Theme

The load must go somewhere — page 21

Essays 481 to 487 of 487 on this thread, in the same order.
Visits when the force says, against visits on dates. The creep force in one arm of the late-connected outrigger over fifty years: re-shimmed at 1, 3, 10 years, never above 1.40 MN; re-shimmed whenever a load cell reads 1.40 MN, 3 visits, at 12 months, 4.1 years, 22.7 years; and whenever it reads 0.58 MN, a tenth of the design wind, 8 visits, the first three at 5 months, 7 months, 1.1 years. Structural form

The arm that calls for its own visit

An outrigger connected to a concrete building collects the core's and the columns' differential creep, and re-shimming its joint every few years lets that force go. Dates on a drawing are a guess at how fast the building will creep. A load cell in the joint replaces the guess: re-shim whenever it reads 1.40 MN and three visits, at one, four and twenty-three years, hold the arm there whatever the building does. A building that creeps 60 per cent more than predicted needs a fourth visit; the dated schedule lets it reach 2.30 MN. Holding a tenth of the wind takes eight visits, three in the first thirteen months, and a contractor who can come within weeks.

Doubtful piers that may rise or settle, by how much. Twelve 7 m spans under the full 35 kN/m, the fifth and eighth piers each moving anywhere between rising and settling by the amount on the axis, the largest moment over every combination. At ±40 mm: continuous 518 kN·m, groups of three 465, joints over the doubtful piers 335, each in a pair 459, simple spans 214. Internal forces

The pier that may rise belongs under a joint

A pier that may only settle is best put in the middle of a two-span pair, whose hogging a settlement relieves before it adds to anything. A pier on swelling clay, or over a culvert that may be relieved of its fill, may rise instead, and then the pair is the worst place for it: 40 mm of heave puts 459 kN·m into a pair that would have carried 230 for the same settlement. The place that is gentle both ways is the end of a group, under a movement joint. With the doubtful piers' movement known in size but not in sign, joints over them carry 335 kN·m where pairs carry 459 and groups of three 465 — and nothing with the same traffic envelope does better.

Where the plates feel the cross-frame, and where they never did. The range of the corner angle over one crossing of a 60 m box 4 m wide and 2.5 m deep with ring frames at 4 m and a cross-frame every 20 m, under a four-axle lorry of 440 kN at 1.5 m off its centre line, along the span. With no clearance it is 0.21 mrad at the cross-frames, 0.48 midway between them and at most 0.52; with 0.5 mm of clearance 0.36 at the frames and at most 0.53; with 1.0 mm of clearance 0.50 at the frames and at most 0.53; with no cross-frames at all, 0.51 and at most 0.53. Sections and stress

The plate the loose frame stops protecting

A cross-frame bolted through clearance holes does nothing until a lorry has distorted the box far enough to take up the hole, and among ring frames a millimetre is nearly the whole distortion a lorry produces. What that costs is not the frame's own life but the plates' around it. A tight frame holds the corner angle's range to 0.21 mrad over a few metres either side of itself; a millimetre of clearance lets it rise to 0.50, and a detail there loses a factor of thirteen in fatigue life. The box's worst place does not move, because it was never at the frame. The critical detail moves only if the frame's own detail is a worse category than the plain plate's, which it usually is.

The later the fill, the less of the slab's shrinkage is still to come. The slab end's movement away from the stem over thirty years after the fill is finished, its shrinkage and its seasons together, for a 3 m stem fixed at its base, its fill rolled in 250 mm lifts at 60 kN/m, its top held by a 30 m ground slab in 60 per cent humidity swinging 3.0 K either way each year, the fill finished 4 weeks, 6 months, a year, 2.0 years after the slab was cast; the stem lets go of the slab at 2.08 mm. At thirty years the shrinkage has taken the end 4.42, 3.14, 2.36, 1.57 mm away; the slab last touches the stem 1.3 years on, 5.3 years on, still in the thirtieth year, still in the thirtieth year. Equilibrium

