Which failure arrives first — page 17
The hangers that carry the shear twice
Crossing a tied arch's hangers turns them into the web of a truss, which is why the tie stops bending. It also means a live load's shear passes through them, so as a load runs on from either end each crossed hanger swings from nearly nothing to nearly its most: on a 100 m arch the worst swings through 678 kN, 90% of the largest force in any hanger, where a vertical hanger swings through 194, half of its own. More dead load raises the force and leaves the range alone. The arrangement that is best for strength is the one that hands its hangers to fatigue.
The damper is only as good as its brace
A viscous damper added to a frame is held by a brace, and the brace is a spring in series with it. That pair has a ceiling: the most damping it can add is (√(1+κ) − 1)/2, κ being the brace's stiffness over the frame's, reached at one damper size and lost on either side of it. A brace as stiff as the frame allows 20.7%; a quarter as stiff, 5.9%. A damper larger than the best one is not better — it strokes less, locks, and turns the brace into a strut that moves the resonance instead of flattening it.
A quarter of the weld takes half the pull
A beam flange welded straight on to an unstiffened column flange is checked with an effective width of 191 mm out of 250. While the joint is elastic the plate's force does not use anything like that width: 47 per cent of it goes through the 65 mm over the web, and the flange has already yielded at 30 per cent of the force the rule allows. The rule's width is a plastic width, and the full-strength weld it insists on is what lets the joint get there.
A hole takes a tenth of every perimeter
A 300 mm riser cut a slab's depth from a column throws a shadow from the column's centre, and EN 1992-1-1 deletes whatever part of a punching perimeter falls inside it. The outer perimeter, being longest, loses the most length — but it loses the same share as the control perimeter, a tenth of each, because the shadow is an angle. The cost arrives somewhere less obvious: a seventh ring of studs, 24 per cent more steel, and studs needed in a bay a third of a metre shorter than before.
The beam the wind walks without pushing
A fixed-base portal whose beam carries exactly its collapse load is safe under that load applied once. Add a wind that comes from either side — a wind that does no work at all in the beam's collapse mechanism — and the beam can no longer carry the load for ever: 12 per cent comes off, and above that the midspan gains fifteen milliradians every cycle while the frame does not sway. Each knee takes its worst moment from a different wind, and the beam assembles a mechanism no single storm drives.
The prop that holds what the roller left
A basement wall whose ground-floor slab is cast before the backfill spans between its base and the slab, and as the fill is compacted against it the wall bows by a sixth of a millimetre. A free cantilever stem leaned sixteen times as far and shed an eighth of the roller's pressure; the propped wall sheds one per cent. Its base moment falls to a third, which looks like a gain, but the pressure has not gone: the slab now carries 22.6 kN a metre against the 6 an active-pressure design gives it and the 9 of soil at rest.
The pile the ground pulls apart
Clay that swells after its trees are felled rises past the piles in it, and the same compatibility that put a pile into compression in settling ground puts it into tension in heaving ground, at nearly the same depth. Nearly everything else changes. A lifted toe parts from the soil and holds nothing, so the shaft alone anchors the pile; the head load that added to the downdrag now subtracts from the tension; and the tension peaks 17 metres down, far below the short cage a lightly loaded pile is given. A house's piles in swelling clay are tension members nobody reinforced.
The ceiling the bore sets
A thick tube can be put into compression at its bore two ways: overstrain it past yield once and let it spring back, or build it from layers each shrunk on to the one inside. The second never yields the steel at all. Two layers carry 1.43 times a plain tube's pressure where an overstrain carries 2; four layers 1.75; and no number of layers, no overstrain and no combination of the two carries more than twice. The ceiling is not in either method. It is the range the bore's stress swings through, which belongs to the assembled wall, and the floor that range may reach, which belongs to the steel.
The beam that leaves the bed
A pretensioned beam's debonding is designed for the moment its strands are cut, when the casting bed holds it at its ends and its own weight is the largest relief its top fibre will get. Then it is lifted by loops a little in from its ends and stored on bearers a little further in. Setting the supports a metre in takes 31.5 kN·m off the self-weight moment along the whole length between them, not just at the ends, and the schedule that passed transfer with 0.07 N/mm² to spare has room for 51 mm of it. In the yard's conditions the bearers may come in 0.57 m; a metre in needs a third strand sleeved, and past 2.2 m nothing does.
The frames the deck pushes first
A half-through girder's U-frames are the ends of the cross-girders that carry its deck. Load the deck and every cross-girder sags, its ends rotate, and every frame's foot swings inward by millimetres before the compression chord has asked the frames for anything. It looks like a second imperfection on top of the chord's bow. It is a much weaker one: the frames all move together and the chord simply goes with them, so a 7.5 mm push adds 1.4 kN to frames that the bow loads with 13.6, and stiffer frames make it smaller, not larger. What the push leaves is mostly in the frames' own members, not in what they ask of the chord.
How far a doubler has to run
A doubler on a coped web is joined to the beam only along its welds, and the force reaches it through those welds from wherever it is welded. Stopped at the end of the cope, a plate welded along its two long edges gives about two fifths of the relief a fully joined plate would give at the very section it was put there for. Run on past the cope by four tenths of its own depth, it gives nine tenths. Welded all round, it is fully joined at any length.
