The build-sequence generator
The props decide where the stress ends up. Bottom-fibre stress in the steel of a 12 m composite beam carrying 12 kN/m of wet concrete and 18 kN/m afterwards. Unpropped, the bare steel takes the first stage alone and reaches 292 MPa; propped, the finished composite section takes everything and reaches 186 MPa — a ratio of 1.57. 62% of the unpropped beam's final stress was locked in before the slab was structural at all. The deflections differ by 1.73 times for the same reason, and no drawing of the finished beam distinguishes the two.
1 essay calls
build-sequence. The drawing above is what it returns with no arguments at all; every
call below passes it something, because a placement that passes nothing draws whichever
member of the family the generator happens to default to rather than the one its essay
argues about.
Where it is called
Changing this generator changes every one of these figures.