The deflection that arrives years late
The deflection that arrives years late. The multiplier on a concrete member's deflection under a sustained load, against time. The elastic deflection arrives on the day the load does and is the 1.0 at the left. After a year it has been multiplied by 3.00, after five years by 3.29, and it approaches 3.38. Nothing has been added to the load and nothing about the strength has changed: this is a serviceability failure arriving on a structure that passed every strength check on the day it was built.
23 essays call
creep-curve. The drawing above is what it returns with no arguments at all; every
call below passes it something, because a placement that passes nothing draws whichever
member of the family the generator happens to default to rather than the one its essay
argues about.
Where it is called
Changing this generator changes every one of these figures.
The deflection that arrives three years late
A concrete beam that passes every check on the day it is built goes on deflecting for a decade, and ends up three times where it started. Nothing about the load changed, and nothing about the strength was ever in question.
The strain that was imposed, and the stress that leaked away
Multiply a restrained shrinkage strain by the modulus and the answer is three times the tensile strength — which predicts that every restrained concrete member ever cast has cracked. Most have not, and the reason is that the material creeps while it is being stressed.
The columns are shorter than the core
Every column in a tall building gets shorter as the building is built on top of it, and the core beside it gets shorter by a different amount. The floors between them tilt by the difference — and the difference is largest exactly half way up, because a floor near the top has almost nothing built above it and a floor near the bottom has almost nothing beneath it.
The column that fails years later
A concrete column under sustained load goes on straining at constant stress, so its deflection grows — and because the second-order moment is the load times that deflection, the demand grows with it. There is a load below which the two settle and one above which they never do.
Stiffer than its cracked section says
At a crack the concrete below the neutral axis has gone and the steel carries the tension alone. Between the cracks it has not gone — bond drags it back into tension, the steel strain drops, and the curvature averaged over a length of beam is neither section's.
The section that changed while it was being loaded
A stress is computed from a moment and a section modulus. When part of the moment arrived while the section was a different shape, there is no single section modulus to divide by — the stresses add and the properties do not, and two identical finished beams can differ by half again in stress with nothing on the drawing to say which is which.
The curvature nobody applied
Concrete shrinks as it dries, by about half a millimetre in every metre. In a symmetrically reinforced member that is a shortening and nothing else. In a member with more steel in one face than the other — which is every beam and every slab — the steel holds one side back and the section bends, with no load on it at all.
The load that was left on too long
A timber beam that carries a load for fifty years fails at about fifty-nine per cent of the stress the same beam carries for five minutes in a testing machine. Nothing about the load varies, the member need not have deflected, and the relation between the two is a straight line on a logarithmic time axis over ten decades.
The limit that depends on a date
Total deflection can nearly always be met, and on a long span it is met with camber. The limit that actually decides the member is the other one — the deflection occurring after the brittle finishes are built — and camber does nothing for it whatever, because it is subtracted from both terms of a difference. The same beam passes or fails on the day the partitions went up.
The strength that is never used
Concrete's tensile strength appears in no bending calculation, no column calculation and no shear calculation with links in it. The whole design philosophy is that it cracks and the steel takes over. And it decides where nearly every transition in the subject sits — when a section cracks, how much minimum steel it needs, how far a bar has to be lapped, what a member without links can carry, and how wide a crack opens.
The strength it had on the day
Every concrete strength a design quotes is a twenty-eight-day cylinder value, and a structure is loaded long before that — formwork struck at three days, the next storey cast at seven, a prestressing force transferred at two. The number that existed at the moment the load arrived is a different one.
The stress that leaks away
Creep makes a load's deflection grow and an imposed strain's stress shrink, and the second is why restrained concrete does not crack as often as an elastic calculation says. The same material property runs both ways, and which way it runs depends on whether the structure was given a force or a movement.
The creep that belongs to the member
A creep coefficient is quoted for a concrete, and half of it is not a property of the concrete. It is the member drying out, and drying goes through the surface — so one mix creeps a quarter more in a thin slab than in a deep beam, gets there years sooner, and in saturated air forgets its size altogether.
