The gap between two buildings
Assumes The spectrum is not a load, The period nobody chose and Two motions with one name.
Two buildings share a boundary. Both sway in an earthquake, and if the gap between them is too small they hit each other — which is called pounding, and which has damaged more buildings in more earthquakes than almost any other single mechanism because city blocks are built to the site boundary.
The question is how wide the gap has to be, and the arithmetic looks trivial. One building moves 120 mm and the other 220, so they need 340 mm between them.
The peaks do not coincide
Each building’s response is a time history — a sway back and forth, at its own period, driven by the same ground motion. Its maximum displacement occurs at some instant during that history, and there is no reason whatever for the other building’s maximum to occur at the same one.
What the gap has to accommodate is the maximum of the relative displacement , and the maximum of a difference is not the difference of the maxima unless the two are perfectly anticorrelated.
This is not a new problem. It is exactly the problem combining modal responses solves, one level up: several responses to the same input, each with its own peak at its own instant, to be combined into one number. The answer is the same:
with the cross-correlation coefficient of the two responses. The only new feature is the minus sign, which is there because the quantity wanted is a difference rather than a sum.
The coefficient depends only on the period ratio
has a closed form — the same one modal combination uses — and it contains the frequency ratio and the two damping ratios and nothing else:
At it is exactly one. At , the pair drawn, it is 0.029 — the two responses are essentially independent. At below about 0.8 it is negligible for ordinary damping.
So the answer has two regimes and the boundary between them is sharp:
| period ratio | gap needed | |
|---|---|---|
| 1.00 | 1.000 | 100 mm |
| 0.90 | 0.470 | 176 mm |
| 0.80 | 0.147 | 227 mm |
| 0.57 | 0.029 | 248 mm |
| 0.20 | 0.001 | 250 mm |
Buildings that sway alike need the difference of their drifts. Buildings that sway differently need very nearly the square root of the sum of the squares. Between the two the answer moves quickly, and it never reaches the sum.
Why that is the opposite of the intuition
The word resonance does a lot of damage here. Two structures with the same period sound like the dangerous pair — they will get excited by the same frequencies, both reach their maxima, and surely that is worst.
Both halves of that are true and the conclusion does not follow. They do both reach their maxima. They reach them at the same instant and in the same direction, because they are being driven by the same ground motion through the same transfer function, so they are moving together and the gap between them barely changes.
The mismatched pair is worse for exactly the reason it sounds safer. One is at its extreme while the other is at its middle or its other extreme, so the relative movement can approach the sum even though neither building is doing anything remarkable.
What the codes say
Most of them say , the absolute sum, and some allow the square root of the sum of squares where the two structures’ dynamic properties are known.
The absolute sum is safe and expensive, in the way an envelope assembled from separate load cases is: correct at every station and corresponding to no state the structure ever occupies. For the pair drawn it demands 340 mm of gap where 248 suffices — 92 mm of building width per boundary, on both sides of every plot, on every floor, permanently. On a city block that is a material quantity of floor area given up to a combination rule.
The case where the conservatism inverts is the one worth watching, and it exists: where the two buildings are nominally identical — a pair of blocks by the same developer, same frame, same height — a designer applying the correct rule finds a very small gap is needed, and is relying on the period ratio staying at one. It will not: the two buildings have different tenants, different fit-outs, different foundation conditions on the two halves of the site, and different amounts of cracking after the first shake. A rule that gives its smallest answer where the input is least reliable is a rule to be careful with, and that is the honest argument for the absolute sum.
If they do meet
The two buildings meet with a relative velocity of the order of from each — 1.94 m/s in total for the pair drawn. Conservation of momentum with a coefficient of restitution gives the impulse
597 kN·s here. That impulse is shared equally and absorbed unequally: the 500 tonne building takes a velocity change of 1.19 m/s and the 300 tonne one takes 1.99.
The damage in recorded poundings is overwhelmingly on the lighter, more flexible building, and this is why. It is also why the worst arrangement is a stiff low building against a flexible tall one: the impact happens at the top of the low building, which is a point on the tall one’s height where nothing was designed for a horizontal point load, and the tall building’s column at that level takes a shear it has no capacity for.
Why it happens so often
Pounding is not a rare failure. In every urban earthquake with a decent post-event survey it appears in a large fraction of the damaged buildings, and the reasons are all about how cities are built rather than about how structures behave.
Buildings are built to the boundary. Land is expensive, plots are narrow, and the gap between two buildings is floor area nobody is paid for. Every millimetre of it is argued about.
The neighbour was built first, to an older code. The gap that exists is the one the earlier building left, and it was calculated — if at all — against a smaller design event and a stiffer assumed structure.
The two buildings have different owners. So the total gap is the sum of two independently chosen setbacks, neither owner knows the other’s dynamic properties, and neither has any incentive to give up more than the minimum.
And the gap fills up. Expansion joint material, services, cladding brackets, birds’ nests and forty years of debris. A 100 mm gap that has been closed by 60 mm of accumulated fabric is a 40 mm gap, and nothing inspects it.
