The load must go somewhere — page 14
The cable that pays the factor back
A frame that loses a column carries the floor across the gap first by bending and then, as the beam sags, as a cable. The hope is that a path which stiffens as it deflects needs less than the factor of two a suddenly loaded spring does. On the bending plateau it does — 1.18 at nine tenths of the collapse load. But past one depth of sag the cable is a straight line again, and the factor climbs straight back toward two: 1.73 at one and a half times the collapse load. And the connections are asked for a tenth of a radian on the way.
The filler that cannot be gentle twice
A crushable filler in the gap between two buildings caps a collision at its crush force, but a filler soft enough to make the everyday contacts gentle runs out on the hardest one. Grade it — soft at the face, strong behind — and the soft layer takes the small contacts while the strong layer stops the large. The energy says otherwise. Every kilojoule the soft layer does not absorb, the strong layer must, in less depth: in a 40 mm filler, an outer half at 1.5 MPa needs an inner half at 56 MN, far above the 35 MN of the bare concrete it was meant to improve on.
The studs that send the check outward
Shear studs round a column fix a failing punching check, and they turn one check into three. The studs carry the control perimeter; past them the concrete alone must carry a perimeter long enough to need no help, and that outer perimeter stands further from the column the larger the load, so the studs follow it out. At a 10 m bay they reach four effective depths from the face, and the steel they need grows as the shear to the power 3.5. The third check, at the column face, is the one no stud reaches, and it ends the series at 11.8 m.
The counter fitted after the load
A truss with a counter-diagonal in every panel cannot take a change of length for free, so a camber cut into its members might seem to lock force into it. One cutting list locks in nothing — every member shortened by its own dead-load stretch — and the simpler lists lock in little. What locks in force is the shop: a millimetre of error per member puts 174 kN into some member of a truss whose largest dead-load force is 471. Leave the counters loose until the dead load is on and cut them to the gap, and the same errors lock in nothing at all.
The tension a fire leaves behind
A steel beam held at its ends by the structure around it is pushed into compression as a fire heats it, and yields, because its strength is falling while its expansion is not. When the fire goes out the expansion comes back and the yield does not. Held at a tenth of its own stiffness, a beam that peaked at 134 N/mm² of compression on the way up ends the fire at 195 N/mm² of tension — more than it was ever pushed, arriving hours after the fire was out, and on connections that were designed to carry shear.
The piles that would lift the ground
A basement too light to stay down can be pinned down with tension piles, each holding by the friction on its shaft. Add enough of them, close enough together, and the ground between them stops being something they grip and becomes something they carry: the group lifts out as a block, and the block's weight is all it can hold. For 600 mm piles 15 m long that happens closer than 2.06 m apart, a spacing with no raft, no water and no load in it — and every pile past that point is paid for twice.
The tendon that pulls before the deck arrives
A stressed ribbon is hung one span at a time, and the obvious fear is the stage at which one span carries its deck and the next does not: the pier between them asked for a whole span's thrust. It is not asked for that, because tendons cut to the finished length are already stretched across the empty span and pulling. For two 100 m spans at a fiftieth, the rigid pier's stage force is 4,109 kN against a crowd's 9,440 — unless the tendons were sized generously, when the stage overtakes the crowd.
The reaction that is made of short waves
Run a wide-flanged girder continuously over a support and its worst moment moves to the support. That moment is made by a reaction, a reaction is made of short waves, and a short wave puts its stress next to the web. Over the support of two 20 m spans with a 3 m overhang the flange works over a third of its width, against four fifths at the sagging peak, so the stress at the web there is 4.2 times the sagging peak for a moment only 1.7 times as large — and how much flange works depends on what the support bears on.
The thinner cover carries more
A plate spliced with a cover on each face is the standard cure for a lap joint's eccentricity, and the covers are usually sized as if they shared the load in proportion to their areas. A free body cut across the splice says otherwise. With nothing but the two covers crossing the cut, their forces must balance about the line the load acts on, so they share by lever arm and not by area — and the thinner cover, which sits nearer that line, carries more than half the load on less than half the steel.
