that are still turning when the joint goes in, and the joint stops them. What it is then asked to carry depends on the day it is cast. At four weeks the beams' creep is still lifting their ends and the joint is sagged to half as much again as its cracking moment. At a year the beams have nearly stopped and the slab's shrinkage hogs the joint by as much the other way. Cast at about sixteen weeks, it is asked for almost nothing.
The joint poured twice over the pier
A continuity joint over a pier can be cast in two stages — the diaphragm and the beams' bottom connection first, the slab weeks later — in the hope that the early pour catches the beams' creep and the late one leaves the slab's shrinkage little to do. It does neither. From the slab's day on the composite section holds exactly what a single pour on that day would have held, and the first stage adds only its own small account, of either sign. It trims a year-old slab's hog by a fifth, and it asks a joint with half the cracking moment to carry the beams through the months between.
The arch that waits with its hinges open
A concrete arch fixed on the day it is struck has to restrain every millimetre its rib creeps and shrinks and its ground settles for the rest of its life, and jacking it again a year later cannot make it forget the year before. Struck as a three-hinged arch and left that way, it takes the fastest part of every movement for nothing, because a determinate arch has no moment to spend on a change of length. Closed at a year it ends the century with half the springing moment of the arch fixed at striking, and a third less than the arch jacked again on the same date. The price is a crown that has dropped 78 mm while it waited, and a rib that is no longer the shape of its own thrust.
The seasons that stop reaching the wall
A ground-floor slab that has shrunk away from the basement wall it propped moves with the seasons as well, a few tenths of a millimetre at each end every year. It looks like a ratchet waiting to happen: each winter the slab presses the stem back into its fill, and each push might lock a little more pressure in. On a 30 m slab it never gets the chance — the seasons ride on a shrinkage ten times larger, and the slab last touches the wall sixteen months after the fill is finished. On a 10 m slab it touches every year for good, and the stem still loses most of its prop.
The younger span catches up
Close one span of a stressed ribbon a month before its neighbour and the older band has already shortened when the younger arrives, by a difference that ought to keep working on the pier between them. It does not. The younger span shortens faster and closes most of the gap within a year, and what looked like a grievance that never stops growing is at its largest on the day it begins. What it leaves is small, and it stays, because the part of a ribbon that holds it is a sag, and a sag does not creep.
The bars that take the column over
Steel does not creep and concrete does, so a reinforced column's concrete slowly hands its load to the bars, with nothing on the outside having changed. Bars carrying a seventh of the load on the first day carry more than a third after fifty years, the column shortens a quarter less than plain concrete would, and the column-to-core difference that a tower has to be built around can be closed or even reversed by the steel alone. And if the load is ever taken away, the bars that took it over pull the concrete into tension and crack it, with nothing on the column at all.
The column that cannot be unloaded slowly enough
A heavily reinforced concrete column that has carried its load for ten years has handed much of it to its bars, and when the load is taken away the bars, still squeezed, pull the concrete into tension. Taking the load off slowly lets the concrete creep under that tension as it arises, so it seems a slow enough programme could keep any column uncracked. It cannot. Slowness takes a fifth off the peak, and decades later every column arrives at the same tension however it was unloaded — past the concrete's strength above 3.3 per cent of steel.
The slab left to dry before the fill
A basement stem propped by its ground slab keeps the pressure the roller locked into its fill only while the slab still bears on it, and a slab cast four weeks before the fill shrinks away within sixteen months. Casting the slab first and letting it dry before the fill goes up sounds like the cure. Six months of drying buys four more years; a year keeps the slab touching the stem every summer for thirty. But a slab that touches only in summer gives back the propped moment only in summer, and in the tenth year a stem filled two years late still reaches 63 kN·m of its unpropped 70. The delay keeps the contact. It does not keep the design.
The joint born holding a moment
A continuity joint over a pier ends its first thirty years sagged or hogged by the beams' creep and the slab's shrinkage, by an amount the date of the pour decides. Jacking the beams' pier ends before the joint is cast lets it be born holding the opposite moment, so that the two cancel at thirty years. The arithmetic works for any slab date. The jack does not, for two reasons: the beams' creep relaxes a jacked moment like every other restraint, so the jack must be two to three times the moment it cancels and is larger than the joint's cracking moment on either side; and a jack sized for one humidity is wrong by as much as the moment it removed at another. Held to what the joint can take uncracked, it cancels about half.
Named alongside it
The objects these essays reach for when they reach for this one.
CreepServiceabilityImposed deformationPrestressRelaxationConstruction sequenceCamberDifferential shorteningMinimum reinforcementTensile strengthAgeingComposite action