Load sharing — where it appears
Named by 32 essays across 7 fields — each of them below, with the objects they name alongside it.
The stiffest path takes the load
When two members share a force the split can be argued about. When they share a displacement it cannot — stiffness settles it, and nothing about the load or the plan drawing gets a vote. The consequence is that stiffening a lightly loaded member raises its stress, and the way to unload something is to soften it.
The deck is not there to carry the load
A cable takes the shape of whatever is on it, which is exactly the problem — under a point load its shape is a kink, and a kink is not a road. The stiffening girder exists to spread the load until what reaches the cable is something the cable's own shape is right for.
Three equations at every joint
A plane truss is determinate when m + r = 2j. A space frame needs 3j, and that one changed digit is why a cube of twelve bars is six mechanisms short while looking perfectly solid — and why every three-dimensional frame ever built is made of triangles in several planes at once.
The corner that moves most
A lateral force is shared out in proportion to stiffness only if it passes through the centre of rigidity, which is not the centre of the plan and not the centre of mass. The distance between the two is a torque, and the wall that pays for it is the one furthest away and carrying least.
The floor is a beam lying down
A floor plate spans horizontally between the walls that resist a lateral load, carries a distributed inertia load, and has chords, a web and a span-to-depth ratio like any other beam. Its stiffness decides whether the walls share the load by their stiffness or by the area of floor nearest them — and the familiar tributary answer turns out to be neither limit.
The deflection that belongs to the support
A beam calculation answers a question about a beam sitting on things that do not move. Real ones sit on bearings, on other beams and on columns that shorten, and every one of those is a spring in series with the member — so a deflection is the sum of two things and only one of them is a property of the beam.
The joint that has to be as good as the member
A splice exists because members come in lengths and structures do not. It has to deliver the same force, at the same stiffness, in the same distribution across the section, through a discontinuity — and each of those three requirements is met by a different feature of the detail, with the third one usually left to look after itself.
Where the structure is allowed to move
One drawing decides how big every movement joint on a bridge is and where every horizontal force goes, it takes an afternoon, and it appears on no calculation sheet. Move the fixed point from an abutment to the middle pier and the largest joint halves and the horizontal force on that support drops from the whole of the friction to none of it.
The column that leans on its neighbours
A column with a pinned base and a pinned top has no lateral stiffness at all and cannot stand up alone, and yet thousands of them do. What holds them is the rest of the storey, and what it costs is paid by whichever columns do have stiffness — whose effective length rises as the square root of the load being leaned on them, straight off the end of every chart.
Nine piles, and four times the settlement
A pile cap divides its load between its piles by the same three terms a bolt group uses and a section under biaxial bending uses. What a bolt group does not have is neighbours it shares ground with — and the group effect that matters is not the strength check everybody makes, but a stiffness effect nobody tabulates.
The pipe decides what the soil weighs
A buried conduit is not loaded by the soil above it. It is loaded by whatever share of that soil the relative movement leaves it — and which way the shear on the sides of the prism acts depends on whether the conduit settles more or less than the ground beside it. Two identical pipes under identical fill, one carrying two thirds of the prism and one carrying nearly twice it.
The column given more than its rectangle
The tributary rule draws a rectangle round each column and hands it whatever stands inside. A floor is continuous over its columns, and a continuous beam does not give each support the load above it — the first interior one takes a quarter more and the end ones a quarter less. On a grid the two directions multiply, and two columns on the same floor differ by a factor of nearly three.
The pier that carries only the difference
A stressed ribbon continued over a pier pulls on it from both sides, and under its own weight the two pulls cancel. Load one span and they do not: the pier is asked for the difference, nearly ten meganewtons for a crowd on one of two hundred-metre spans. Whether it gives it depends on its stiffness against a number the ribbon supplies itself, and whatever the pier does not carry, the ribbon turns into movement — a third of a metre of extra sag in the loaded span and a fifth of a metre of rise in the empty one.
The truss whose forces follow its sections
In a determinate truss each member's force is fixed before its section is chosen, so sizing for strength and sizing for stiffness can be done in either order. Put a counter-diagonal in every panel and they cannot. The fully stressed design becomes an iteration that starves some counters to nothing and keeps others, lands on a different truss from every start, and — whichever it lands on — weighs the same and deflects the same. Then enlarge one group of members to stiffen it, and a vertical nobody touched is overloaded by 58 per cent.