The slab left to dry before the fill

A basement stem propped by its ground slab keeps the pressure the roller locked into its fill only while the slab still bears on it, and a slab cast four weeks before the fill shrinks away within sixteen months. Casting the slab first and letting it dry before the fill goes up sounds like the cure. Six months of drying buys four more years; a year keeps the slab touching the stem every summer for thirty. But a slab that touches only in summer gives back the propped moment only in summer, and in the tenth year a stem filled two years late still reaches 63 kN·m of its unpropped 70. The delay keeps the contact. It does not keep the design.

Its own weight bends the line the force runs along. A 168.3 × 5.0 mm steel tube 8.0 m long between pins, horizontal, weighing 198 N/m, as a strut pushed with 100 kN and as a tie pulled with as much, drawn with the depth exaggerated 17 times. Statics alone puts the line of thrust on a parabola 15.8 mm off the straight line between the pins — above it for the strut, an arch; below it for the tie, a cable — and the two end forces meet on the weight's own line at twice that. The band is the kern, ±39.6 mm. The member sags 9.2 mm as a strut and 4.3 as a tie, and bends by the gap between its axis and its thrust line: 25.0 mm for the strut, 11.5 for the tie. Equilibrium

The load at which a strut's weight matters least

A pinned member that weighs something is no longer a two-force member — its own weight bends the line its force runs along into a parabola. A tie only straightens as it is pulled harder. A strut does not: its weight matters least at very nearly half its Euler load, for every section, length and material, and past a certain length it matters at every load the strut can carry.

A splice's loop, and the one loose bolt it can show. The loop a gauge across a lap splice of six bolts at a 70 mm pitch in two 140 by 15 mm plates, each bolt clamped by 172 kN with a friction of 0.50 draws under a cycle of ±120 kN, drawn as the reading less the tight row's straight line, so that only what is not elastic shows: all six tight, the end bolt at half its clamp, and the third bolt at half. Its width at no load is 0.710 µm tight, 1.381 with the end bolt loose and 0.712 with the third. Connections

The loop that sees only the end bolts

A friction joint's hysteresis loop below slip carries its clamp in it, so a gauge across a splice reading a small loop could in principle tell a loose bolt from a tight one. In a row of six it can tell only some of them. The plates between the bolts share the load so that the two end bolts carry 38 kN of a 120 kN cycle and the middle two 7, and a loop's width goes as the square of a bolt's force: the end bolts draw the loop, the middle ones barely touch it. One end bolt at half its clamp nearly doubles the loop; the third bolt at half changes it by a third of a per cent. Forty rows of scattered clamps read their end bolts' mean with a correlation of 0.99 and their weakest bolt's with 0.51.

Every member's stress range as the load crosses the uniform girder. The stress range in each post (at its worse corner) and in each panel's chords (at the worst of their four ends, axial force and moment together) of a Vierendeel girder of six 2 m panels, 1.5 m deep, every member at first of one section (I = 117 × 10⁶ mm⁴), crossed by a 100 kN load, along the span. The posts range 50, 78, 76, 76, 76, 78, 50 N/mm² from end to end; the chords 71, 92, 103, 103, 92, 71. The worst member is a middle chord at 102.8, the worst post 78.3. Structural form

The girder sized member by member

A Vierendeel girder's posts can be sized to the stress ranges a crossing load gives them, and the earlier essay found that this keeps the girder's fatigue life for a tenth less steel. With the chords counted too — their axial force and their bending together — the girder's worst member is not a post but a middle chord. Sizing every member to that one range takes a quarter of the steel out and keeps the life; the posts barely move when the chords are resized, and sizing the two in turn settles in four passes. Sized for strength instead, the same girder uses more steel and lives a third as long, and sized to a range a fifth below the worst it is lighter than the uniform girder and lives twice as long.

All themes