Which free body produced the number
There is no free body until they touch, and that is the point. Up to the moment of contact the two structures are independent dynamic systems with no interaction at all, and the whole calculation is about a geometric condition — a distance being exceeded — rather than about a force.
That is unusual enough in this collection to be worth naming. Almost every check here is a comparison of an action with a resistance. This one is a comparison of a movement with a clearance, and the resistance side of it does not exist: there is no strength anybody can add to a building that lets it be closer to its neighbour.
The three things a designer can move
The gap is one of them and it is the least available, because it costs floor area on every storey for ever. The other two are worth naming.
The periods. Moving one building’s period toward the other’s raises the correlation and shrinks the required gap, and it is achievable — a stiffer or softer lateral system, an added damper, a different bracing layout. It is almost never done deliberately, and it is the only intervention that makes the required gap smaller rather than making the consequence of closing it less bad.
The contact. If the buildings are going to touch, they can be made to touch well: a bumper of a soft, thick, replaceable material at every floor level, aligned floor-to-floor, sized so the contact lasts long enough for the force to stay finite. That converts an impact into a collision with a known stiffness, which is a design problem rather than an accident.
The last of those is the elegant answer and it is used: several retrofits of adjacent towers have replaced a gap that could not be widened with a set of viscous dampers across it, turning the worst feature of the pair into the mechanism that protects them.
Where the model stops
The two buildings are on the same ground. They are not quite: two adjacent sites can have different foundation conditions, and ground with a period of its own filters the motion before either building sees it. Two buildings driven by slightly different inputs are less correlated than the formula says, which pushes the answer back toward the square root of the sum of squares.
Both structures are single-degree systems. They are not: each has several modes, the drift at the level where they touch is not the roof drift, and the relevant is the displacement at the contact level rather than at the top. For two buildings of different heights the contact is at the shorter one’s roof and the taller one’s mid-height.
The floors line up. Where they do not, the collision is floor-to-column rather than floor-to-floor, and it is much worse — a floor slab is a hard, heavy, in-plane-stiff object and a column is not. Floor levels that match is the single most important mitigating feature of an adjacent pair, and it is an architectural decision.
The displacements come from a spectrum. Which means they are already peak values of independent histories, and combining them with a correlation coefficient derived for stationary random processes is an approximation applied to an approximation.
The restitution is 0.65 and is a guess. It depends on the local damage at the contact — a concrete edge crushing is a very different collision from two steel plates meeting — and the impulse depends on it linearly.
Nothing here is inelastic. A building that has yielded has a longer effective period and a different damping, so the period ratio at the end of the shake is not the one it started with. Two buildings yielding by different amounts drift apart in period as the event proceeds, which lowers the correlation exactly when the displacements are largest — and an equal-displacement rule says the displacements themselves barely change, so the gap requirement grows during the event.
And no drawing here shows the collision. Everything above is either a peak displacement or a momentum balance, and neither of those is a picture of the event: a contact lasting a few hundredths of a second, repeated a dozen times during the shake, at whichever floor levels happen to be closest.
The number to design to
Putting it together, the gap a designer should provide is
with two qualifications that between them recover most of the conservatism the formula removes.
Use the displacements at the contact level, not at the roofs, and take them from the design event rather than from a service one — a gap is a collapse-prevention item and there is no serviceability version of it.
And do not take above about 0.5 unless the two structures are genuinely the same structure. The high-correlation regime is the one where the formula is generous and the input is least reliable, and a period ratio that starts at one drifts away from one over the buildings’ lives.
Applied to the pair drawn, that gives 248 mm rather than 340 — a saving of 27 per cent, arrived at by asking when the peaks occur rather than only how large they are.
The ladder from here
Later rungs on this anchor: the multi-storey case, where the contact level and the mode shapes at that level decide the relative displacement rather than the roof drifts. Floor-to-column pounding and why it is the arrangement that kills people. The contact model itself — a spring, a spring and a dashpot, or a Hertz law — and how much the answer depends on which. Retrofitting an existing pair, where the gap cannot be changed and the options are to stiffen one building toward the other’s period, to link them together deliberately, or to accept the pounding and detail for it. Linked buildings, where a damper spanning the gap is designed to dissipate exactly the energy the collision would have delivered. And the urban-scale version, which is a row of buildings in a terrace, where the end building has a neighbour on one side only and takes everything the row delivers.
Named alongside this one
Essays reaching for the same objects. Nobody chose these; they are what the concept index makes visible.
- Made weaker on purpose damping · natural period · response spectrum · serviceability
- The ground is a spring damping · natural period · response spectrum · serviceability
- The deck that is its own cable load path · natural period · serviceability
- The force read off a frequency damping · natural period · serviceability
- The liquid has a period of its own load path · natural period · response spectrum
- The load that is over before it has moved damping · load path · natural period
The objects this essay names
Each one links to every other essay that touches it.
DampingImpactLoad pathModal combinationMovement budgetNatural periodResponse spectrumServiceability