Tolerance — where it appears
Named by 16 essays across 6 fields — each of them below, with the objects they name alongside it.
The angle nobody limits
Every serviceability rule in this collection limits a displacement. What a bearing, a joint and a cladding gap actually have to accommodate is an angle — and the angle is locked to the displacement by a coefficient that contains no material, no section and no span.
The angle that doubles the force
A crane hook takes the weight and nothing else. What holds the load is a set of legs running down to it at an angle, and each leg is a two-force member — so at thirty degrees from the horizontal each of two legs carries the entire load, and the difference goes into the thing being lifted as compression.
The dimension nobody can measure
Every flexural capacity in reinforced concrete is proportional to the effective depth, and the effective depth is not on the drawing. It is what is left of the thickness after a cover, a link and half a bar diameter have been taken off it — and each of those is a site tolerance. In a slab, ten millimetres of workmanship is six per cent of the strength.
The gap nobody computed
A movement joint is sized by adding up everything the structure will do to it, and the deflection calculation — the only term anybody computes carefully — is usually the smallest one in the list. The largest is a construction tolerance, which is not a structural quantity at all, and the sum of the extremes is nearly twice what treating them as independent would ask for.
Built to the wrong length
A redundant structure's members do not have independent lengths. Choose all but one and geometry decides the last, so a member made a different length has to be pulled or pushed into place — and the force required stays in the structure for as long as the structure does. Nothing has been applied to it, there is no load case and no factor, and the members are carrying real force.
The strength that belongs to the test programme
A characteristic strength is a fractile of a distribution, and a distribution estimated from four specimens is not the same object as one known exactly. The same material tested four times reports a strength 15 per cent below what it reports when its scatter is known — and nothing about the material differs.
The hole made bigger so the steel would fit
A preloaded joint carries load by friction, and the friction is reduced by the shape of the hole the bolt passes through — not by how much steel the hole removes, but by a coefficient in a table. An oversize hole costs fifteen per cent of the resistance; a long slot costs thirty-seven. Both are provided because the steel would not otherwise line up.
Two fasteners that never arrive together
Every steel code forbids adding a weld's capacity to a bolt's in one shear joint, and states it as a rule rather than deriving it. It is derivable. Two fasteners in parallel are at the same displacement rather than the same force, and a weld has ruptured at four tenths of a millimetre while a bolt in a standard hole has not yet touched the side of it.
The torque that goes into the thread
A preload specified as a torque is a preload specified through two coefficients of friction that nobody measures. Nine-tenths of the torque on a bolt is spent turning against its own thread and the face of its nut, so a change in the grease moves the clamping force by half — and the one method that escapes it does so by yielding the bolt on purpose.
How wrong a drawing is
A pencil line is a band, and two bands cross in a parallelogram that grows as they turn parallel. The accuracy of a graphical construction is therefore a property of the angles it makes, not of the hand that made it — and the worst case is the shallow arch, the structure the method was most used on. Measured properly, the drawing's error there is the size of the builder's, and the check draughtsmen relied on cannot see it.
The angle made in the casting yard
A bridge bearing is designed for the rotation of the beam it carries, and the rotation is listed as a sum of load, temperature, creep and a tolerance. Followed through the life of a pretensioned beam, the largest term is none of those. It is the upward turn the prestress gives the beam's ends in the casting yard, before any bearing exists, and under every load the beam will ever carry its ends still point up.
The beam at the bottom of the stack
A precast yard stacks pretensioned beams to save space, each on bearers resting on the one below. If the bearers line up, the weight above goes straight down through them and the bottom beam never knows it is there. If they land outside its own bearers, the stack hogs the bottom beam at every section between them and takes from its top fibre relief that its debonding schedule had already spent. A schedule built for the yard leaves the bearers of a stack of three seven millimetres to be out of line. A bottom beam with a schedule of its own can be given half a metre.
The core drilled after the slab was built
A building in use acquires new services, and a core drilled through a flat slab beside a column is a routine instruction. The studs round the column were laid out for a slab without the hole, and the drill finds whatever is there. Whether it cuts a stud matters less than it looks. What decides is the outer perimeter, which the hole pushes outward while the studs stay where they are, and whether the slab survives is set by a margin nobody chose: the room left when the studs were rounded up to a stock size and the rings to a whole number.
The floor that is level on one date
Each floor of a tall concrete building is set high by the amount its columns are predicted to drop against the core, so that it arrives level. Counted in time, the drop does not peak at mid-height and stop at the roof: the worst floor of a forty-storey building is level 31, the roof moves 24 mm, and half the movement is still to come when the floors are fitted out. Set high by all of the prediction, a floor is level on one date thirty years away and 16 mm high at handover. With the creep known to ±30 per cent, setting it high by about four fifths of the prediction makes the worst floor's error 11 mm instead of 16. And none of it changes what the partitions see.
The wrench that reads the rust
The obvious check on a preloaded joint that has been in service for years is a wrench on the nut, and it measures the wrong thing. The nut holds against the bolt's tension times a friction bracket, and twenty years of rust raise the bracket until a bolt with half its preload passes four times in five. The washer that could have said more remembers only the day it was crushed.
The survey that arrives after the floors
A tall building's lower storeys start shortening months before its upper floors are cast, so a survey every ten floors should tell the creep the building really has and let the floors still to come be set for it. It does tell it, to a millimetre's precision, after the twenty-fifth floor. By then most of the floors whose height it was meant to correct are already set, and the floor that ends furthest from level is the one no survey can help.
Named alongside it
The objects these essays reach for when they reach for this one.
ServiceabilityBearingCreepPreloadSlip resistanceCamberCoefficient of frictionConnectionEffective depthErectionFrictionImposed deformation