Concept

Propping — where it appears

Supporting a member temporarily so that a load is carried by a different structure from the one that will carry it afterwards. It changes which section carried which load, so a propped member and an unpropped one of identical size have different stresses and different deflections at the same finished state.

Named by 8 essays across 3 fields — each of them below, with the objects they name alongside it.

The props decide where the stress ends up. Bottom-fibre stress in the steel of a 12 m composite beam carrying 12 kN/m of wet concrete and 18 kN/m afterwards. Unpropped, the bare steel takes the first stage alone and reaches 292 MPa; propped, the finished composite section takes everything and reaches 186 MPa — a ratio of 1.57. 62% of the unpropped beam's final stress was locked in before the slab was structural at all. The deflections differ by 1.73 times for the same reason, and no drawing of the finished beam distinguishes the two.

The structure that was never complete

Every analysis in this collection is of a finished structure loaded once. Real ones are built in pieces, and each piece carries whatever was present at the moment it became structural — so the stress in a member depends on when it arrived, which appears nowhere on any drawing.

structures · Construction sequence
Four camber rules, and what each leaves on the finished beam. The same 12 m composite beam, cambered against four different things, followed through its own load history. Positive is a sag and negative a hog, and the point at the left of each line is the shape it was fabricated to. Cambering against the wet concrete leaves 12.7 mm of sag at the end and a flat beam on the day the slab is poured; cambering against the total load leaves the beam dead flat when fully loaded and hogged 37.9 mm — one part in 316 of the span — before anything is on it at all.

Built to the wrong shape on purpose

A cambered beam is fabricated curved upward so that load bends it down to something like straight. Nothing in the analysis changes, no stress anywhere is altered, and almost every mistake made with it is a bookkeeping mistake about which loads count.

deflection · Camber
The check that depends on a date. Total deflection and the deflection occurring after the brittle finishes are built, for one 12 m beam, against the day those finishes go up. The total barely moves — the beam ends up where it ends up. The increment falls from 32 mm at a week to 14 mm at a year, because creep is fast at first and slow later and a partition built early inherits nearly all of it: 44% of the final creep has already happened by day 28. The span/500 limit is 24 mm and the span/250 limit is 48; this beam passes the first only after day 25. Camber subtracts from both terms of the difference and therefore changes the upper curve and not the lower one, which is the reason a cambered beam can satisfy every total-deflection check and still crack the wall.

The limit that depends on a date

Total deflection can nearly always be met, and on a long span it is met with camber. The limit that actually decides the member is the other one — the deflection occurring after the brittle finishes are built — and camber does nothing for it whatever, because it is subtracted from both terms of a difference. The same beam passes or fails on the day the partitions went up.

deflection · Incremental deflection
More props, heavier slabs — unless they go in after the weight. The heaviest load any slab carries during construction, as a multiple of its own weight, against the number of levels of props under the slab being cast. Every level a shore that carried the wet concrete and moves up with the formwork: 2.00, 2.25, 2.37, 2.44 w for one to four levels. One level of shores and the rest backprops, put in snug after the formwork is struck: 2.00, 1.50, 1.33, 1.25 w. The same number of props, differently timed: a shore enters the load path before the weight it carries and passes it down, and a backprop enters after and shares only what arrives later.

Loaded twice over before it is a month old

A concrete floor in a building going up a storey a week carries, in its first weeks, the wet weight of the floors being cast above it, handed down through the props. By Grundy and Kabaila's arithmetic that is twice its own weight on a single level of shores, and more with more levels — 2.25 on two, 2.37 on three — because every prop that carried wet concrete passes its load down the stack. The same props put in after the formwork is struck carry nothing until something new arrives, and the peak falls to 1.5, 1.33, 1.25. The heaviest day of a floor's life is decided by when its props went in, not how many there are.

materials · Maturity
Where in a slab's first month its heaviest load lands. The load on the sixth floor of a frame of 250 mm slabs on a 7.5 m grid cast a floor every 7 days at 20 °C, on one level of shores and one of backprops, as a multiple of its own weight, against its age. Rigid and snug, no creep: a peak of 1.51 w at 14 days; steel springs and creep: a peak of 1.71 w at 21 days; the same, 1.0 mm of slack: a peak of 1.78 w at 7 days. Snug and rigid, the slab carries its heaviest load twice, a week apart, as the struck slab and then as the one below it. With creep the second is the heavier, because in the intervening week the slab above has sunk onto the backprops; with slack, the first.

