The last reading is the one that counts
Assumes The angle nobody limits, The deflection that arrives three years late and The moment over the support, and what it buys.
The reading that points the wrong way left the jacks in. Two 12 m pretensioned beams made continuous over their pier by a joint cast with the slab had been jacked as the joint went in, by the moment that would leave it holding nothing at thirty years in 60 per cent humidity, as the joint born holding a moment worked out. A building does not tell the designer its humidity, so the jacks stayed under the beams’ pier ends, read the reaction there — the joint’s moment in another form — and were reset once, from the reading plus the design model’s forecast of everything still to come. For a slab cast at a year a reset a year later cut the thirty-year moment’s spread over 45 to 80 per cent humidity from 158 kN·m to 24. For a slab cast at six weeks the same reset made the spread worse, because at one year the early slab’s humidity error points the other way from its error at thirty.
The essay’s last section asked the obvious next question. If the jacks are there, they can be read every year and reset every year, each reset small and each made with one more year of evidence and one less year of the future to guess. For the late slab that sounds like convergence; for the early slab it sounds like a few wrong-way resets followed by later ones that undo them. Whether a programme of annual resets does better than one reset at the right moment is a question with an exact answer, and the answer is not the one the word “programme” suggests.
Each reset is a step that creeps
The resets are made by the same rule as the single reset before. On the day of a reading, the jacks report the joint’s moment. The design model — the creep and shrinkage model the first jack was set with, run at 60 per cent — forecasts how that moment will change from the reading’s day to thirty years: the restraint still building as the beams creep and the slab shrinks, the first jack still relaxing, and every earlier reset still relaxing too. The new reset is the moment that, relaxed by the design model’s creep from its own day on, cancels that forecast. If the beams really are creeping at 60 per cent, every reading equals its prediction and every reset is nothing; the programme spends its jacks only on the difference between the building and the design model.
Each reset is an imposed rotation held by a creeping structure, so it relaxes. A step of moment applied when the beams are two years old keeps more of itself than one applied when they were four weeks old, because older concrete creeps less, and the relaxation of every step is computed by the same step-by-step creep integral that has carried every jack in this sequence. That is all a programme is: a sum of steps, each relaxing at its own age, laid over the restraint — the same superposition that let the joint poured twice over the pier add a first stage’s small account to a single pour’s.
In the hero figure the early slab in humid air reads −91.6 kN·m at its first reading, a year after the slab, against the design model’s −82.1. The reset rule turns that 9.5 kN·m of extra hog into a forecast of extra hog at thirty years and resets by 17.8 kN·m of sag. That is the wrong direction — left alone, this joint was heading for 29.6 kN·m of sag — and the reason is the one the single reset found: in humid air the slab’s shrinkage onto the finished beams is slower, which is what the reading sees in the first year, while the beams’ creep is also smaller, which is what decides the thirty-year moment. The second reading sees the joint heading for sag after all and resets by −23.2. The third, −10.6. By the fifth the resets are −4.9 and still all of one sign. The joint ends at 12.4 kN·m. Left until the fifth reading’s day and reset once there, by −27.9, it ends at 11.4.
The first reset is the large one
For the slab cast at a year, the first reading sees most of what humidity will do, because for a late slab the humidity’s main effect is the slab’s shrinkage and a slab shrinks fastest in its first year. Its first reset is −170.6 kN·m in humid air and 55.9 in dry, and every later one is under 8 kN·m. The programme for the late slab is one reset followed by nine corrections to it, small and of alternating or mixed sign as the forecast is refined.
For the early slab the shape is different. In dry air its resets are all small and of one sign. In humid air the first reset is the wrong way and the next two take it back and go past it. Nothing in the reset rule is wrong — every reset is the best estimate available on its day — but the estimate on the first day is of the wrong sign, and a programme that acts on every estimate acts on that one too.
This is where the intuition of convergence comes from and where it misleads. The resets shrink, and a sequence of shrinking corrections looks like a sequence closing in. It is closing in, but on what each year’s forecast says, and a forecast is only as good as the part of the future it still has to guess.
The spread follows the date
The measure that decides whether a programme is worth having is the one the single reset was judged by: how far apart the thirty-year moments are across the humidities the building might actually have. Jacked once and left, the spread is 29.6 kN·m for the early slab and 157.5 for the late one. After five years of annual resets it is 13.0 and 9.2. Reset once, on the date of the fifth reading, it is 11.7 and 1.5. After ten years of annual resets it is 5.9 and 4.2; reset once on the tenth reading’s day, 4.3 and 3.5.
