The arm that calls for its own visit
Assumes The arm that makes the columns work, The deflection that arrives three years late and The columns are shorter than the core.
The arm that is reset by hand took the outrigger of a 200 m concrete building, connected late so that the construction-stage creep had already gone, and found that the creep still to come would put 3.48 MN into each arm over fifty years — three fifths of the 5.80 MN the arm was designed to carry in the wind. The older remedy is a joint closed with shims and opened every few years: the arm lets go of its force, the shims are changed to take up the differential since the last visit, and the arm starts collecting again. Visits at one, three and ten years held the arm below 1.40 MN, and spaced like the creep — geometrically — they did it with about equal thicknesses of shim each time. Evenly spaced from five years, the same three visits held it only below 2.48.
The dates in that schedule came from a calculation: the creep of every storey of the core and the columns, from a code’s creep function, the building’s own construction programme and its working stresses. The essay ended on what a measurement could do instead. A joint with a load cell in it tells its owner how much creep force the arm is holding, and a visit could be made when the force reaches a chosen limit rather than on a date. Whether a limit as low as a tenth of the wind could be held with a reasonable number of visits, and whether the first year after connection, when the creep is fastest and the building is busiest being fitted out, could be served at all by a schedule that waits for the force to arrive, was the question.
A visit when the load cell says
The building and the arm are the earlier essay’s: 55 storeys built at one a week, fitted out over six months, the outrigger at three quarters of the height with a rotational stiffness of kN·m a radian and its columns 30 m apart, connected on day 385. Every storey of the core and the perimeter columns creeps under each load increment it receives, from its own casting date, by Eurocode 2’s creep function, and shrinks by its shrinkage function; the differential at the arm’s level is the columns’ shortening less the core’s, and the arm resists it through its own stiffness in series with the concrete that carries its force, which also creeps.
A re-shimming opens the joint, lets the arm’s force fall to nothing, and closes it again with new shims. The concrete that was carrying that force is unloaded, and it recovers the creep of that unloading over the following months, which the arm then collects as well. The schedule is no longer a list of dates. It is found one visit at a time: run the creep with the visits so far, find the first day after the last visit on which the arm’s force reaches the limit, and make the next visit then.
Three visits that find their own dates
Set the limit at 1.40 MN, the force the dated schedule held, and the measured schedule needs the same three visits. It puts them at 12 months, 4.1 years and 22.7 years rather than at one, three and ten. The first visit falls on the same day; the second and third come later, because the dated schedule’s later visits were made before the arm had reached its limit — each of them gave back less than it could have, and the arm then took longer to come back. Waiting for the force spreads the visits out further, the later the more, because the creep is slowing all the time and the time it takes to put 1.40 MN back into the arm grows with every year.
This is the earlier essay’s geometric spacing, found by the building rather than by a calculation. There the visits spaced like the creep held the arm better than evenly spaced ones; here the arm spaces them like the creep by construction, because each visit is triggered by the creep itself.
How low a limit can go
The number of visits rises as the limit falls, and more slowly than might be feared. Holding the arm at 1.00 MN takes four visits; at 0.58 MN, a tenth of the design wind, eight; even at 0.40 MN, twelve. Fifty years is a long time and the creep’s rate falls quickly, so most of a low limit’s visits are spent early, when the building is young: the tenth-of-the-wind schedule makes its first visit five months after connection and its eighth twenty-five years after.
So a low limit is not out of reach by count. Eight visits in fifty years, each a day or two of opening one joint, is an ordinary maintenance item for a tall building; the earlier essay’s arm that slips on purpose, a damper or friction joint that lets the creep through continuously, does the same job with a machine that has to be maintained instead. The count is not the problem. The timing is.
Where the visits fall
Drawn as dates, the visits a limit calls for make the creep’s own clock visible. Each limit’s visits stand at roughly equal steps on a logarithmic axis of time — at a tenth of the wind every visit one and a half to two and a half times as long after connection as the one before, at 1.40 MN four or five times — because the creep function rises roughly with the logarithm of the time since loading over the decades that matter here. A lower limit packs more visits onto the same logarithmic spacing; it does not change its shape.