The branch that holds the riser to a floor
A riser guided at every floor leans with each storey's drift and is barely bent by it. Take a branch off it and brace the branch to a slab, and the branch becomes a strut that holds the riser to that slab partway up the storey. The riser, which was carrying 3 N/mm², carries 71 at the tee. Let the branch slide at its brace and the riser is spared, but the branch is then bent by the riser's lean. The lean has to go somewhere, and the brace decides where.
The basement that leaks before it floats
A water table that rises after a basement is finished is a load that grows through the building's life, and the building's flotation check is the last thing it troubles. A metre of rise adds a sixth to the uplift on the whole building but over a quarter to the net load on the slab, which carries the water less its own weight. The slab's cracks, which a watertight basement is designed to, are the first thing to run out of room — and the limit for the cracks that pass right through it tightens as the water rises.
Three braces where the moment is
A row of torsional braces is spaced equally because that is how it is drawn, and under a uniform moment equal spacing is very nearly the best there is. Under a moment that peaks at midspan it is not. Moving the outer two of three braces toward the middle cuts the total stiffness a 24 m girder needs by a quarter under a uniform load and a third under a point load, and the bays it leaves at the ends cost nothing, because they carry so little of the moment.
The same studs, moved to where the slip is
A composite beam with half the studs full interaction needs reaches 85 per cent of the full plastic moment, if its end studs can slip as far as the beam asks — nearly 9 mm on a 12 m span, past the 6 mm a stud is trusted to give. Keep the same nineteen studs and crowd them toward the supports, and the end studs need 4.4 mm. Nothing about the beam's strength changes; what changes is how soon the slab's force builds up, and the least connection the slip allows falls from 0.69 to 0.40.
The preload that cannot be taken back
A backprop jacked tight under a young slab relieves it and loads the slab below by the same amount at the same instant. The obvious repair is to slacken the backprop once the young slab is past its worst, so that the preload never reaches the slab below. It cannot work. Slackened to snug, a backprop lets go of everything it carries, not only its preload, and the young slab's load jumps from 1.19 to 2.00 times its weight. Let down by the preload alone, it gives back a load the slab below has already carried at its worst.
Two islands in one film
Bore a hole along a shaft and its torsion film acquires an island that floats at a height of its own. Bore two and there are two islands, and the steel between them is a strip of film stretched from one to the other. Side by side at one radius, the islands float level, the strip is flat, and two holes cost twice one hole's stiffness and none of its stress. One inside the other on a radius, the islands float at different heights, the strip is steep, and the steel between the holes becomes the shaft's weak point.
The day taken off the floor cycle
A frame cast a floor a week loads its slabs with the same multiples of their weight whether the cycle is seven days or four. What a shorter cycle changes is how strong each slab is when its load arrives, and it changes that unequally, costing the youngest slab more than the one below it. That is why a faster cycle makes a jacked backprop more useful rather than less, and why a frame that wants four days needs both a second level of backprops and a preload to be as safe as a week on one.
The braces that stay where the framing puts them
Three cross-frames on a girder usually go where the floor beams or the bridge's bays put them, and cannot be moved toward the moment. They can still be made unequal. Giving the middle one three-fifths of the row's stiffness saves a sixth of the total under a uniform load and more than a quarter under a point load — most of what moving them would save. Moved and graded together, they save no more than moved alone, because both are ways of making every brace twist by the same amount.
The slab that shrinks away from the wall
A basement wall propped by its ground-floor slab before it is backfilled keeps the roller's pressure, and its slab takes it. Then the slab dries. Two millimetres of shrinkage at each end — about a year for a 30 m slab indoors — and a slab that only bears on the wall has let go of it, leaving a stem designed as propped to carry 2.6 times the base moment it was given. Tying the slab into the wall to stop that makes it worse: the slab goes on shrinking and pulls, and the base moment passes the free cantilever's.
The joint cast over the pier
Two pretensioned beams made continuous over a pier by a joint cast with the slab have ends that are still turning when the joint goes in, and the joint stops them. What it is then asked to carry depends on the day it is cast. At four weeks the beams' creep is still lifting their ends and the joint is sagged to half as much again as its cracking moment. At a year the beams have nearly stopped and the slab's shrinkage hogs the joint by as much the other way. Cast at about sixteen weeks, it is asked for almost nothing.
The nut turned after the storm
A preloaded column base that has been through a storm has lost some of its preload, and the obvious repair is to retighten its bolts. Left alone, the bolts stretched once in the first storm and never again; the base settled. Retightened, they are given back the preload the storm could not live with, and the next storm takes it away again by stretching them again. Retightening after every storm turns a base that settles into one that ratchets, a tenth of a millimetre at a time, and the count of storms it has in it is set by the bolt's elongation.
The arm that slips on purpose
An outrigger connected to a concrete building at topping out goes on collecting the columns' and the core's differential shortening for fifty years. The obvious cure is a joint that lets the arm move under the slow force and holds under the fast one. A friction joint cannot do it — once creep has brought it to its slip load it has nothing left on one side of the core, and a joint strong enough to hold the wind is never reached by the creep at all. A viscous damper can, because its force depends on how fast it is pushed rather than how far.
The beam at the bottom of the stack
A precast yard stacks pretensioned beams to save space, each on bearers resting on the one below. If the bearers line up, the weight above goes straight down through them and the bottom beam never knows it is there. If they land outside its own bearers, the stack hogs the bottom beam at every section between them and takes from its top fibre relief that its debonding schedule had already spent. A schedule built for the yard leaves the bearers of a stack of three seven millimetres to be out of line. A bottom beam with a schedule of its own can be given half a metre.