The relief that belongs to the pressure line
An inclined tendon carries part of a prestressed beam's shear, and the rule is to subtract its vertical component, P times the slope of the tendon. In a continuous beam the tendon also provokes reactions, and the reactions make a shear of their own — a constant in each span, too small to look at. It is not small where it matters. Beside the end support of a two-span beam it doubles the shear left for the links, and moving the tendon without changing the beam at all can make the tendon's slope report that there is none.
Two slips are a shear test
One failed slope gives a line of soils, every one of which fits the failure. Two failed slopes give two lines, and where they cross is a soil that fits both. Whether the crossing means anything depends on how differently the two slopes loaded the ground: two slips at one angle cross only at zero cohesion, two at nearby angles cross anywhere in a twenty-degree band, and a flat, tall slope beside a steep, short one pins the soil to within two degrees — because each slip is a shear test at one normal stress, and a strength line needs two tests far apart.
One column is enough to find the sway
The unit load that finds a deflection may be carried on any structure that can carry it, so in a fixed-base portal the sway can be found from one column's two end moments and nothing else. Carry it on a three-hinged frame instead and the same sway comes out of all four members, one of them contributing a negative amount. Every structure gives the same total and a different account of where it came from — which means "how much of the sway is axial shortening" has no answer until a structure is named, and only one structure's answer is worth having.
The seam that pressure protects
A soft weld zone pulled at 55 degrees to the load gets no help from the metal around it, because 55 degrees is the line a plate under uniaxial tension does not stretch. A spiral-welded tube winds its seam at about that angle. Pressurise the tube and the line that does not stretch moves to the tube's own axis, so the spiral seam is suddenly well protected and the longitudinal seam is the exposed one. The soft zone's weakness belongs to the loading as much as to the weld: a seam is in danger only where the field around it leaves its line unstretched.
The web that leans and lifts the centre
In a rectangular box an interior web pulls the shear centre sideways toward itself and leaves its height alone, because a vertical web cannot carry horizontal shear. Most steel box girders are trapezoids, and their webs lean. Leaning the outer webs puts the shear centre below the centroid instead of above it; leaning an interior web lifts the shear centre as well as pulling it, by up to 35 mm in a 1.5 m box; and a vee of interior webs meeting at the bottom flange drops it by as much as 200. A web that leans carries horizontal shear, and whatever carries horizontal shear decides where the shear centre is in height.
The collector the slab does not need
A floor delivers its storey force to a short braced bay through a collector, a member along the brace line that gathers the floor's shear and carries it to the bay. The rule that sizes it assumes the floor hands over its shear uniformly along the whole line. A concrete slab does not: it is so stiff in shear that it sends most of its load straight into the bay, the collector carries about a quarter of the rule's force, and the slab beside the bay works at more than three times the rule's shear. A steel deck is the other way round. The rule is right for one floor, and safe for the other only while the slab stays uncracked.
The base that is rigid until the bed lets go
A column base drawn as fixed is a spring about a tenth as stiff as the rule for "rigid" requires, and most of its softness is the holding-down bolts stretching. Shortening the bolts helps less than it seems: even 60 mm of free length leaves the base below two thirds of the rigid boundary. Preloading them works completely — the base becomes half as stiff again as the boundary asks — but only while the grout under the plate stays in compression. The preload is spent at a definite moment, the same moment the column's own weight would buy for free, and the shorter the bolt the faster creep of the grout takes the preload away.
