The worst force in a pile is not at the top of it. A 0.6 m pile 24 m long through ground that is settling, carrying 800 kN at its head. Above the neutral plane the soil moves down past the shaft and the friction acts downward, so the axial force *grows* with depth; below it the friction acts upward in the ordinary way and the force falls again to the 300 kN the base takes. The maximum is 1282.87 kN at 13.78 m — 1.60 times the load applied, and it is at a depth where nothing is applied, nothing is connected and nothing can be inspected. A pile section chosen for the head load is under-sized by that factor over the middle third of its length.