So the curves fall with the date of the last reading, and the number of readings before it hardly matters. One reset on the fifth reading’s day does as well as five resets ending on that day, and for the late slab rather better. The second curve is not a coincidence of these two slabs. It follows from what the reset rule does, and the rule can be taken apart exactly.
What the end moment is made of
On the day of the last reset the forecast is exact, by construction: the reset cancels the forecast thirty-year moment, as the design model would have it, from that day’s actual state. Whatever the joint holds at thirty years is therefore what the design model got wrong after that day, and that is a sum of three parts. The restraint and the first jack keep changing after the last reading, and the building changes them by a different amount from the model. The last reset relaxes, and the building relaxes it by a different amount from the model. And every earlier reset is still relaxing too, and the building relaxes each of those differently.
For the early slab in humid air, after one reading the restraint’s error from then on is 39.1 kN·m, the reset’s own misjudged relaxation 0.8, and there are no earlier resets. After five, the restraint’s error from the fifth reading on is 12.5, the last reset’s −0.2, and the four earlier resets’ together 0.1. Across ten, the earlier resets’ part never exceeds 0.2 kN·m.
The reason it is so small is that the earlier resets are small and old. A reset of 20 kN·m made at two years and still relaxing at five has most of its relaxation behind it, and what is left differs between 60 and 80 per cent humidity by a fraction of what is left. Its whole account after the last reading is a fraction of a fraction of 20 kN·m. So the end moment is, to within a few tenths of a kN·m, the restraint’s error after the last reading — the creep and shrinkage the design model still had to forecast on that day, and got wrong. The earlier resets do not accumulate accuracy. They change the path the joint takes to its last reading, and on that day the last reset rewrites everything they did.
For the late slab in humid air the single reset on the fifth reading’s day ends at 0.9 kN·m and the five-reset programme at 9.2, and the split shows why the single one is better there. Both have the same restraint error after the fifth reading, 8.7. The single reset is a large one, −189 kN·m, and its misjudged relaxation is −7.8; the programme’s last reset is −3.2 and its misjudged relaxation is nothing worth counting. The large single reset is relaxed less in humid air than the design model expects, which leaves more hog, and the restraint’s error is sag: the two happen to cancel. That is luck of sign, and it would not survive a building drier than the design rather than wetter. What does survive is that the programme gains nothing by being a programme.
The cost is jack travel
If the programme bought nothing and cost nothing it would be a matter of taste. It costs travel. For the early slab, five annual resets move the jacks through 61.9 kN·m in all, because the second reset has to take back the first before going further; one reset on the fifth reading’s day moves them 27.9. For the late slab the difference is small, 190.5 against 188.8, because its first reset is nearly all of it either way.
Travel is not a free quantity. Each reset is a jacking operation under a live structure: a reaction raised or lowered by a measured amount at a pier, with the bearings, the joint’s concrete and the beams’ ends taking the change as an imposed rotation. The jack that creep carries past the mark found the same thing in a continuous beam’s closure: every jacked moment is held by creeping concrete and then partly given back, and every one has to be reversed if the next reading says it was wrong. A programme that resets in both directions spends jacking on undoing itself. The early slab’s programme moves its jacks the wrong way first and then back, and the back is paid for twice.
A different rule: back to nothing every year
There is a second way to run the jacks that a programme makes possible and a single reset does not. Instead of forecasting the thirty-year moment and cancelling it, the jacks can simply bring the joint back to nothing on every reading’s day — no forecast, no design model, only the reading. The reading that points the wrong way found that rule worse than a forecast for a single reset, because zero on the day is not zero at thirty years: the creep still to come and the reset’s own relaxation are both ignored. Done every year, it is a different thing. The joint is never allowed far from nothing, and the error each year is only that year’s drift.
Brought to nothing every year for ten years, the early slab’s joint in humid air ends at 18.7 kN·m and the jacks move through 189.8; for fifteen years, 10.0 through 202.3. Reset to the forecast every year for ten years, it ends at 5.7 through 71.8. The zeroing rule ends worse because it stops caring at its last reading: whatever creep and shrinkage are still to come after the last day are left to happen, and on a time grid where the beams creep for thirty years, fifteen years is not the end of it. The forecast rule ends better because it did care — its last reset already anticipated the remaining drift, and only the model’s error in that anticipation is left.
Where zeroing does better is on the way there. The joint brought to nothing every year is within 21 kN·m of nothing from its first reading to its fifteenth. Reset to the forecast, the joint is deliberately pushed past nothing on every reset day so that the creep still to come will bring it back — the cancelling reset has to overshoot now to land later — and its largest moment after the first year stays at 74 kN·m however many resets are made. The two rules answer two different questions. The forecast asks where the joint ends; zeroing asks where it is.
