Theme

Which failure arrives first — page 13

Essays 289 to 312 of 541 on this thread, in the same order.
Four ways to put six bolts in one plate. Six bolts inside a 150 × 150 mm field of bolt centres, no two closer than 60 mm, loaded through a point (200, 0) mm from the field's centre. The two-column layout carries 193.5 kN complete and 138.8 kN with its worst bolt missing. The ring carries 167.2 kN complete and 117.8 kN with its worst bolt missing. The strongest found carries 234.3 kN complete and 149.7 kN with its worst bolt missing. The most robust found carries 231.6 kN complete and 174.7 kN with its worst bolt missing. The layout found by maximising the complete capacity and the layout found by maximising the worst omission are different layouts, 1 per cent apart when complete and 17 per cent apart with a bolt missing, and both beat the ring — the most evenly spread of the four — on both counts. The dashed line runs from each group's centroid to the load: 200 mm, 200 mm, 180 mm, 188 mm. The ringed bolt is the one each group can least afford to lose. Connections

The strongest layout leans on one bolt

Search a plate for the six bolt positions that carry most and the answer carries 234 kN — and loses 36 per cent of it if one particular bolt is missing. Move that one bolt fifty millimetres, into the corner the optimum had just left, and the group carries 232 kN and loses 25 per cent whichever bolt goes. Robustness here costs one per cent of strength, and a search for strength alone will never find it.

Two flanges, one bolt, one prying force. An end plate 18 mm thick with its bolt 45 mm from the beam web, bolted to a column flange 14 mm thick with the same bolt 30 mm from the column web; their tips are 35 mm beyond the bolt and bear on each other, so the prying force there is one force acting on both. Checked as two separate tee stubs on rigid bases, the end plate carries 109.3 kN per bolt (mode 2, web hinge and bolt) and the column flange 104.4 (mode 1, both hinges), so the component method gives the joint 104.4. The pair carries 92.3 kN, 12 per cent less, with the prying force at 44.7 kN and hinges in the end plate at its web and the column flange at the bolt line — the end plate's web hinge working with the column flange's bolt-line hinge, a mechanism that exists in neither tee stub on its own. Connections

The hinge that forms in the other flange

An end plate bolted to a column flange is two tee stubs sharing one bolt, and the force at their tips is one force pressing on both. Checked separately, as the component method checks them, the end plate carries 109 kN a bolt and the column flange 104. Together they carry 92 — by a mechanism with one hinge in each flange that neither tee stub has on its own.

Two blows on three foundations. The movement of a 150 tonne block struck by a hammer delivering 18 kN·s, twice, 0.75 s apart. On soil at 12.5 Hz with the 47 per cent of damping a half-space radiates, the block moves 0.86 mm and is still before the second blow. On the same soil over shallow rock, with 5 per cent, it moves 1.42 mm and rings for the whole interval. On springs at 4.0 Hz it moves 4.42 mm, and its ringing has not died when the second blow arrives. The peak force passed to the ground is 1.34, 1.32 and 0.42 MN: the heavily damped block and the lightly damped one pass almost the same force. Dynamics

The blow that has no frequency

A forge hammer does not shake its foundation; it strikes it. The transmissibility curve every isolation design is drawn on has nothing to say about a blow, and the rules it teaches mislead. The force a struck block passes to the ground is least at a quarter of critical damping, not the most; five per cent and forty-seven pass almost the same; and the springs that soften every blow can bring the block down to the hammer's own rate and make a train of blows ring four times as high as one.

Thirty years later, two concretes against one. Stress down the composite section after thirty years — a 160 mm slab cast 6 weeks after a 700 mm pretensioned beam — computed twice: with the slab as a second, younger concrete that creeps and shrinks by its own laws, and with it given the beam's concrete and age. With two concretes the slab ends at −0.15 N/mm² at its top and −0.30 at its bottom, the beam at −4.03 at its top and −7.43 at its soffit. With one, the slab is at −0.29 and −1.06, the beam at −2.22 and −8.37. The slab's own shrinkage has taken its compression away and handed it to the top of the beam, and the soffit — the fibre the prestress was designed to keep in compression — has lost 0.94 N/mm² of it. Compression is negative. Materials

The slab that shrinks onto a finished beam

A precast beam with an in-situ slab cast on it is one member made of two concretes, and they do not age together. The slab's shrinkage is nearly the same whenever it is poured; what changes is how much shrinking the beam has left to share it with. Cast the slab at six weeks and it takes a ninth of the soffit's precompression away over thirty years. Cast it at a year and it takes a quarter, and goes into tension itself.

The same restraint, spread and gathered. The buckled shape of a 24.0 m compression chord with the same smeared restraint, 0.35 N/mm per mm, delivered by U-frames at two spacings. With frames every 2.0 m the chord buckles in half-waves of about 5.1 m that ignore the frames — the smeared shape — at 1892 kN, matching the smeared answer. With frames every 4.0 m it buckles between them, with a node at every frame, at 1548 kN: 18 per cent below the smeared 1897 and at the Euler load of one bay. The dots are the frames. Stability

A row of frames is not a foundation

The top chord of a half-through girder is held sideways by U-frames, and the standard calculation smears them into a continuous elastic foundation. That is right while the frames are close and quietly wrong once they are not. The crossover sits at seven-tenths of the buckle's own half-wavelength, whatever the frames' stiffness — and beyond it the chord buckles between frames at a load no stiffening of the frames can raise.