Loaded twice over before it is a month old
A concrete floor in a building going up a storey a week carries, in its first weeks, the wet weight of the floors being cast above it, handed down through the props. By Grundy and Kabaila's arithmetic that is twice its own weight on a single level of shores, and more with more levels — 2.25 on two, 2.37 on three — because every prop that carried wet concrete passes its load down the stack. The same props put in after the formwork is struck carry nothing until something new arrives, and the peak falls to 1.5, 1.33, 1.25. The heaviest day of a floor's life is decided by when its props went in, not how many there are.
Rigid by one code and not by the other
A floor plate between shear walls shares its storey force out in proportions that move continuously with its stiffness, from a continuous beam's to a rigid body's. The codes put it in one of two boxes and use a different model in each. ASCE 7 and EN 1998-1 draw their boxes' edges a hundred times apart in plate stiffness, each at a point where its own licensed model already misstates the middle wall by about a tenth — and an ordinary 200 mm slab sits in the gap between them.
The tendon that pulls before the deck arrives
A stressed ribbon is hung one span at a time, and the obvious fear is the stage at which one span carries its deck and the next does not: the pier between them asked for a whole span's thrust. It is not asked for that, because tendons cut to the finished length are already stretched across the empty span and pulling. For two 100 m spans at a fiftieth, the rigid pier's stage force is 4,109 kN against a crowd's 9,440 — unless the tendons were sized generously, when the stage overtakes the crowd.
The collector the slab does not need
A floor delivers its storey force to a short braced bay through a collector, a member along the brace line that gathers the floor's shear and carries it to the bay. The rule that sizes it assumes the floor hands over its shear uniformly along the whole line. A concrete slab does not: it is so stiff in shear that it sends most of its load straight into the bay, the collector carries about a quarter of the rule's force, and the slab beside the bay works at more than three times the rule's shear. A steel deck is the other way round. The rule is right for one floor, and safe for the other only while the slab stays uncracked.
The backprop that takes load nobody gave it
The arithmetic of propped construction says a backprop put in snug carries nothing until the next floor is cast, and then only a share of it. Count the props as the springs they are and that barely changes, because a steel prop is about seven times stiffer than the slab per square metre. Two other things change it. The young slab just struck creeps onto its backprops within a day and hands a quarter of a slab's weight down to the one below, which then carries 1.71 times its weight rather than 1.5. And a millimetre of slack at installation — about half the slab's own deflection — gives the struck slab back everything a backprop was meant to save.
The heavy chord the posts will not let work
A Vierendeel girder carries its shear as bending in its two chords, and when one chord is four times as stiff as the other the obvious rule gives it four fifths of the shear. With posts as stiff as the light chord it takes 0.56. The heavy chord's end moments have to be carried round each joint by a post, the post bends, and the heavy chord turns with its joints instead of bending between them. No amount of extra steel in that chord takes its share past 0.55 in the middle of a long girder; only the posts can, and they have to be about 150 times as stiff as the light chord to make the rule come true.
The backprop jacked tight lands on the floor below
A backprop put in snug shares only the load that arrives after it, and creep then pushes the young slab above onto it anyway. Jack it to a preload instead and the young slab is lifted at once — but the preload survives the week, so the lift lands on the slab below the moment the next level is struck, and about half of it is load creep would have moved within the week regardless. The best preload balances the week-old slab against the fortnight-old one, and with creep it is small: a fourteenth of a slab's weight, about six hundred newtons a prop. Anything over a fifth leaves the frame worse than snug. What a small preload does buy completely is immunity to slack.
The water the valley floor takes
An arch dam is not a stack of rings. At its crown it is also a vertical cantilever fixed into the valley floor, and the water at each depth is shared between the ring there and the cantilever in whatever proportion makes them bend alike. In a V-shaped canyon the short lower rings are stiff and carry nearly everything, and the top rings carry up to twice their own water because the cantilever leans on them. In a U-shaped canyon the cantilever takes half the reservoir and bends the heel into tension that the ring formula never sees.
The preload that cannot be taken back
A backprop jacked tight under a young slab relieves it and loads the slab below by the same amount at the same instant. The obvious repair is to slacken the backprop once the young slab is past its worst, so that the preload never reaches the slab below. It cannot work. Slackened to snug, a backprop lets go of everything it carries, not only its preload, and the young slab's load jumps from 1.19 to 2.00 times its weight. Let down by the preload alone, it gives back a load the slab below has already carried at its worst.
The load that visits every panel
A Vierendeel girder checked for a load at mid-span is checked for one position of a load that, on a bridge, stands everywhere in turn. Crossing it, a 100 kN load puts 1.7 times the mid-span check's moment into the end panels' chords, loads the middle post that a central load leaves idle, and makes the deck chord a beam between its posts in every panel where its share of the shear is small. Equal chords stay the stiffest arrangement; a vehicle whose axles span a panel cannot stand in the middle of one.
