Internal forces

The steel decides how many, not how much

A wall cast on a base that has already set cools, tries to contract, and is not allowed to. What follows is not a stress problem with a strength on the other side of it. The movement is going to happen; the only question the reinforcement gets to answer is how many pieces it is divided into.

Assumes The movement nobody applied, The same steel, and a wider crack and The steel the concrete asks for.

A retaining wall is poured against a base slab that went in three weeks earlier. Over the next two days the wall heats itself to about forty degrees above ambient, because cement hydrating is an exothermic reaction and four hundred millimetres of concrete has nowhere to put the heat. Over the following week it cools back down. It would like to get shorter by three or four hundred microstrain while it does so.

The base will not let it. The base is cold, hard, and considerably stiffer in its own plane than the wall is, and it is connected to the wall by a kicker and a mat of starter bars. So the wall cracks — vertically, at intervals of a few metres, right through its thickness, before anything has been backfilled behind it and before any load has been applied to it at all.

Restraint is a fraction, and the length decides how far up it reaches. A 20 m wall 3.0 m high cast against a base that has already hardened — a length-to-height ratio of 6.67. The base holds the bottom of the wall at R = 0.50 and the top of it at 0.304, decaying as 0.609 to the power of the height in wall heights. The free contraction is 380 microstrain, of which 84 per cent is the wall cooling from its own hydration peak and the rest is drying; the concrete's own strain capacity is 50. Everything to the right of the dashed line cracks, which here is the bottom 3.00 m of it. Nothing has been loaded.
Fig. 1 A 20 m wall 3 m high on a base cast three weeks before it. The restraint factor is 0.5 at the joint and 0.304 at the top, falling as 0.609 to the power of the height in wall heights — a decay whose rate is set by the length-to-height ratio of 6.67 and by nothing else. The free contraction is 380 microstrain, 84 per cent of it the wall cooling from its own hydration peak, against a strain capacity of 50. The whole height cracks: thirty-two cracks, 0.10 mm each.

This is the commonest structural crack in the world and it is not caused by a load. The rest of this essay is about what that changes.

The free body is the wall, and the thing acting on it is a length

Cut the wall free of its base and lay it out. It has a length it wants to be — the length it was cast at, less the contraction — and a length it is allowed to be, which is the length of the base. The difference is imposed, and the whole problem is contained in that word.

εfree=αΔT+εcs=10×106×32+60×106=380 με\varepsilon_{\text{free}} = \alpha\,\Delta T + \varepsilon_{cs} = 10\times10^{-6}\times32 + 60\times10^{-6} = 380\ \mu\varepsilon

with 84 per cent of it thermal and the rest early drying and autogenous shrinkage. That is what the concrete would do unrestrained. What it is permitted to do is (1R)(1-R) of it, and the rest turns into strain the material has to find somewhere.

The restraint factor RR is the number the whole calculation hangs on, and it is neither one nor zero. A member held rigidly at both ends carries EαΔTE\alpha\Delta T with no dimension in it at all — a stress independent of length, area and second moment. That is the case at R=1R = 1, and it is not this case. A base slab is stiff but not rigid; it can strain a little in its own plane, and the wall can slide on it slightly, and the joint between them is a construction joint rather than a weld.

It moves, or it pushes. Never both, and never neither. A 20 m steel member 32 °C warmer than it was built, in three conditions. Free, it grows 6.4 mm and carries nothing. Held, it moves nothing and carries 9.9 MPa — which is E·α·ΔT and contains neither the length nor the area of the member, so the identical stress arises in a two-metre strut. Held by a spring it does some of each: 5.5 mm of movement and 1.4 MPa, and the split is decided by the spring rather than by the member.
Fig. 2 The two extremes the real case sits between: free to move, so a movement and no stress; held completely, so a stress and no movement. Everything about a restrained wall is a point on the line joining them, and the position of that point is not a material property — it is a fact about what the wall was cast against.