The path the joint did not need
A bounded path is worth having if the unbounded one does harm. Jacked once and left, the early slab’s joint is at its furthest from nothing a year after the slab, at −91.6 kN·m, and creeps back toward its end from there. The joint cracks at 140 kN·m in sag, where the beams’ bottom connection opens, and 239 in hog, where the slab’s top fibre does. Left alone after its first jack the joint never comes within 48 kN·m of either. Reset to the forecast every year its largest is 74; brought to nothing every year, 83 after a single reading and 21 after fifteen.
So the path a zeroing programme bounds is a path the joint did not need bounded. The single jack at the pour had already done the work that matters for cracking: the joint cast over the pier found an unjacked joint cast at four weeks sagged to half as much again as its cracking moment, and the first jack is what took it out of that range. What is left for the resets is the last few tens of kN·m of the thirty-year moment — the part that decides the sign of the joint’s moment late in its life, the part the angle nobody limits would ask a bearing to accommodate — and for that only the last reading matters.
What the programme rests on
The humidity is constant. A building in 80 per cent humidity is in 80 per cent for thirty years. A real building’s humidity changes with seasons and with use, and an annual reading taken in the same month each year averages over a season rather than tracking one. The arithmetic of the split does not depend on constancy — the end moment is the model’s error after the last reading whatever the error is — but a humidity that changes late in the life is exactly an error after the last reading, and no earlier reset can see it.
The model is wrong only in humidity. Every error here comes from the beams creeping in a different humidity from the design one — the half of a creep coefficient that, as the creep that belongs to the member found, is the member drying rather than the concrete. A design model can also be wrong in its creep function itself, in the beams’ concrete strength, or in the slab’s shrinkage, and those errors would show in the readings the same way. Which way they would make an early reading point is a property of each error, not of the programme.
The readings are exact. The jacks read the joint’s moment through a reaction, and over two 12 m spans a moment of 1 kN·m at the joint changes the pier’s reaction by only a sixth of a kilonewton, so a reading good to a kilonewton is good to about 6 kN·m — the same size as the programme’s later resets. An annual programme’s last few resets are near the reading’s own resolution, and a real programme would stop resetting when the reset fell below it. That makes the case for one late reset stronger, not weaker.
The time grid is the creep integral’s. The readings are taken on the steps the creep integral uses, which near a year after the slab are a few weeks apart and at ten years most of a year apart. “Every year” is every year to within those steps, and fifteen is about as many as the grid can honestly separate.
A measurement is spent once
The general point is about what a measurement of a creeping structure buys. Each reading is a fact about the structure’s past, and the forecast built on it is a guess about its future; a reset acts on both. Acting on every reading means acting on every guess, including the early ones, which are the worst. Acting on the last one means acting on the best guess available, made with the most past and the least future, and the earlier readings are not wasted — they tell the engineer whether the joint is behaving, and when its readings have settled enough to act on — but they are not improved by being turned into jacking.
That is the same conclusion the arm connected late reached by a different route for an outrigger’s connection: a force set once, as late as the programme allows, holds less creep in it than a force set early and corrected. A creeping structure is best adjusted once, and that once is as late as the adjustment can wait.
Still open: the reading as a test of the model
Every reset here takes the design model as given and uses the reading only to correct the joint. The readings could instead correct the model: a year of readings is a measurement of how the beams are creeping, and fitting the creep model’s humidity, or its creep coefficient, to the readings would give a forecast that improves as the readings accumulate rather than one that only shifts. Whether a model fitted to five annual readings forecasts the thirty-year moment better than the design model corrected by the fifth reading alone — and whether the early slab’s wrong-way first year, which no humidity can produce in the design model, then shows up as a model that cannot fit, which is itself the warning — needs the readings treated as data for the model’s parameters rather than as offsets to its output.
Named alongside this one
Essays reaching for the same objects. Nobody chose these; they are what the concept index makes visible.
- The prestress the member takes back creep · imposed deformation · prestress · relaxation · shrinkage
- The strain that was imposed, and the stress that leaked away creep · imposed deformation · prestress · relaxation · shrinkage
- The angle made in the casting yard creep · end rotation · prestress · shrinkage
- The arch that waits with its hinges open creep · imposed deformation · relaxation · shrinkage
- The coefficient that answered the wrong question creep · imposed deformation · relaxation · shrinkage
- The jacks the arch forgets creep · imposed deformation · relaxation · shrinkage
The objects this essay names
Each one links to every other essay that touches it.
ContinuityCreepEnd rotationImposed deformationPrestressRelaxationRestraint momentShrinkage