The day taken off the floor cycle
A frame cast a floor a week loads its slabs with the same multiples of their weight whether the cycle is seven days or four. What a shorter cycle changes is how strong each slab is when its load arrives, and it changes that unequally, costing the youngest slab more than the one below it. That is why a faster cycle makes a jacked backprop more useful rather than less, and why a frame that wants four days needs both a second level of backprops and a preload to be as safe as a week on one.
The floor that feeds two bays
A brace line with a braced frame at one end and a core wall ten times as stiff at the other is analysed one of two ways. As a rigid floor, which shares the line's force between the bays by their stiffness and gives the frame 9%. Or as a flexible floor, which gives each bay the half of the line nearest it, 50%. Solved as a membrane, an uncracked concrete slab gives the frame 16%, the same slab cracked 30%, and a steel deck 37%. The floor does not send its shear to the nearer bay; a stiff floor sends it to the stiffer one. The frame's design force depends on which state the floor is in when the storey force arrives, by more than a factor of two.
The truss sized to lose a diagonal
A Pratt truss with a counter-diagonal in every interior panel, sized fully stressed, starves its middle counters to nothing and saves a little steel over the plain Pratt. Ask it to survive the loss of any one diagonal at the accidental two thirds of its load and the family of equal designs collapses to one: every counter comes back, sized by its partner's loss, and the truss needs 1,304 units of steel against 1,200 — 9 per cent for an alternative path the Pratt cannot have at any price. A lost chord can be survived too, by the panel's diagonals turned into a chord, for twice the steel. Four members in the end triangles cannot be survived at all.
The hanger that cannot be made soft enough
A network arch's crossed hangers swing through nearly all their force as traffic passes, because they are the web of a truss. Make them softer — a spring at each anchorage — and the tie ought to take back some of the shear and the hangers' ranges ought to fall. They hardly do. A tenth of the stiffness takes 6 per cent off the worst range and adds a third to the tie's bending; a fiftieth takes 18 per cent off and multiplies the tie's bending by 3.7. The range belongs to the truss and leaves only when the truss does, which vertical hangers show at 194 kN against 678 and eleven times the bending. So the hanger is sized for its range, eight times the area its strength needs, and the stiffness that comes with it costs the range nothing.
More hangers, and the same steel
A network arch's crossed hangers are the web of a truss, and a live load's shear passes through them, so every hanger swings through nearly all of its force. The obvious cure is more hangers, each crossing more of its neighbours, so that every section's shear is shared among more diagonals. It works hanger by hanger — three times the hangers, a third of the range — and not at all in total: the hangers' fatigue steel, sized for their ranges, is set by the shear the arch carries and barely changes with how many hangers it is divided among. What more hangers buy is elsewhere.
The post sized by what it must survive
A Vierendeel girder's posts are usually all one section, and a crossing load gives them peaks that differ by a factor of two and ranges that barely differ at all. Size each post to its peak and the steel falls by a quarter — and the middle post, lightened to two-fifths of the chords, sweeps twice the stress range the whole girder used to, and lasts a seventh as long. Size each post to its range instead and the girder needs less steel than the uniform one, not more, because the posts that can be lightened are the ones at the ends.
Nine piles and a third of the pull
A group of piles in settling ground settles several times further than one pile, because each pile drags the soil around its neighbours down with it. Put the same group in heaving clay and the same interaction runs the other way, and in the pile's favour. Each pile holds the clay back from its neighbours, the clay between them rises with the piles rather than past them, and the pile at the middle of a nine-pile square, which might have been expected to be pulled hardest of all, is hardly pulled at all. The tension that remains goes to the corners, and it is about half of what a pile alone would carry.
The load goes to the cable furthest along
Applied to one stiffening member, Castigliano's theorem halves or thirds its deflection and leaves its force alone, since there is only one member to carry it. A net has many, each at its own place on its own curve, and when the wrong energy has to divide a load among them it hands it to whichever is furthest along. The peak cable force comes out a fifth too high on one net and a quarter too low on another, by the same mistake. Only a net with no pretension at all gets the force right, and even that one gets the deflection wrong by a factor of three.
Named alongside it
The objects these essays reach for when they reach for this one.
StiffnessLoad pathConstruction sequenceBackproppingDiaphragmEarly-age strengthLateral systemProppingCreepFree bodyPreloadShear wall