For a wall on a base, measured values cluster around 0.5 at the joint, and creep at early age relieves roughly a third of whatever stress does develop, because concrete two days old is very much more creep-prone than concrete two years old. The stress that actually arrives is

σ=KRεfreeEcm=0.65×0.5×380×106×31,000=3.83 N/mm2,\sigma = K R \varepsilon_{\text{free}} E_{cm} = 0.65 \times 0.5 \times 380\times10^{-6} \times 31{,}000 = 3.83\ \text{N/mm}^2,

against EαΔT=67E\alpha\Delta T = 67 N/mm² for the fully restrained case with no creep. A factor of seventeen separates the textbook expression from the number, and the factor is made of two things neither of which is in the expression.

The stress that leaks away. A restrained shrinkage strain of 300 microstrain in concrete of modulus 32000 N/mm². Ignoring creep it produces 9.60 N/mm², which is above the tensile strength of 3.5 and predicts that every restrained concrete member ever cast has cracked. Counting creep by the superposition integral leaves -0.07 N/mm² after 27 years, and the one-line age-adjusted shortcut at the usually quoted ageing coefficient of 0.8 leaves 2.20. The two disagree — this creep function implies an ageing coefficient of -31.50, not 0.8 — and both are below the tensile strength, so the conclusion turns on counting creep at all rather than on how it is counted.
Fig. 3 Why the stress is smaller than the strain suggests. When a strain is imposed and held, the stress that answers it leaks away — and concrete at two days is at its most obliging. The relief factor of 0.65 used here is that curve reduced to one number, and it is the least defensible number in the calculation.

It still cracks

3.83 N/mm² against a tensile strength around 2.4 is not a close call, and the comparison is better made in strain than in stress because the strength is not the quantity that varies most.

εctu=KfctmEcm=0.65×2.431,000=50 με\varepsilon_{ctu} = \frac{K f_{ctm}}{E_{cm}} = \frac{0.65 \times 2.4}{31{,}000} = 50\ \mu\varepsilon

against a restrained strain of Rεfree=190 μεR \varepsilon_{\text{free}} = 190\ \mu\varepsilon: a factor of 3.78. There is no arrangement of reinforcement that prevents this, and no realistic concrete mix either, because the tensile strength gains more slowly than the heat arrives — the peak temperature is at two days and the strength at two days is about two thirds of its 28-day value.

The strength that does not keep pace. Concrete's mean tensile strength against its characteristic compressive strength, with the ratio of the two on the same axis, scaled. The tensile strength goes as f_ck^⅔, so it rises from 1.57 to 5.04 N/mm² over a sixfold rise in the compressive strength, and the ratio between them falls from 11.1% at C20 to 6.0% at C80 — a factor of 1.83. Nothing in a bending or a column calculation ever uses the lower curve, and everything that decides a transition does: when the section cracks, how much minimum steel it needs, how far a bar has to be lapped, what a member without links carries. So a stronger concrete needs more minimum reinforcement, longer laps and a bigger crack-control check, in a member whose ultimate capacity has barely moved. Its real scale is a length: E·G_F/f_ct² is 275 mm here, which is the size at which a member stops behaving plastically and starts behaving like a fracture problem.
Fig. 4 The strength that does not keep pace. Compressive strength is what a mix is specified by and tensile strength is what decides this, and the second grows as roughly the two-thirds power of the first — so a stronger mix buys proportionately less tension, and buys it having generated more heat to get there. Specifying C40 instead of C30 to control early cracking makes it worse in both terms.

So the wall is going to crack. The design decision is not whether.

The conservation statement

Here is the argument that makes this problem different in kind from every other crack calculation on this site.

A crack in a beam opens because the steel across it stretches under a stress the steel has to carry. Give the beam more steel and the stress falls, the strain falls, and the crack narrows: the same steel in smaller bars gives a narrower crack and more of it gives a narrower one still. The width is bought.

In a restrained member the applied quantity is a strain. The wall is 20 m of concrete that has to end up 3.30 mm shorter than it wants to be, and every millimetre of that has to appear somewhere: as elastic strain in the uncracked concrete, or as crack. Sum along the length:

w=(Rεfree12εctu)L=164.8×106×20,000=3.30 mm.\sum w = \left(R\varepsilon_{\text{free}} - \tfrac12 \varepsilon_{ctu}\right) L = 164.8\times10^{-6} \times 20{,}000 = 3.30\ \text{mm}.

