Concept

Cover — where it appears

The thickness of concrete between a reinforcing bar and the nearest face. It sets how long a carbonation or chloride front takes to reach the steel, as a square of itself, and it sets the pressure the surrounding concrete can take before a corroding bar splits it.

Named by 6 essays across 3 fields — each of them below, with the objects they name alongside it.

Four inequalities, and the wedge between them. The Magnel diagram: every limit on a prestressed section, plotted as a bound on 1/P against the eccentricity. Two of the four come from transfer, when the force is largest and the only moment is the beam's own weight, and two from service, when 20% of the force has been lost and the moment is 640 kNm. Each is linear in 1/P, which is the substitution that makes the problem a picture rather than a search. The shaded region is every force-and-eccentricity pair the section will accept: it is a wedge opening to the right, so the cheapest prestress is always at the largest eccentricity the cover allows — 1029 kN at e = 400 mm here. The section's kern is 241 mm, and every useful answer is outside it.

Four inequalities and a wedge

A prestressed section has to satisfy two stress limits when the force is largest and the load smallest, and two more when the force has relaxed and the load has arrived. Each is linear in one over the force — which turns a search for a prestress into a region on a page, and turns an impossible section into an empty one.

sections · Prestress limits
Cover enters twice, and the strength of the concrete enters once. How long a 20 mm bar has before the cover over it splits, against the cover, split into the two halves it is always split into. Initiation is the time for the chloride front to reach the bar, which goes as the square of the cover — Fick's law and nothing else — and it is 9.1 years at 35 mm and 36.2 at 70. Propagation is the time from there to a split cover, which is short: 0.9 years, because the cover cracks at a section loss of 0.21% and no strength check in this collection would notice a loss that small. The pressure the cover can take grows with the cover too, so cover appears in both terms and the concrete's own tensile strength appears in one of them, linearly. That asymmetry is why every durability clause in every code is about cover and crack width, and hardly at all about strength.

The load that comes from inside

Every action in this collection has been applied from outside — a weight, a pressure, a movement, a temperature. Corrosion is not applied at all, and the reason it belongs to statics rather than to durability is that what does the damage is a load: rust occupies three times the volume of the steel it came from, and the only place to make room is by pushing the cover apart.

materials · Corrosion
The neutral axis is wherever the first moment vanishes. A 300 by 600 section with 1800 mm² of steel at a depth of 540, carrying 250 kNm after the tension side has cracked. The neutral axis is no longer at mid-depth: it has risen to 234.5 mm from the top, which is where the first moment of the compression zone plus the transformed steel vanishes. The compression is 15.4 N/mm² at the top fibre and the steel carries 301 N/mm²; the resulting couple is 541 kN on a lever arm of 462 mm, which multiplies back to the 250 kNm applied. The uncracked section would have had 6673×10⁶ mm⁴ against the cracked 3809×10⁶ — a loss of 43% of the stiffness.

Where the steel is, not how much of it

A section in bending resists a moment with a couple, and a couple is a force times a distance. The force is bought — it is an area of steel at a stress. The distance is free, decided by where the bars were put, and it is the variable almost nobody optimises because it does not appear on an order.

sections · Lever arm
A base plate, and when the bolts start working. A 500 × 500 mm plate carrying 600 kN and 180 kN·m, so the resultant sits 300 mm from the centre against a kern of 83.33 mm. The plate is in bolts engaged: bearing over 150.88 mm at a peak of 20 N/mm², with the holding-down bolts carrying 154.42 kN. The plate lifts at 50 kN·m and crushes at 126 kN·m, and the bolts are not needed until 150 kN·m.

The failure that is in the concrete

An anchor bolt is a steel component and its capacity is usually decided by something else entirely — a cone of concrete pulled out around it, failing in tension, in a material every other calculation on the project has assumed cannot take tension at all. The exponent in the capacity says so: it is not the square the geometry implies.

connections · Anchor breakout
The dimension the capacity rides on is not a drawn dimension. Moment capacity of a 225 mm slab against the cover to the reinforcement. The line is very nearly straight, because capacity is A_s·f_yd·z and z is about 0.9d — so the capacity is proportional to a dimension that is not on the drawing. What is on the drawing is the overall depth, and the effective depth is what the cover, the link and half a bar diameter leave of it: 225 − 30 − 0 − 8 = 187 mm here. Every one of those three is a site tolerance rather than a design decision. Ten millimetres of bar position is 5.7% of this slab's capacity and 1.8% of a 600 mm beam's — the same workmanship costs 3.0 times as much in the shallow member, and the shallow member is the one whose steel is walked on before the pour.

The dimension nobody can measure

Every flexural capacity in reinforced concrete is proportional to the effective depth, and the effective depth is not on the drawing. It is what is left of the thickness after a cover, a link and half a bar diameter have been taken off it — and each of those is a site tolerance. In a slab, ten millimetres of workmanship is six per cent of the strength.

sections · Effective depth
The same steel, and a crack three times as wide. Calculated crack width against bar diameter, with the area of steel held at 1340 mm² per metre throughout — so the spacing changes with the square of the diameter and the amount of reinforcement does not change at all. The width runs from 0.173 mm at 8 mm bars to 0.372 at 25, a factor of 2.15 for identical steel. The reason is in the crack spacing: after a crack forms the bar has to re-anchor the concrete's tensile force before the next one can, and the length that takes is proportional to the bar's diameter. Of the 337 mm spacing drawn, 35% is the cover term and 65% is the bar term — and the cover term is the one that puts crack control and durability in opposition, because cover protects the bar and widens the crack that reaches it.

The same steel, and a wider crack

A crack's width is the distance between cracks times the strain the steel carries over that distance. Neither of those is decided by how much reinforcement there is. The spacing is a bond length, so it goes as the bar diameter; the strain is set by the stress in the steel. Two arrangements of identical steel can differ by a factor of two in crack width, and the one that wins is the one with more, smaller bars.

sections · Crack width

Named alongside it

The objects these essays reach for when they reach for this one.

BondDurabilityPrestressSection modulusTensile strengthAnchorageCharacteristic strengthCorrosionCrack widthCracked sectionEffective depthLever arm