Debonding — where it appears
Named by 5 essays across one field — each of them below, with the objects they name alongside it.
Also named here as pretensioning — the same set of essays touches all of them, so they are one junction rather than several.
The strands that are sleeved at the ends
A post-tensioned tendon can be draped up towards the centroid near the supports, where the self-weight moment that made its eccentricity safe has gone. A pretensioned strand cannot: it runs straight between the abutments of the casting bed. Choose eight strands at 220 mm below the centroid of a 12 m beam and mid-span passes every limit at transfer, while a metre in from each end the top fibre cracks. The cure is to stop some strands gripping the concrete near the ends, and how many is a trade: every strand saved at mid-span by lowering the strands is a strand to sleeve at the ends.
The beam that leaves the bed
A pretensioned beam's debonding is designed for the moment its strands are cut, when the casting bed holds it at its ends and its own weight is the largest relief its top fibre will get. Then it is lifted by loops a little in from its ends and stored on bearers a little further in. Setting the supports a metre in takes 31.5 kN·m off the self-weight moment along the whole length between them, not just at the ends, and the schedule that passed transfer with 0.07 N/mm² to spare has room for 51 mm of it. In the yard's conditions the bearers may come in 0.57 m; a metre in needs a third strand sleeved, and past 2.2 m nothing does.
The beam at the bottom of the stack
A precast yard stacks pretensioned beams to save space, each on bearers resting on the one below. If the bearers line up, the weight above goes straight down through them and the bottom beam never knows it is there. If they land outside its own bearers, the stack hogs the bottom beam at every section between them and takes from its top fibre relief that its debonding schedule had already spent. A schedule built for the yard leaves the bearers of a stack of three seven millimetres to be out of line. A bottom beam with a schedule of its own can be given half a metre.
The beam the haulier holds
A pretensioned beam leaves the yard on a trailer, carried on a turntable and a bogie the haulier places, and bounced on them at road speed. The bounce works both ways: a wheel rising adds to the beam's weight over its overhangs, and a wheel falling away takes weight off — and with it the sag that was relieving the beam's top fibre between its supports. On the yard's own bearers a bounce of 30 per cent takes as much from that fibre as a stack placed 100 mm out of line. A rear overhang of 2.5 m takes five times as much. With the yard's schedule, a trailer may hold this beam only within half a metre and three quarters of a metre of its ends.
The beam hung from its loops
A pretensioned beam is cast in a bed, stored on bearers, hauled on a trailer and then lifted by a crane onto its bearings — and at every stage its top fibre, which the strands put in tension, has to stay inside the limit its debonding schedule was drawn for. The trailer, with a bouncing wheel and supports where the haulier put them, was the harshest stage the yard essays found. The last few metres, from the trailer to the bearings, are gentler: hung from loops at the yard's bearer positions the beam is on its bearers again, set down it is on the support its middle was designed for, and only a slew of the crane pushes it a little past its limit. Where the loops are cast decides how much margin the lift has, and the best place for them is not where the yard put its bearers but where the bed held the beam: at its ends.
Named alongside it
The objects these essays reach for when they reach for this one.
PrestressPretensioningTransferCantileverCable zoneImpact factorLiftingSelf-weightBondDynamic amplificationKernTolerance