Plastic hinge — where it appears
Named by 52 essays across 9 fields — each of them below, with the objects they name alongside it.
After the first yield, which is not the end
A steel beam whose extreme fibre has reached yield has not failed. It has started forming a hinge, and collapse waits until there are enough hinges to make a mechanism.
The property that appears in none of the equations
Ductility is in no design formula on this site. Every method on this site depends on it — and a brittle structure does not merely fail early, it makes the analysis wrong.
The force the bolt never saw applied
Pull a tee stub with a hundred kilonewtons and its bolt carries a hundred and fifty. The extra comes from the flange bending and pressing its own edge against the thing it is bolted to, and no free body of the connection as a point contains it.
The earthquake asks for a displacement
A structure a quarter as strong as the elastic demand does not deflect four times as far. It deflects almost exactly as far, yields on the way, and survives — which is why no ordinary building is designed for the force an earthquake would apply if it stayed elastic.
The slab that spans both ways
A panel supported on four sides sends its load in two directions at once, and the share is decided by a fourth power — so a panel a third longer than it is wide has already stopped being a two-way slab in any useful sense. What it does at collapse is a different calculation with a different answer.
Both at once, and neither matters until it does
A section carrying shear has less moment capacity, and the reduction is the web's share of the plastic modulus times one minus the root of one minus the shear ratio squared. On a rolled beam that share is a quarter, so half the shear capacity costs three and a half per cent — and then the last tenth costs more than the first eight.
The moment that was moved on purpose
The elastic analysis of a continuous beam gives one set of moments. It is not the only set the beam is allowed to have, and taking a smaller one at the support is legal, cheaper, and paid for in a rotation that has to be delivered before the design exists.
The part that is meant to be weak
A braced frame is stiff and has nowhere to yield. A moment frame yields everywhere and is soft. Move the two diagonals a metre apart along the beam and the whole storey shear has to pass through the segment between them — which keeps most of the stiffness and puts every yielding in one member the designer chose.
Squeezed sideways into a different material
Concrete in a cylinder test fails by splitting apart sideways under a load pushing it down. Put a hoop round it and the splitting has to stretch steel — and a lateral pressure of a twelfth of the strength raises the strength by half and the ultimate strain by eight.
Two ways of being wrong
Plastic analysis has two theorems and they point in opposite directions. Any equilibrium field that nowhere exceeds the plastic moment gives a load at or below the collapse load; any mechanism gives one at or above it. Only one of those errors is safe.
What is left after the first fibre yields
The elastic section modulus stops at the moment the outermost fibre reaches yield. Nothing else in the section has, so it goes on taking load — and how much more it takes turns out to be a property of the shape alone, with no dimension, no stress and no material anywhere in the answer.
The point the mechanism turns about
A collapsing frame is a chain of rigid pieces, and every piece is rotating about some point. Find those points and the whole collapse load reads off two ratios of lengths, with no trigonometry anywhere — and for a pitched roof the point in question is well above the top of the drawing.
The smallest of six failures
Everything else in this collection that fails does so in one way at a time. A dowel through timber does not — the wood can crush while the steel stays straight, or one plastic hinge can form in it, or two — and the capacity is the smallest of the six, which is the kinematic theorem of plasticity applied to a joint rather than to a frame.
The steel that is stronger in a millisecond
Every strength quoted anywhere in this collection was measured at about a ten-thousandth of a strain per second, because that is what a testing machine does, and nothing on a drawing says so. Load the same steel a million times faster and its yield stress rises by a third.
The load that is over before it has moved
A blast delivers an enormous pressure for a few milliseconds. Everything else in this field asks what force a structure can carry; a load that has come and gone before the structure has travelled any distance is not asking that question, and the answer turns out to depend on the mass and the ductility with the strength barely in it.
The force the brace leaves behind
Two braces meeting under a beam carry the storey shear as a tension and a compression whose vertical components cancel, so the beam above sees nothing. They cancel only while both braces are elastic. Once the compression brace buckles it sheds most of its force, the tension brace goes on to yield, and the difference is a point load at midspan that nobody applied.