The first of those steps are where the question about the first year lives. At a tenth of the wind the first three visits come at 5, 7 and 13 months after connection: in the year the building is being fitted out and occupied, when the outrigger floor is a plant room full of new services and access to a joint means scaffolding round a working installation. A schedule that waits for the force must be able to reach the joint at a few months’ notice in exactly the year that is hardest.
When the building does not creep as predicted
The real case for a load cell is that the prediction is wrong. A creep function is fitted to laboratory specimens, a building’s concrete differs from the mix in the specification, its working stresses depend on the loads actually placed, and the humidity of its interior on how it is used. A calculation of column shortening that lands within thirty per cent of what is later measured is usually counted a good one; the columns are shorter than the core set out how many independent parts go into it.
Scale the building’s shortening from 0.7 to 1.6 times the prediction and the dated schedule’s outcome scatters with it. A building that creeps less than predicted is held at 1.04 MN, with visits that were partly unnecessary. One that creeps 60 per cent more reaches 2.30 MN, nearly two fifths of the design wind, with the arm’s capacity for wind reduced by that much. Re-shimmed at a load cell reading of 1.40 MN, every one of those buildings stays at 1.40.
What varies instead is the number of visits, which is the right thing to vary: a building that creeps more is visited more. At 1.40 MN it takes two visits if it creeps at 0.7 of the prediction, three as predicted, four at 1.6 times. At a tenth of the wind, six to twelve. The schedule spends its visits where the building’s creep turns out to be, which a list of dates fixed before the building was built cannot do.
The days between the alarm and the visit
A visit cannot be made on the day the load cell reads its limit. A contractor has to be found, access arranged, the joint’s cover removed, shims cut. The figure prices the delay. With a limit of 1.40 MN the delay hardly matters: by the time the force has crept to that level the creep is slow, and a visit made three months late lets it run to 1.51, eight per cent over. With a limit of a tenth of the wind the same delay is ruinous: a month’s wait lets the force reach 0.77 MN, a third over; three months, 1.16, double the limit; six months, 1.34, nearly the force a 1.40 limit would have held anyway.
The difference is the first year again. A low limit’s first visits come while the creep is fast, and a week’s delay then is worth a year’s delay at twenty years. So the answer to the earlier essay’s question is conditional: the first year can be served by a schedule that waits for the force, but only by an owner who can open the joint within a fortnight of the alarm, three times in a year. Otherwise the realistic choice is a limit set where the delay does not matter — near the 1.40 MN the dated schedule already reached — or a joint that does not need a visit at all.
The first interval, by rate
The reason the first year is so different from the rest can be read off the arm’s force without any schedule at all. Left alone after connection, the arm collects about 5 kN a day through its first seven months — the fit-out is still going on, every new partition and plant item is a new load increment on the columns, and each increment’s creep is at its fastest. Between the first and second years it collects about 1.1 kN a day; between ten and twenty years, 0.09; between twenty and forty, 0.03. The rate falls by a factor of more than a hundred and fifty over the building’s life, and a force limit converts a rate into an interval: at a tenth of the wind the interval between the second and third visits is 71 days, between the fifth and sixth 801, between the seventh and the eighth fifteen years.
That is the earlier essays’ observation turned into a maintenance contract. The arm connected late waited until the building was topped out before making the joint, so that the construction’s own shortening went by unresisted; the creep after connection is the remainder, and most of the remainder arrives in the first two years, when the finishes are going on and the building’s early concrete is still young. The deflection that arrives three years late found the same shape in a beam that goes on deflecting for a decade, fastest at first: and a structure that has to accommodate creep accommodates most of it in the years when the building is newest and its owners least inclined to open it up.
What the drawing has to say instead
A dated schedule is written on a drawing as three dates. A measured one has to be written as a specification, and it has more parts: a load cell in the joint, of a type whose drift over decades is known and which can be checked when the joint is opened; a force at which a visit is called; a reading rule that takes the wind and the seasons out — the mean of a calm week, or of a month; and a response time within which the visit must be made, which the last figure says is the part that matters most when the limit is low. The limit and the response time are a pair, and they should be chosen together: a limit near 1.40 MN tolerates a response of a quarter of a year, a limit of a tenth of the wind needs one of a fortnight.