The backprop that takes load nobody gave it

The arithmetic of propped construction says a backprop put in snug carries nothing until the next floor is cast, and then only a share of it. Count the props as the springs they are and that barely changes, because a steel prop is about seven times stiffer than the slab per square metre. Two other things change it. The young slab just struck creeps onto its backprops within a day and hands a quarter of a slab's weight down to the one below, which then carries 1.71 times its weight rather than 1.5. And a millimetre of slack at installation — about half the slab's own deflection — gives the struck slab back everything a backprop was meant to save.

materials · Maturity
The preload lifts the young slab and lands on the one below it. The load on one slab of a frame of 250 mm slabs on a 7.5 m grid cast a floor every 7 days at 20 °C, on one level of shores and one of backprops, as a multiple of its own weight, from the day it is struck at 7 days to 28 days, with creep. With its backprops put in snug (dashed) it takes 1.52 w at the cast above it, creeps down to 1.29 by the end of the week, takes 1.48 w when the slab above it is struck and cast on in turn, and creeps up to 1.71. With every backprop jacked to 0.30 w (solid) the young slab starts its week at 1.22 w and ends it at 1.14; a week later the preload of the backprops above lands on it, and it takes 1.78 w, creeping to 1.86.

The backprop jacked tight lands on the floor below

A backprop put in snug shares only the load that arrives after it, and creep then pushes the young slab above onto it anyway. Jack it to a preload instead and the young slab is lifted at once — but the preload survives the week, so the lift lands on the slab below the moment the next level is struck, and about half of it is load creep would have moved within the week regardless. The best preload balances the week-old slab against the fortnight-old one, and with creep it is small: a fourteenth of a slab's weight, about six hundred newtons a prop. Anything over a fifth leaves the frame worse than snug. What a small preload does buy completely is immunity to slack.

materials · Maturity
Slackening a backprop gives the young slab back more than the preload. The load on one slab of a frame of 250 mm slabs cast a floor every 7 days at 20 °C, on one level of shores and one of backprops, as a multiple of its own weight, from the day it is struck at 7 days to 21 days, with creep. Snug, it takes 1.52 w at the cast above it. With its backprops jacked to 0.15 w it takes 1.37. Slackened to snug 1.0 day later, the backprops give it back everything they carry — the preload, their share of the slab cast above and what creep has added — and its load jumps from 1.19 to 2.00 w. Let down by the preload alone, it goes from 1.23 to 1.38. A week after it is struck the slab becomes the slab below, and the backprops jacked above it land on it whatever is done to its own.

The preload that cannot be taken back

A backprop jacked tight under a young slab relieves it and loads the slab below by the same amount at the same instant. The obvious repair is to slacken the backprop once the young slab is past its worst, so that the preload never reaches the slab below. It cannot work. Slackened to snug, a backprop lets go of everything it carries, not only its preload, and the young slab's load jumps from 1.19 to 2.00 times its weight. Let down by the preload alone, it gives back a load the slab below has already carried at its worst.

materials · Maturity
Every day taken off the cycle is paid for in the youngest slab. For a frame of 250 mm slabs on a 7.5 m grid at 20 °C, on one level of shores: the largest use of strength of any slab against the floor cycle, with one level of backprops snug or jacked to its best preload, and with two levels snug or jacked to theirs; dotted, a seven-day cycle on snug backprops. On one level of snug backprops the worst use is 1.95 at seven days, 2.14 at five and 2.53 at three. With the best preload, 1.87, 2.01 and 2.30. With two levels, 1.79, 1.95 and 2.31; with two levels and their best preload, 1.67, 1.78 and 1.99.

The day taken off the floor cycle

A frame cast a floor a week loads its slabs with the same multiples of their weight whether the cycle is seven days or four. What a shorter cycle changes is how strong each slab is when its load arrives, and it changes that unequally, costing the youngest slab more than the one below it. That is why a faster cycle makes a jacked backprop more useful rather than less, and why a frame that wants four days needs both a second level of backprops and a preload to be as safe as a week on one.

materials · Maturity

Named alongside it

The objects these essays reach for when they reach for this one.

Construction sequenceCreepBackproppingEarly-age strengthLoad sharingComposite actionPreloadDeflection limitFlat slabServiceabilitySuperpositionCamber

All concepts