The web that is crushed from inside
A plate girder's compression flange is curved by the beam's own deflection, and a curved force needs a transverse load to stay on its curve. The only thing available to supply it is the web. So a deep girder can buckle its web vertically with nothing applied to it at all, and the rule that prevents it is the only clause in the codes about a load no load case contains.
The analysis that assumes the answer
A rigid frame is indeterminate, so statics cannot finish it. The hand methods finish it anyway, by assuming where the bending moment is zero and treating those points as hinges. That is not a shortcut around the analysis — it is a different kind of answer, exact in equilibrium and wrong in compatibility, and knowing which half is which is what makes the error a bound rather than a mystery.
Two of these move and the third cannot
Cut one span of a continuous beam free and add up the forces on it. What comes out is that the mid-span moment plus the average of the two end moments equals the free bending moment of that span, with nothing else in it — no stiffness, no support settlement, no analysis at all. Continuity moves moment about. It does not reduce the total, and it never has.
The axis that moves when the section yields
An elastic section bends about its centroid. A fully plastic one bends about the axis that halves its area, and for anything symmetric those are the same line — which is why the distinction is almost never met. For a tee they are a fifth of the depth apart, and three things follow that the elastic calculation gives no warning of.
The moment that was shed has to land
Redistribution takes a moment off a beam's support and pays for it with rotation. On a beam that is the whole story. In a frame the support is a column, the shed moment does not vanish, and it arrives at a member whose section was chosen from the diagram it has just left.
The map with three regions
A structure carrying a constant load and a cycling temperature has three possible fates and only one of them is a collapse. It can stay elastic, it can yield once and then stop, or it can gain a little more deformation every cycle for ever — and the third has no failure load at all.
The wide side goes inside
A crane hook's section is a trapezoid with its broad face towards the centre of curvature, and that is not a casting convenience. Turn the same section round — same area, same depth, same moment — and the stress at the fibre that breaks rises by thirty-nine per cent. The shape is doing two things at once, and only one of them is in a straight beam's arithmetic.
The tension has to pull on something
A buckled web carries its shear on a diagonal band of membrane tension, and the band pulls sideways on the flanges and stiffeners that bound it. That pull is the design output nobody plots — it runs from 72 to 603 newtons per millimetre across ordinary panel proportions, it is largest exactly where the panel is most efficient, and at the end of the girder there is nothing beyond to take it.
Four corners and a mechanism
The check on a hole in a web adds an axial stress to a local bending stress and compares the sum with the yield stress at one corner. What ends the opening is four hinges arriving together — and the gap between the two is a factor that varies along the span from two and a half to exactly one.
The section that governs is inside the haunch
A tapered cantilever has its worst section somewhere along it because the moment grows linearly and the modulus quadratically. A haunched rafter has the same competition with a step in it, and the step is where the check lands — at neither end of the member, at a station no formula names.
The pattern that stopped describing the building
A pushover analysis pushes with a load pattern chosen to resemble the first mode, and by the time the structure has done anything worth analysing it no longer has that mode. Recomputing the pattern as the frame softens changes the base shear by nine per cent and the drift at the fourth floor by a factor of four.
Any structure will carry the unit load
Virtual work has two readings and each is free exactly where the other is bound. A unit load needs only something to stand on in equilibrium, so the deflection of a beam statics cannot solve comes out of a cantilever statics can. A virtual displacement needs only to fit together, so a reaction comes out of pushing a mechanism — and on a redundant beam the unknown cancels out of the equation and nothing is found at all.
The load it can carry once
A two-span beam whose loads come and go span by span collapses at 150 kN under any one arrangement, and walks at 127. Between the two it can carry every arrangement once and none of them forever: each cycle leaves a few more milliradians of rotation at the support and a midspan fifteen millimetres lower. Melan's theorem finds the limit as the last residual moment line that fits, Koiter's as a mechanism no single load state can drive, and a cycle-by-cycle calculation walks exactly where both say it will.