There is no steel in that expression. No area, no diameter, no spacing, no yield strength. The total opening is a strain times a length, and both are properties of the pour and the ground plan.

The steel decides how many cracks, and never how much movement. Crack width and crack count against the reinforcement ratio, for a restrained wall whose total movement is fixed at 3.3 mm by the strain it was not allowed to make. The two curves are reciprocals of one another by construction, because their product is that total and the total contains no steel. At 1.11 per cent the wall makes 32 cracks 0.10 mm wide; at twice the steel it makes about twice as many, half as wide. Reinforcement in a restrained member is not resisting anything. It is dividing a movement that was going to happen into pieces small enough to be acceptable.
Fig. 5 Crack width and crack count against reinforcement ratio, for a wall whose total movement is fixed at 3.30 mm. The two curves are exact reciprocals because their product is a constant that contains no steel. At 1.12 per cent the wall makes 32 cracks of 0.10 mm; at twice the steel it makes about twice as many, half as wide.

So the reinforcement is not resisting anything. It is a divider. It sets the crack spacing, the spacing sets the width, and the number of cracks is whatever the total requires. This is why the check on a restrained member is written as a crack width and never as a stress, and why the answer to the cracks are too wide is more bars and smaller ones rather than more steel.

The spacing is a bond length

What the steel actually controls is how far along the wall the concrete has to go before the bars have handed enough force back into it to crack it again. That distance is

sr,max=3.4c+0.425k1k2ϕρp,eff,s_{r,\max} = 3.4c + \frac{0.425\,k_1k_2\,\phi}{\rho_{p,\text{eff}}},

a cover term and a bar term. For the wall drawn — 40 mm cover, 16 mm bars at 150 on both faces — it is 623 mm, of which the cover contributes 136 and the bar 487.

The bond stress is crowded against the loaded end. A 16 mm bar embedded 296 mm, with the force in it and the bond stress on it plotted along the embedment. Uniform bond — the assumption behind every development length ever tabulated — is a flat stress and a straight line of force. An elastic bond of the same peak strength is neither: the slip is largest where the bar is pulled and dies away over 1/α = 422 mm, so the far end of the bar is doing almost nothing. At the code's own length of 19 diameters the elastic bond is 86 per cent used. The uniform answer is what the bond looks like after it has yielded along the whole length, which is a statement about ductility rather than about strength.
Fig. 6 Where the second term comes from. After a crack, the bar carries everything across it and hands force back to the concrete through bond over a transfer length; the concrete cannot crack again until it has recovered its tensile strength, which takes that length. The transfer length is proportional to the bar diameter and inversely proportional to the steel ratio, which is exactly the second term above.

The bar term dominating is why bar size is the effective variable rather than bar area. Halving the diameter at constant area halves the spacing, halves the width and doubles the count, and costs nothing except more bars to fix.

The steel that is needed for a different reason

There is a separate and prior check, and it is the one that decides whether the wall gets thirty cracks or one.

The steel that is sized by the concrete. Ultimate moment of a 1000 × 400 mm section against the area of tension steel in it, with the moment that cracks the section drawn across. The cracking moment is 77.2 kNm and contains no steel at all — it is f_ctm times the gross section modulus, 2.90 N/mm² times bh²/6 — so it is a horizontal line, and every section to the left of where the two meet is one whose first crack is its failure. The crossing is at 507 mm², and rearranging the two expressions gives 0.245·(f_ctm/f_yk)·bd against the 0.26 the codes print — the constant is a section modulus divided by a lever arm and not a fitted number. The rule as printed asks for 538 mm² here, which is 6% more than the derivation needs, and that margin is the whole of the safety in a check whose failure mode is sudden.
Fig. 7 The steel the concrete asks for, which is sized by the concrete’s own tensile strength and not by any applied action. At the instant a crack forms the force the concrete was carrying transfers to the bars across it; if they cannot take it without yielding, they yield, that crack takes the entire movement, and the wall has one crack several millimetres wide instead of many small ones.

