Creep coefficient — where it appears
Named by 2 essays across 2 fields — each of them below, with the objects they name alongside it.
The slab that shrinks onto a finished beam
A precast beam with an in-situ slab cast on it is one member made of two concretes, and they do not age together. The slab's shrinkage is nearly the same whenever it is poured; what changes is how much shrinking the beam has left to share it with. Cast the slab at six weeks and it takes a ninth of the soffit's precompression away over thirty years. Cast it at a year and it takes a quarter, and goes into tension itself.
The survey that arrives after the floors
A tall building's lower storeys start shortening months before its upper floors are cast, so a survey every ten floors should tell the creep the building really has and let the floors still to come be set for it. It does tell it, to a millimetre's precision, after the twenty-fifth floor. By then most of the floors whose height it was meant to correct are already set, and the floor that ends furthest from level is the one no survey can help.
Named alongside it
The objects these essays reach for when they reach for this one.
CreepCamberComposite actionConstruction sequenceDifferential shorteningPrecast concretePrestressRestrained strainSamplingServiceabilityShrinkageTolerance