The hinge that forms in the other flange
An end plate bolted to a column flange is two tee stubs sharing one bolt, and the force at their tips is one force pressing on both. Checked separately, as the component method checks them, the end plate carries 109 kN a bolt and the column flange 104. Together they carry 92 — by a mechanism with one hinge in each flange that neither tee stub has on its own.
The face that dents and the core that crushes
A sandwich panel carries bending as a couple between its faces, and that is a calculation about the whole panel. Put a local load on one face — a foot, a fixing, a dropped tool — and the face becomes a thin beam on a soft bed, spreading the load over a length the fourth root of their stiffnesses sets. Then either the face yields and dents, or the core crushes beneath it, and which comes first is decided by one thickness: below it the face gives, above it the core does, and a steel-faced roof panel is on the wrong side of it for anyone who walks on it.
The pull that Johansen left out
Johansen's mechanisms treat a timber fastener as a beam in a bed of crushing wood, bent and pushed sideways and nothing else. A real fastener that tilts across the joint is also pulled along its own axis, and if a washer or a thread resists the pull, it clamps the two members together and adds to what the joint can carry. The addition is a quarter of the axial resistance, it goes only to the modes in which the fastener tilts, and it is capped by fastener type — nothing for a dowel, a quarter for a bolt, all of it for a screw — which is how a screw keeps gaining strength past the thickness at which Johansen's capacity stops.
The screw that is pulled instead of bent
A screw square to a timber joint resists slip by bending, and its thread is engaged only when it has tilted far enough to be pulled. Lean the same screw to 45 degrees and the slip pulls it from the first millimetre. An 8 mm screw through two 100 mm members goes from 5.9 kN to 13.4, reached after 2.2 mm of slip instead of more than twelve, and the bending that Johansen's model is about becomes an eighth of the joint. The price is a joint that holds one way better than the other.
The cable that pays the factor back
A frame that loses a column carries the floor across the gap first by bending and then, as the beam sags, as a cable. The hope is that a path which stiffens as it deflects needs less than the factor of two a suddenly loaded spring does. On the bending plateau it does — 1.18 at nine tenths of the collapse load. But past one depth of sag the cable is a straight line again, and the factor climbs straight back toward two: 1.73 at one and a half times the collapse load. And the connections are asked for a tenth of a radian on the way.
The hinge a squeezed section has to work for
Unloaded, a rectangle carries half again its first-yield moment once it is fully plastic and an I-section only a little more, and the I-section gets there almost at once while the rectangle has to bend four times further. Put a column's axial load on them and both rankings move. The rectangle's reserve grows as 1.5(1 + n), to nearly three times its first-yield moment under heavy compression; the I-section's barely moves. And the I-section loses the thing that made it the beam everyone uses: under three-fifths of its squash load it needs more than five times the curvature to develop its plastic moment that it needs as a beam, because the compression has yielded its web before any bending began.
The beam the wind walks without pushing
A fixed-base portal whose beam carries exactly its collapse load is safe under that load applied once. Add a wind that comes from either side — a wind that does no work at all in the beam's collapse mechanism — and the beam can no longer carry the load for ever: 12 per cent comes off, and above that the midspan gains fifteen milliradians every cycle while the frame does not sway. Each knee takes its worst moment from a different wind, and the beam assembles a mechanism no single storm drives.
The hinge squeezed while it turns
The leeward column of a frame overturning in an earthquake gains compression as its base hinge rotates. Followed fibre by fibre, with every fibre's plastic strain remembered, the hinge does neither of the things the constant-load curves suggest. It forms early, at the low load it started with, and then rides down the section's plastic moment as the load rises: an I-section whose compression goes from a tenth to six-tenths of its squash load holds 0.86 of its unloaded plastic moment at twice its first-yield curvature and 0.43 at twelve times it. The steel never softens, and the hinge still has a falling branch, set by statics. The relieved column on the other side gains what this one loses, less the curvature of the interaction curve.