For the wall here, As,min=0.8fctmAct/fyk=922A_{s,\min} = 0.8 f_{ctm} A_{ct} / f_{yk} = 922 mm²/m against 2,681 provided, a ratio of 2.91. This is the check that makes the conservation statement useful rather than terrifying: the total opening is fixed either way, and the only thing standing between thirty-two cracks of a tenth of a millimetre and one crack of three and a quarter is enough steel to survive the first one.

Why a short wall does not crack

The restraint factor falls with height, and the rate it falls at is not a material property or a joint property. It is geometry.

R(z)=R0kz/h,k=L/h2L/h+1R(z) = R_0\,k^{z/h}, \qquad k = \frac{L/h - 2}{L/h + 1}

At a length-to-height ratio of 2 the base of that exponent is exactly zero: the top of the wall is entirely free, because a wall as short as that can rotate and bow on its base rather than being held by it. At 6.67 the base is 0.609 and 30 per cent of the restraint survives to the top of the wall. The consequences are large and discrete:

L/hL/h restraint at the top cracked height cracks
2.0 0.000 50 mm 0
3.0 0.125 2.90 m 14
4.0 0.200 3.00 m 19
6.67 0.304 3.00 m 32
13.3 0.395 3.00 m 64

A wall is restrained by being long. The length does not appear in the strain — a 6 m wall and a 60 m wall cool by the same amount and want to contract by the same 380 microstrain each — but it appears twice in the consequences: once in how much of the height is held, and once as the multiplier on the total opening.

The stress has no length in it and the movement is nothing but length. Stress and movement against member length, for a 32 °C change. Held rigidly, the stress is 9.9 MPa at every length there is — E·α·ΔT, with no L, no A and no I anywhere in it. Held by a spring of 100 kN/mm the answer climbs with length rather than falling, because a longer member hands the same spring more movement to absorb: 8% of full restraint at 10 m and 33% at 60 m. The free movement, plotted to its own scale, reaches 19 mm.
Fig. 8 The same asymmetry stated generally. The restrained stress has no length in it whatever; the movement is nothing but length. Restraint cracking is the case where both statements are live at once, and the design response — a movement joint — works by attacking the second.

This is where movement joints come from, and it explains the spacing they are put at. A joint every two wall heights takes every panel to L/h=2L/h = 2 and the top of the exponent to zero. That is not a rule of thumb: it is the point where the ACI distribution goes to zero, and the reason the rule is stated as a multiple of the height rather than as an absolute length.

It also explains an observation that puzzles people on site, which is that the deepest walls crack least. A 6 m basement wall in a building with a 40 m plan is at L/h=6.7L/h = 6.7 and cracks throughout; the same 40 m of plan in a 1.2 m upstand is at L/h=33L/h = 33 and cracks four times as often. Height is working in the numerator of the restraint and in the denominator of the crack count at once, and both directions favour the deep wall. Nothing about the concrete has changed.

The joint itself is worth being honest about. It is a plane of weakness deliberately introduced so that the movement collects at a place where it can be sealed rather than distributing itself where it cannot, which puts it in the same family as a hinge put into an arch on purpose — a restraint given up in exchange for control of where the consequence lands. And like that hinge it is not free: a joint is a maintenance item, a leakage path and a discontinuity in the reinforcement, and the alternative of accepting many fine cracks and relying on autogenous healing is a legitimate design and increasingly the usual one.

The width the wall actually gets

The number that goes on the drawing is the crack width, and it is worth seeing what moves it.