It also changes what the designer is asked to predict. With dates, the designer predicts the creep and the schedule is only as good as the prediction. With a load cell, the designer predicts only the number of visits, for budgeting, and the spread of that number — two to four at 1.40 MN for a building that creeps between 0.7 and 1.6 times the prediction — is a far smaller uncertainty to carry than a force between 1.04 and 2.30 MN in an arm whose wind capacity depends on it. The arm that makes the columns work set out what the arm buys in the columns’ share of the overturning; the measured schedule guarantees that the arm keeps that share for its whole life, rather than for the life of a prediction.
What the free body is, and what the load cell reads
The free body is the arm and the two pieces of concrete it is joined to: a perimeter column below the outrigger level and the core, which between them carry the arm’s force down to the foundation. The arm is a spring; the concrete is a spring that creeps, so its contribution to the joint’s displacement at any time is the sum over every change of force it has carried of that change times for the age at which it was applied. The imposed movement is the differential shortening at the outrigger level, and the arm’s force is whatever makes the arm’s stretch and the concrete’s creep add up to it. A re-shimming sets the force to nothing and leaves the concrete’s creep history in place, which is why the force starts climbing back faster than it first did: the concrete is recovering the creep of its own unloading.
The load cell reads that force directly, and so it reads everything the calculation guessed at: the actual working stresses, the actual creep of the actual concrete, the actual humidity of the building’s interior. The creep that belongs to the member found how much the creep coefficient depends on a member’s size and its exposure; a load cell does not need to know.
What the schedule leaves out
The load cell is perfect. Real load cells drift, especially over decades, and a joint’s force read by strain gauges on its plates is a measurement of strain with a temperature correction in it. Over fifty years the instrument itself needs checking — the arm’s own response to a known wind, or a lift-off test when the joint is opened, can calibrate it at each visit.
The wind is absent. The arm’s force in a storm is the creep force plus the wind’s, and a load cell reading during a gale reads both. A schedule triggered by a reading has to be triggered by a calm-weather reading or by a reading averaged over enough days that the wind’s fluctuation is out of it.
Each visit returns the arm to nothing. A visit that takes out a little less, because the shims come in fixed thicknesses, starts the next interval with a residual force, and over many visits the residuals add up unless the shim schedule allows for them; the nut turned after the storm found the same arithmetic in retightened bolts.
Temperature is not in the differential. A perimeter column in a façade sees the seasons and the core does not, so the differential swings each year by an amount comparable to a few months’ creep. A load-cell limit read in winter and summer will call for visits at different times of year, and the limit itself should be read against a seasonal correction.
Still open: the second arm
Every building here has one outrigger level. Tall buildings often have two or three, and what the second arm is worth found that they share the wind between them by their stiffness. They share the creep differently: each arm collects the differential at its own level, which grows with height, and re-shimming one arm changes the forces in the core and columns between the levels and so the force the other arm is collecting. Whether a building with two measured arms should visit them together, when either reads its limit, or separately, each by its own load cell — and whether visiting one arm brings the other to its limit sooner, so that the visits come in pairs whatever the plan — needs both arms and the concrete between them followed through the same fifty years.
Named alongside this one
Essays reaching for the same objects. Nobody chose these; they are what the concept index makes visible.
- The arch that waits with its hinges open construction sequence · creep · relaxation
- The floor that is level on one date construction sequence · creep · differential shortening
- The jack that creep carries past the mark construction sequence · creep · relaxation
- The section that changed while it was being loaded construction sequence · creep · differential shortening
- The survey that arrives after the floors construction sequence · creep · differential shortening
- Built to the wrong shape on purpose construction sequence · creep
The objects this essay names
Each one links to every other essay that touches it.
Construction sequenceCreepDifferential shorteningInspectionOutriggerRelaxation