Load-sharing — where it appears
Named by 17 essays across 7 fields — each of them below, with the objects they name alongside it.
The stiffest path takes the load
When two members share a force the split can be argued about. When they share a displacement it cannot — stiffness settles it, and nothing about the load or the plan drawing gets a vote. The consequence is that stiffening a lightly loaded member raises its stress, and the way to unload something is to soften it.
The deck is not there to carry the load
A cable takes the shape of whatever is on it, which is exactly the problem — under a point load its shape is a kink, and a kink is not a road. The stiffening girder exists to spread the load until what reaches the cable is something the cable's own shape is right for.
Three equations at every joint
A plane truss is determinate when m + r = 2j. A space frame needs 3j, and that one changed digit is why a cube of twelve bars is six mechanisms short while looking perfectly solid — and why every three-dimensional frame ever built is made of triangles in several planes at once.
The corner that moves most
A lateral force is shared out in proportion to stiffness only if it passes through the centre of rigidity, which is not the centre of the plan and not the centre of mass. The distance between the two is a torque, and the wall that pays for it is the one furthest away and carrying least.
The floor is a beam lying down
A floor plate spans horizontally between the walls that resist a lateral load, carries a distributed inertia load, and has chords, a web and a span-to-depth ratio like any other beam. Its stiffness decides whether the walls share the load by their stiffness or by the area of floor nearest them — and the familiar tributary answer turns out to be neither limit.
The deflection that belongs to the support
A beam calculation answers a question about a beam sitting on things that do not move. Real ones sit on bearings, on other beams and on columns that shorten, and every one of those is a spring in series with the member — so a deflection is the sum of two things and only one of them is a property of the beam.
The joint that has to be as good as the member
A splice exists because members come in lengths and structures do not. It has to deliver the same force, at the same stiffness, in the same distribution across the section, through a discontinuity — and each of those three requirements is met by a different feature of the detail, with the third one usually left to look after itself.
Where the structure is allowed to move
One drawing decides how big every movement joint on a bridge is and where every horizontal force goes, it takes an afternoon, and it appears on no calculation sheet. Move the fixed point from an abutment to the middle pier and the largest joint halves and the horizontal force on that support drops from the whole of the friction to none of it.
The column that leans on its neighbours
A column with a pinned base and a pinned top has no lateral stiffness at all and cannot stand up alone, and yet thousands of them do. What holds them is the rest of the storey, and what it costs is paid by whichever columns do have stiffness — whose effective length rises as the square root of the load being leaned on them, straight off the end of every chart.
Nine piles, and four times the settlement
A pile cap divides its load between its piles by the same three terms a bolt group uses and a section under biaxial bending uses. What a bolt group does not have is neighbours it shares ground with — and the group effect that matters is not the strength check everybody makes, but a stiffness effect nobody tabulates.
The pipe decides what the soil weighs
A buried conduit is not loaded by the soil above it. It is loaded by whatever share of that soil the relative movement leaves it — and which way the shear on the sides of the prism acts depends on whether the conduit settles more or less than the ground beside it. Two identical pipes under identical fill, one carrying two thirds of the prism and one carrying nearly twice it.
The column given more than its rectangle
The tributary rule draws a rectangle round each column and hands it whatever stands inside. A floor is continuous over its columns, and a continuous beam does not give each support the load above it — the first interior one takes a quarter more and the end ones a quarter less. On a grid the two directions multiply, and two columns on the same floor differ by a factor of nearly three.
The pier that carries only the difference
A stressed ribbon continued over a pier pulls on it from both sides, and under its own weight the two pulls cancel. Load one span and they do not: the pier is asked for the difference, nearly ten meganewtons for a crowd on one of two hundred-metre spans. Whether it gives it depends on its stiffness against a number the ribbon supplies itself, and whatever the pier does not carry, the ribbon turns into movement — a third of a metre of extra sag in the loaded span and a fifth of a metre of rise in the empty one.
The truss whose forces follow its sections
In a determinate truss each member's force is fixed before its section is chosen, so sizing for strength and sizing for stiffness can be done in either order. Put a counter-diagonal in every panel and they cannot. The fully stressed design becomes an iteration that starves some counters to nothing and keeps others, lands on a different truss from every start, and — whichever it lands on — weighs the same and deflects the same. Then enlarge one group of members to stiffen it, and a vertical nobody touched is overloaded by 58 per cent.
Loaded twice over before it is a month old
A concrete floor in a building going up a storey a week carries, in its first weeks, the wet weight of the floors being cast above it, handed down through the props. By Grundy and Kabaila's arithmetic that is twice its own weight on a single level of shores, and more with more levels — 2.25 on two, 2.37 on three — because every prop that carried wet concrete passes its load down the stack. The same props put in after the formwork is struck carry nothing until something new arrives, and the peak falls to 1.5, 1.33, 1.25. The heaviest day of a floor's life is decided by when its props went in, not how many there are.
Rigid by one code and not by the other
A floor plate between shear walls shares its storey force out in proportions that move continuously with its stiffness, from a continuous beam's to a rigid body's. The codes put it in one of two boxes and use a different model in each. ASCE 7 and EN 1998-1 draw their boxes' edges a hundred times apart in plate stiffness, each at a point where its own licensed model already misstates the middle wall by about a tenth — and an ordinary 200 mm slab sits in the gap between them.
The tendon that pulls before the deck arrives
A stressed ribbon is hung one span at a time, and the obvious fear is the stage at which one span carries its deck and the next does not: the pier between them asked for a whole span's thrust. It is not asked for that, because tendons cut to the finished length are already stretched across the empty span and pulling. For two 100 m spans at a fiftieth, the rigid pier's stage force is 4,109 kN against a crowd's 9,440 — unless the tendons were sized generously, when the stage overtakes the crowd.
Named alongside it
The objects these essays reach for when they reach for this one.
StiffnessLoad pathFree bodyTributary areaDeflectionDiaphragmElastic foundationGeometric stiffnessLateral systemServiceabilityShear wallAccidental eccentricity