The same steel, and a crack three times as wide. Calculated crack width against bar diameter, with the area of steel held at 1340 mm² per metre throughout — so the spacing changes with the square of the diameter and the amount of reinforcement does not change at all. The width runs from 0.173 mm at 8 mm bars to 0.372 at 25, a factor of 2.15 for identical steel. The reason is in the crack spacing: after a crack forms the bar has to re-anchor the concrete's tensile force before the next one can, and the length that takes is proportional to the bar's diameter. Of the 337 mm spacing drawn, 35% is the cover term and 65% is the bar term — and the cover term is the one that puts crack control and durability in opposition, because cover protects the bar and widens the crack that reaches it.
Fig. 9 Crack width against bar size at constant steel area, which is the variable with the most leverage on this problem and the least cost attached to it. The steel ratio and the cover are the other two, and the cover fights durability: deeper cover is a longer transfer length and a wider crack, and shallower cover is a shorter life.

For a wall retaining water the limit is often 0.2 mm and for one retaining soil 0.3, and the wall drawn is at 0.10 with a factor of two in hand. Halving the bars to 8 mm at 75 would take it to 0.063 and fifty-three cracks; going to 25 mm at 365 would take it to 0.148 and twenty-two. Both are the same wall moving by the same 3.30 mm.

Where the model stops

The temperature drop is one number. It is not: the wall has a temperature profile through its thickness and a history in time, the surface cools first and the core later, and there is an internal self-equilibrating stress from that gradient on top of the external restraint. A thermal gradient produces stress with no restraint at all, and the two effects superpose at exactly the age when the strength is lowest.

The restraint factor is a distribution and it is drawn as a curve. Real edge restraint also varies along the length — highest at mid-length, falling toward a free end — so the first crack forms near the middle and the ends may never crack. The ACI expression captures the height variation and says nothing about the length variation.

Creep is one factor. K=0.65K = 0.65 is a whole relaxation calculation compressed to a number, and it is a function of the age at loading, the maturity, the mix and the section thickness. It is also the number the answer is most sensitive to that is least measured.

The crack spacing formula is borrowed. It was derived and calibrated for flexural cracking under sustained load, where a steel stress exists to be plugged into it. Here there is no steel stress until after the crack forms, and using the same expression is a convention rather than a derivation.

The wall is treated as a bar in tension. It is not: it is a plate held along one edge, so the strain it is prevented from making varies over its face in two directions and the cracks that result are tapered rather than parallel-sided — widest at the base and closing toward the top, in the way a member restrained continuously rather than at points distributes its response over a length it chooses for itself. The single width reported here is the width at the joint, which is the right place to report it and is not the width anywhere else.

And the section is uncracked in bending throughout. A retaining wall gets backfilled, and the flexural cracks that then arrive are on the earth face at the base — the same face and the same region where the restraint cracks already are. The two crack patterns superpose, the code check treats them separately, and nothing in either calculation knows that the concrete it is about has already been divided into thirty-two pieces by the other one.

And the pictures cannot show the wall doing it. Every figure here is a state — a restraint profile, a width, a count. The event is a week long, the cracks arrive one at a time in an order the drawings do not attempt, and the second crack forms where the first one has finished handing its force back. A drawing of thirty-two evenly spaced cracks is a drawing of the end state of a sequence, and the sequence is where the spacing actually comes from.

The ladder from here

Later rungs on this anchor: the temperature history itself, computed rather than assumed, from cement content, section thickness and formwork type — which is the one input a designer genuinely controls. End restraint as against edge restraint, where a wall cast between two completed panels has RR near 0.8 uniformly and behaves entirely differently. The sequence question: bay sizes, pour order, and whether the infill bay or the first bay is the one at risk. Restraint from piles rather than from a base, where the wall is held at points and the crack pattern is a fan. Long-term shrinkage arriving years after the thermal event, adding to a member that has already cracked and widening what is there rather than making new ones. And the same argument wherever a strain is imposed on something that cannot move — a composite deck restrained by its studs, a continuous slab held by friction on the ground, and every jointless bridge deck ever built.

Named alongside this one

Essays reaching for the same objects. Nobody chose these; they are what the concept index makes visible.

What links here

Every essay whose body links to this one.

The objects this essay names

Each one links to every other essay that touches it.

BondCrack spacingCrack widthMinimum reinforcementRestraintSelf equilibratingServiceabilityThermal movement