The collapse mechanism of a propped cantilever
The collapse mechanism of a propped cantilever. A collapse mechanism, with the hinge position found by searching rather than quoted. Every position gives an upper bound on the collapse load; the lowest is 7.29, at a hinge 58.6 per cent along, which is a coefficient of 11.657 times Mp over the square of the span.
10 essays call
plastic-mechanism. The drawing above is what it returns with no arguments at all; every
call below passes it something, because a placement that passes nothing draws whichever
member of the family the generator happens to default to rather than the one its essay
argues about.
Where it is called
Changing this generator changes every one of these figures.
After the first yield, which is not the end
A steel beam whose extreme fibre has reached yield has not failed. It has started forming a hinge, and collapse waits until there are enough hinges to make a mechanism.
The structure that survives losing a member
Every check in this collection asks what a structure carries. None of them asks what is left when part of it is gone — and two frames with the same members, the same weight and the same factor of safety can answer that question completely differently.
The slab that spans both ways
A panel supported on four sides sends its load in two directions at once, and the share is decided by a fourth power — so a panel a third longer than it is wide has already stopped being a two-way slab in any useful sense. What it does at collapse is a different calculation with a different answer.
When there is no section to design
Beam theory needs a section, and a section needs the strain to be linear across it. Within about a depth of a support, a load, a corner or a hole it is not — and those are the regions structures actually fail in.
Two ways of being wrong
Plastic analysis has two theorems and they point in opposite directions. Any equilibrium field that nowhere exceeds the plastic moment gives a load at or below the collapse load; any mechanism gives one at or above it. Only one of those errors is safe.
The point the mechanism turns about
A collapsing frame is a chain of rigid pieces, and every piece is rotating about some point. Find those points and the whole collapse load reads off two ratios of lengths, with no trigonometry anywhere — and for a pitched roof the point in question is well above the top of the drawing.
The smallest of six failures
Everything else in this collection that fails does so in one way at a time. A dowel through timber does not — the wood can crush while the steel stays straight, or one plastic hinge can form in it, or two — and the capacity is the smallest of the six, which is the kinematic theorem of plasticity applied to a joint rather than to a frame.
The steel that is stronger in a millisecond
Every strength quoted anywhere in this collection was measured at about a ten-thousandth of a strain per second, because that is what a testing machine does, and nothing on a drawing says so. Load the same steel a million times faster and its yield stress rises by a third.
Pushed over until it will not stand
A structure in an earthquake is asked for a displacement rather than a force. A pushover answers a different question cheaply — how much base shear the frame has against how far its roof moves — and the whole art is in what happens when the two are laid over each other.
The load it can carry once
A two-span beam whose loads come and go span by span collapses at 150 kN under any one arrangement, and walks at 127. Between the two it can carry every arrangement once and none of them forever: each cycle leaves a few more milliradians of rotation at the support and a midspan fifteen millimetres lower. Melan's theorem finds the limit as the last residual moment line that fits, Koiter's as a mechanism no single load state can drive, and a cycle-by-cycle calculation walks exactly where both say it will.