The coupling beam asked for shear
The coupling beams of a pair of shear walls are the stubbiest members in a building, and the shear term in their deflection is largest exactly there: a beam two metres deep over a 2.4 m opening is a third as stiff as bending alone says. The walls hardly notice. The pair's degree of coupling moves by under 3%, the beams' shears by under 7%, because a beam that stiff has stopped deciding how much of the overturning the walls carry as a couple. What decides it is the shear the beams can give. A 600 mm beam limited to 2 N/mm² starts to yield at 1.9 times the storey force; past the last yield the pair is two cantilevers again, and the beams supply rotation instead.
The base that sends the wind to the knees
A fixed-base portal loses 12 per cent of its load to a wind that reverses, because each knee takes its worst moment from a different storm. Pin the bases and the loss disappears — not because the pinned frame is better, but because its collapse load already contains it. What the bases decide is where the moment goes, and a base that is merely weaker than its column can cost nothing at all, or be made into the part that yields every storm so that nothing else does.
The column that shortens on every cycle
A column hinge bent back and forth by an earthquake carries its share of the building's weight the whole time. In elastic–perfectly plastic steel an I-section at three tenths of its squash load, cycled to three times its first-yield curvature each way, comes back from every cycle shorter by eight yield strains, and goes on doing so: it never settles. The flange that yields in compression shortens, and the other flange, carrying its part of the column's load, never reaches yield in tension to pull it back. A rectangle of the same area shortens a fifth as fast, and the overturning that swings the column's load up and down hardly matters. The weight and the curvature make the ratchet between them.
The roof that makes the wind worse every storm
A portal frame's shakedown check is made on its elastic moments, and the elastic moments a heavy roof sways are larger than first-order analysis says: each storm's wind is amplified by 1/(1 − N/Ncr), on its way out and on its way back. On pinned bases under a 1,000 kN roof that takes the wind at which the knees start to alternate from 110 kN down to 90, and the shakedown load down by 4.8 per cent where gravity leads and 8.4 where the wind does. Fixed bases are worth more under a heavy roof than without one, but by half again, not twice.
The beam that pays the fire back in sag
A steel beam held at its ends and kept straight through a fire yields short on the way up and pulls on its connections with its plastic shortening on the way down. A beam carrying a floor does not stay straight. Squeezed by its own expansion, it forms a hinge at about 500 °C and bows out of the way, hangs as a catenary while still hot, and keeps a metre of sag when it cools — length it no longer has to be pulled for. It ends the fire pulling a third as hard as the straight beam, nearly whatever holds it, and the hard pull comes earlier instead: at 800 °C, on connections that are as hot as it is.
The slab that catches what the joints let go
When an interior column is lost, the beams that crossed over it sag into cables and the slab over the four bays round it sags with them, into a membrane hanging from the floor that did not lose anything. Whether the floor's robustness belongs to its steelwork or to its concrete turns on one number with no span in it: the slab's mesh only starts to carry its full tension when the beams' ends have turned through about 0.09 radians, more than any ordinary joint can follow. So the membrane arrives after the joints have gone. And then it catches the floor — a metre down, alone — and with an ordinary mesh it holds half as much again as the beams could.
The weight that lands somewhere else
A beam that yields under a falling weight takes a permanent set from every drop, and if the weight always lands in the same place the set grows by the same amount every time. Let the weight land somewhere different each time — rocks on a canopy, crates on a deck — and the set still grows: the weight's energy fixes how much plastic work every drop does, wherever it lands. What the landing point decides is where the work goes. Half of every drop's hinge rotation goes under the weight and half to the supports, so wandering drops spread the first half along the span and leave the second half where it always was: the worst hinge turns half as fast, and it is at a support.