The slab that dries from one face
A creep coefficient is one number for a member, and a member drying through one face does not have one. Give every depth its own humidity and the section a strain profile it cannot deliver, and two things follow that no single coefficient contains — a six-metre slab lifts eleven millimetres at its edges with nothing on it, and its top surface is past cracking before it has been loaded.
The support that had no moment when it was cast
Two beams are set on their bearings, carry their own weight for a month, and are then stitched together over the middle support. Nothing about the loading changes afterwards. Twenty years later the stitch is carrying 155 kilonewton-metres, because the concrete went on creeping and the joint would not let it — and how much arrives is decided by a crane schedule.
The prestress the member takes back
A tendon is stretched, locked off against the concrete, and then has to hold that extension while the concrete underneath it shortens by itself. Fifteen per cent of the force goes, most of it to creep, and how much goes is decided by the shape of the member and the air it stands in rather than by anything about the steel.
The slab that shrinks onto a finished beam
A precast beam with an in-situ slab cast on it is one member made of two concretes, and they do not age together. The slab's shrinkage is nearly the same whenever it is poured; what changes is how much shrinking the beam has left to share it with. Cast the slab at six weeks and it takes a ninth of the soffit's precompression away over thirty years. Cast it at a year and it takes a quarter, and goes into tension itself.
The pier that bends the wrong way
Two precast beams are made continuous over a pier by a joint cast with the deck, and the joint is designed for the hogging moment a continuous beam has there. Thirty years later it is sagging, by more than the moment that cracks its underside, because the beams were still cambering upward when they were joined. Whether that happens is decided by two dates — when the beams were cast and when the joint was — and the deck's shrinkage, which pulls the other way, is not enough to stop it.
MaterialsLoaded twice over before it is a month old
A concrete floor in a building going up a storey a week carries, in its first weeks, the wet weight of the floors being cast above it, handed down through the props. By Grundy and Kabaila's arithmetic that is twice its own weight on a single level of shores, and more with more levels — 2.25 on two, 2.37 on three — because every prop that carried wet concrete passes its load down the stack. The same props put in after the formwork is struck carry nothing until something new arrives, and the peak falls to 1.5, 1.33, 1.25. The heaviest day of a floor's life is decided by when its props went in, not how many there are.
MaterialsThe backprop that takes load nobody gave it
The arithmetic of propped construction says a backprop put in snug carries nothing until the next floor is cast, and then only a share of it. Count the props as the springs they are and that barely changes, because a steel prop is about seven times stiffer than the slab per square metre. Two other things change it. The young slab just struck creeps onto its backprops within a day and hands a quarter of a slab's weight down to the one below, which then carries 1.71 times its weight rather than 1.5. And a millimetre of slack at installation — about half the slab's own deflection — gives the struck slab back everything a backprop was meant to save.
MaterialsThe backprop jacked tight lands on the floor below
A backprop put in snug shares only the load that arrives after it, and creep then pushes the young slab above onto it anyway. Jack it to a preload instead and the young slab is lifted at once — but the preload survives the week, so the lift lands on the slab below the moment the next level is struck, and about half of it is load creep would have moved within the week regardless. The best preload balances the week-old slab against the fortnight-old one, and with creep it is small: a fourteenth of a slab's weight, about six hundred newtons a prop. Anything over a fifth leaves the frame worse than snug. What a small preload does buy completely is immunity to slack.
MaterialsThe preload that cannot be taken back
A backprop jacked tight under a young slab relieves it and loads the slab below by the same amount at the same instant. The obvious repair is to slacken the backprop once the young slab is past its worst, so that the preload never reaches the slab below. It cannot work. Slackened to snug, a backprop lets go of everything it carries, not only its preload, and the young slab's load jumps from 1.19 to 2.00 times its weight. Let down by the preload alone, it gives back a load the slab below has already carried at its worst.
MaterialsThe day taken off the floor cycle
A frame cast a floor a week loads its slabs with the same multiples of their weight whether the cycle is seven days or four. What a shorter cycle changes is how strong each slab is when its load arrives, and it changes that unequally, costing the youngest slab more than the one below it. That is why a faster cycle makes a jacked backprop more useful rather than less, and why a frame that wants four days needs both a second level of backprops and a preload to be as safe as a week on one.