Concept

Deflection limit — where it appears

A bound on movement rather than on stress, usually a fraction of the span, which decides a member's size more often than strength does. It has no factor of safety in front of it, so an error in the calculation is an error in the answer rather than an erosion of a margin.

Named by 7 essays across one field — each of them below, with the objects they name alongside it.

Which limit arrives first. Utilisation of the strength limit and of the deflection limit, against span. Strength grows as the square of the span and deflection as the fourth power, so the two cross — and past the crossing a beam is sized by how far it moves rather than by what it can carry.

Stiffness is not strength, and usually it is the one that governs

A beam can be nowhere near failure and still be unusable, because it has moved too far. For most long-span members that limit arrives first, and stronger steel does not help at all.

deflection · Serviceability
The water that will not run off. Water depth against sag at the middle of the bay, for a roof bay starting with a reversed construction camber of 0.01. There is no critical value to reach: the deflection grows from the first increment, slowly at first and then without bound as the ratio approaches 1.00 — which is the depth at which the bay fills faster than it stiffens, and which the roof bay therefore never attains. The perfect roof bay, drawn for comparison, sits on the vertical axis until it arrives there and then has no answer at all.

The water that will not run off

A flat roof deflects, the deflection makes room for water, the water deepens the deflection. It is the same equation as a buckling column, with rain in place of the axial load.

deflection · Serviceability
Four camber rules, and what each leaves on the finished beam. The same 12 m composite beam, cambered against four different things, followed through its own load history. Positive is a sag and negative a hog, and the point at the left of each line is the shape it was fabricated to. Cambering against the wet concrete leaves 12.7 mm of sag at the end and a flat beam on the day the slab is poured; cambering against the total load leaves the beam dead flat when fully loaded and hogged 37.9 mm — one part in 316 of the span — before anything is on it at all.

Built to the wrong shape on purpose

A cambered beam is fabricated curved upward so that load bends it down to something like straight. Nothing in the analysis changes, no stress anywhere is altered, and almost every mistake made with it is a bookkeeping mistake about which loads count.

deflection · Camber
The check that depends on a date. Total deflection and the deflection occurring after the brittle finishes are built, for one 12 m beam, against the day those finishes go up. The total barely moves — the beam ends up where it ends up. The increment falls from 32 mm at a week to 14 mm at a year, because creep is fast at first and slow later and a partition built early inherits nearly all of it: 44% of the final creep has already happened by day 28. The span/500 limit is 24 mm and the span/250 limit is 48; this beam passes the first only after day 25. Camber subtracts from both terms of the difference and therefore changes the upper curve and not the lower one, which is the reason a cambered beam can satisfy every total-deflection check and still crack the wall.

The limit that depends on a date

Total deflection can nearly always be met, and on a long span it is met with camber. The limit that actually decides the member is the other one — the deflection occurring after the brittle finishes are built — and camber does nothing for it whatever, because it is subtracted from both terms of a difference. The same beam passes or fails on the day the partitions went up.

deflection · Incremental deflection
The deformation with no limit against it. A 8 m open section carrying 12 kN/m at an eccentricity of 75 mm from its shear centre. The torque is small — 900 Nmm per mm — and the twist is not: 2.55° at mid-span with the ends restrained against warping, against 9.09° if they are not, a factor of 3.57. What that angle does is move the flange tip sideways by 8.9 mm — 62 per cent of the member's own vertical deflection, and 28 per cent of the span/250 that vertical deflection is checked against. The same load on a closed section of the same depth moves it 0.15 mm, 60 times less. No code gives a limit for this quantity, so it is the one movement in the collection that is computed only after somebody has complained about it.

The movement with no limit against it

Every code in the world gives a deflection limit. None gives a twist limit — and a beam loaded off its shear centre twists. On an open section a modest eccentricity moves the flange tip sideways by three fifths of the sag that does get checked, and nothing anywhere says whether that is acceptable.

deflection · Twist serviceability
A deck holds the middle of the span. The twist along an 8 m open section on forks, free to warp, carrying 12 kN/m at 75 mm from its shear centre — 900 Nmm of torque per mm of span. With nothing fastened to it the beam twists 6.25° at mid-span; a deck resisting the top flange's rotation at 5.0 kNm per metre per radian holds it to 4.20°, and one four times as stiff to 2.10°. The deck works where the beam is weakest, in the middle; near the supports the beam's own torsional stiffness does most of the work whatever is fastened to it.

A deck is a spring, not a wall

An open-section beam loaded off its shear centre twists, and the usual reassurance is that the deck fastened to its top flange will stop it. The deck resists the flange's rotation with a stiffness per metre of span, and that stiffness has to be compared with the beam's own. On an 8 m beam a screwed deck of ordinary stiffness removes a third of the twist; on a 16 m beam the same deck removes three quarters, because the beam's torsional stiffness falls with the square of its span and the deck's does not.

deflection · Twist serviceability
Two members each half-way to ponding are unstable together. The girder's ponding parameter Cp against the joist's Cs. Either member alone is stable up to 1; together the roof is stable only below the solid curve, (1 − Cp)(1 − Cs) = (8/π²)·Cp·Cs, which meets the diagonal at 0.526 — two members each about half-way to ponding on their own are critical together. The dashed line is the simplified rule Cp + 0.9Cs ≤ 0.25. The marked roof is a 12 by 9 m bay whose girders and joists are each sized to deflect L/240 under 1.5 kN/m²: Cp = 0.26 and Cs = 0.19, stable, with its joists' sag amplified 1.79 times where the joist alone would say 1.24 and the girder alone 1.35.

The roof that ponds on its girders

A flat roof's joists sit on girders, and the water fills the sum of both their sags. Two members each half-way to ponding on their own are unstable together, and long before that the growth of the water is far larger than either member's own amplification says. AISC's simplified rule turns out to be a line of constant growth, and a member sized to a deflection limit has a ponding parameter proportional to its span — so a bay sized to L/240 under 1.5 kN/m² meets the rule up to 6 m, doubles its water at 12 and ponds at 24.5.

deflection · Serviceability

Named alongside it

The objects these essays reach for when they reach for this one.

ServiceabilityStiffnessPondingAmplification factorComposite actionConstruction sequenceCreepCritical loadLimit stateProppingSelf-weightShear centre