The plane where the pile and the ground agree
Downdrag is usually found by equilibrium: the ground hangs on the pile above a neutral plane, holds it up below, and the plane is where those balance the load and the toe's resistance. But the toe's resistance is not a number the designer can supply. It is whatever the toe's own settlement mobilises, and the toe settles because the ground drags the pile down. Solved by compatibility instead — the plane where the pile and the ground settle by the same amount — the drag, the neutral plane, the toe's force and the pile's own settlement all turn out to grow with how far the ground goes, and each kilonewton put on the head costs the pile three quarters of one, not half.
The stem that bends away from the roller
A roller compacting backfill against a wall leaves a lateral pressure behind it that the soil's weight alone would never make, and for a wall that cannot move that residual is Ingold's envelope. A cantilever stem moves as the fill goes up, and a residual locked in against it relaxes as the stem bends away. But not everywhere: the base never moves, so it keeps its pressure, and the last lifts have nothing placed after them, so they keep theirs. A 300 mm stem sheds an eighth of the rigid wall's base moment and the softest stem a third — never more, because the two ends of the stem are where the relief cannot reach.
The restraint that works where the twist is
A deck fastened along a beam's top flange resists its twist a little everywhere. A secondary beam framing in at mid-span resists it a lot at one point. Given the same total stiffness, the point does better — half the deck's total at mid-span holds the beam as well as the whole deck — because it works where the beam twists most. But a point restraint has a price the deck never charged: it takes the torque through one connection, up to three fifths of the whole applied torque, and if it is stiff it moves the worst twist out to the quarter-points rather than removing it.
The deck that forgets its own rhythm
A deck at twice a stay's frequency grows the stay whenever a quarter of the tension swing beats the damping. But a deck pushed by gusts is not a sine: its amplitude comes and goes and its phase drifts, and it holds a rhythm for seconds where the stay needs minutes to answer one. Against that deck the requirement is not a quarter of the swing but its square over sixteen times the deck's own damping — a sixth of the sine's at service, and a number set by how much the deck remembers rather than by how far it moves.
The backprop that takes load nobody gave it
The arithmetic of propped construction says a backprop put in snug carries nothing until the next floor is cast, and then only a share of it. Count the props as the springs they are and that barely changes, because a steel prop is about seven times stiffer than the slab per square metre. Two other things change it. The young slab just struck creeps onto its backprops within a day and hands a quarter of a slab's weight down to the one below, which then carries 1.71 times its weight rather than 1.5. And a millimetre of slack at installation — about half the slab's own deflection — gives the struck slab back everything a backprop was meant to save.
The island the film floats
Bore a hole along a shaft, off centre for a lubrication passage or a cable, and the soap film that solves its torsion has a second edge: a flat island over the hole whose height nobody knows in advance. Let it float where the film's pull balances the pressure on it, and the shaft keeps nearly all its stiffness and doubles the stress beside the hole, as a hole in any shear field does. Pin it at the outline's height instead and the same shaft has been slit to its hole, and loses a third of its stiffness. The island's height is the whole difference between a bore and a cut.
The strand in the sun beside the strand in the shade
Halfway through hanging a stressed ribbon, one span is a sagging cable full of segments and the next is bare tendon stretched nearly straight, and the pier between them carries the difference of their pulls. A warm day takes tension off both — and at the flat sag a ribbon is laid at, the hung span is so nearly all stretch that it loses three quarters of what the bare one does. What moves the pier is not the weather but the shade: strand in the sun beside strand under concrete, 35 kN on the pier for every degree between them. No sun slackens the bare tendon. The hour does change something else, which is the level the joints are cast at.
Twenty screws that peak together
A leaning screw reaches its peak at two millimetres of slip and then lets go, so a row of twenty along the grain looks like the long bolted joint again — the end screws past their peak and falling while the middle ones have barely started. Follow the row slip by slip and it is not: in a member of ordinary depth twenty leaning screws carry 98 per cent of twenty times one, against the 74 per cent the effective-number rule allows. What decides it is one ratio — the slip the timber's stretch spreads along the row against the width of a screw's peak — and the rule is right only for a brittle thread in a thin member.