The joint stronger than its beam
A full-strength joint never reaches its own resistance: the beam beside it hinges first. But an end plate softens from two thirds of its resistance, and a joint only a little stronger than its beam is already on the soft part of its curve before the beam yields. The softening sheds moment from the beam's end into its span, so it delays the first hinge — by 8 per cent for a joint at 1.2 times the beam's strength, 18 for one at exactly the beam's, and not at all from 1.5 on. It never moves the collapse. And too much shedding hands the first hinge to the span, so the first hinge comes latest at the stiffness where the end and the span yield together.
The floor that cannot keep up with the column
A column whose hinges ratchet under an earthquake shortens every cycle, and in a frame it does not shorten alone: the floors it carries bend down towards it and lift its load onto the columns beside it. That ought to slow it and speed them, until every column shortens together. It does — over hundreds of cycles. Over the ten or twenty of an earthquake, the floors of a six-storey frame lift an eighth of the load off the interior column, it shortens nine tenths as far as it would alone, and the floors carry the whole difference as bending. The frame equalises its columns eventually, and pays for it in its floors.
The wall the twist was said to spare
Give a floor's walls the strengths an elastic push says they need and the far wall, which the push loads most, gets the most. Shake it past yielding and the floor does stop twisting: the twist falls by a third, the standards' ratio drops below its limit, and the plan reads regular. The demand has not gone. It has crossed the floor to the stiff wall on the other side, whose strength the same push had reduced, and which is now asked for more than twice the ductility of the far wall it was thought to be sheltered by.
A hinge one way and a spring the other
A frame whose partial-strength joints have all yielded under gravity looks like a set of beams on hinges standing on pinned columns, and on that reading it has no sway stiffness at all. It stands anyway, and the arithmetic of the hinges is the thing that is wrong. A joint at its hogging limit will not take any more hogging, but sway takes hogging off one end of every beam, and that end answers at its full stiffness. Half the joints the gravity load has spent are still there for the wind. They last only until they run out of range, which is why a critical factor taken from them can be right and tell a designer almost nothing.
The fuse that makes the span work harder
A rock-fall canopy's beams hang on connections weaker than themselves, so it seems natural to let those connections be fuses: let them take the blows, replace them after a bad winter, and keep the beam clean. A falling weight is an energy, though, and a mechanism fixes how far its hinges turn relative to each other. Weaken the ends and each drop's energy has less moment to spend itself against, so every hinge turns further, and the one under the weight turns furthest. Under a big rock the fuse is the part of the beam that does less of the work, and it takes the span a third sooner to its limit. It keeps its promise only for the rocks too small to bend the span at all.
The joint chosen for one wind
A frame's beam carries more moment at one end than the other when the wind pushes, so it seems that each end's joint could be chosen for its own end, softer where the moment is larger, and the beam brought to its plastic moment everywhere at once. Chosen that way the first hinge rises to 94 per cent of the collapse load and no further, because the wind takes off one end what it adds to the other. And the wind turns round.
The cut that follows the moment
Cutting the tips off a square bar set on its corner raises its elastic strength by 5.3 per cent and costs it 6.8 per cent of its stiffness. The strength is only needed where the moment is high, so the cut can stop there, and tapered to the moment it buys the whole gain for a sixth of a per cent of stiffness under a point load. What no placing of the cut can save is the plastic strength, because the hinge forms exactly where the cut has to be.
The round hole that hinges off its centreline
A circular hole in a beam's web is shallowest at its centreline and that is not where it fails. Cut the tees vertically all the way round and the first to yield is 35° round on the side towards the support; the mechanism's four hinges form 30° to 60° either side, wider for a small hole near a support than for a large one at mid-span. The design rule replaces the circle with a rectangle 0.45 of its diameter long and 0.9 deep — too short and too deep — and the two errors cancel to within two per cent along most of the span, but not beside a support, where the rule overstates a small hole by eleven.
Named alongside it
The objects these essays reach for when they reach for this one.
DuctilityMechanismRotation capacityCollapse mechanismShakedownFree bodyLoad pathMoment redistributionPlastic momentRatchetingEquilibriumLower bound theorem