Four ways of being nearly a mechanism. Four measures of the two-bar frame against the angle its bars make with the line between the supports, on logarithmic axes: the bar force as a multiple of the load, the condition number of the equilibrium matrix, the largest relative change of force from a one-millimetre error in any joint's position, and the joint's sag under the load as a share of the rise, for bars of axial stiffness 200 MN over a span of 8.0 m, loaded with 50 kN. The first three grow as one over the angle: at 2° the force is 14.6 times the load, the condition number 54, and a millimetre of error changes the force by 0.7 per cent. The sag grows as the cube: 4.3 per cent of the rise at 8°, 41 per cent at 4°, 3.1 times it at 2°. The measure that ends the analysis is not the arithmetic's. Equilibrium

Rigid by every test, and still folding

Counting the unknowns says whether a frame can be solved and the rank of its equations says whether it can stand, and both answers are yes or no. A frame a few degrees from a critical form passes both and is still nearly a mechanism — and of the ways that shows, the last to arrive is the one the rank test measures. Its own sag under load eats a tenth of its geometry at six degrees; sixteen-figure arithmetic would not notice anything until well below half a degree.

Four numbers read from a moment diagram. The moment diagram of the fixed-ended beam under a central point load, scaled to a largest value of one, with the four values the quarter-point formula reads: the peak, and the magnitudes at a quarter, a half and three quarters of the span — 1.00, 0.00, 1.00 and 0.00. The formula turns them into a gradient factor of 1.923. Solving the buckling problem for the whole diagram, on a beam 8 m between lateral restraints, fork-supported at its ends, gives 1.723: the formula is 12 per cent too high, on the unsafe side. Stability

The formula that reads four numbers

The factor that credits a beam for the shape of its moment diagram is usually taken from a formula that reads the diagram at four places — its peak and its quarter points — and nowhere else. On the straight-line diagrams it was built around it is safe. On a fixed-ended beam under a central load, whose moment is zero exactly where the formula looks, it is twelve per cent unsafe, and it would give the same answer for a diagram that deserves twenty-two per cent less.

The toe that runs out of ground. A block 6.0 m square on ground that bears 300 kPa at most — 10800 kN over the whole base — pushed 8.0 m up, weighing 3000 kN, drawn at three stages of the push with the lean exaggerated eight times and the contact pressure under the base; the dashed line is the ground's bearing limit. At a push of 629 kN it touches the ground over 3.9 m of its 6.0 and has not yet brought the ground to its limit anywhere. At a push of 770 kN it touches the ground over 2.5 m of its 6.0 and has brought the ground to its limit under 0.8 m. At a push of 776 kN it touches the ground over 2.3 m of its 6.0 and has brought the ground to its limit under 1.1 m. The last is the tipping push: the heel has lifted, the toe is pressing the ground at its limit over a widening block, and the lever arm of the weight about that block is shrinking as the block grows. Equilibrium

The ballast that helps it over

On rigid ground a heavier block is harder to tip, in exact proportion to its weight — that is the whole of the overturning check. On ground with a bearing capacity it is not. The toe presses the ground to its limit, the weight's lever arm shrinks as the yielded block under the toe grows, and the tipping push peaks when the block weighs half of what the ground under it can bear. Past that, every tonne of ballast added to steady it brings it closer to going over.

The strength design, and the least steel that is stiffer. A Pratt truss of eight panels at a depth of 1, carrying 10 kN at each top joint, each member drawn as wide as its section from a catalogue whose sections step by 25 per cent in area, the smallest 10 per cent of the largest member's need. Above, every member at the smallest section that carries its force. Below, the least steel that makes mid-span 1.50 times as stiff with every member still strong enough — the discrete optimum — with the 24 members it made larger drawn in the second colour: six of six top chord members, eight of eight bottom chord members, six of eight diagonals, four of seven verticals. The optimum uses 44 per cent more steel than the strength design, and it puts it where a member's real and virtual forces are both large; members either force leaves small are not touched. Deflection

The calculus answer, rounded, is the worst one

A real truss is built from a catalogue, and every member is rounded up to the next section. That rounding costs its stiffness almost nothing: the few per cent that separate the strength design from the stiffest survive it. What does cost is the next step. When a deflection limit governs, the obvious move — take the continuous optimum and round it up — needs more steel than any other way of stiffening the truss, and the exact discrete answer is within one per cent of a bound no catalogue can beat.

The rotation a bearing sees is made before it arrives. The end rotation of a 12 m pretensioned beam, 300 mm wide and 700 mm deep, with a 160 mm in-situ slab 1.2 m wide, in 60 per cent humidity, from the prestress's release at three days to thirty years, with sagging positive. Release turns each end 4.8 milliradians upward; creep takes it to 7.9 by day 28, when the beam is set on its bearings. The slab brings it back by 0.9, the surfacing by 0.1, and thirty years of creep take it to 8.1 upward. The band after erection is the imposed load (0.9 down) and a night with the top cooler (0.6 down) above the line, and a sunny day with the top warmer (1.0 up) below it. Every value in the band is below zero: under every load it will carry, the beam's ends still point up, and a level bearing is turned the same way for its whole life. Deflection

The angle made in the casting yard

A bridge bearing is designed for the rotation of the beam it carries, and the rotation is listed as a sum of load, temperature, creep and a tolerance. Followed through the life of a pretensioned beam, the largest term is none of those. It is the upward turn the prestress gives the beam's ends in the casting yard, before any bearing exists, and under every load the beam will ever carry its ends still point up.

The thin plate straightens onto the load line. The centre lines of a 10 mm plate lapped on a 20 mm plate, 100 mm wide, over 60 mm, carrying 60 kN with the grips 1200 mm from the overlap, over 480 mm either side of the overlap, with every vertical distance drawn 14 times the lengthwise scale; dotted, where the centres would be if the joint could not rotate. The load pulls along the straight line between the grips, each of which holds its plate on its own centre, and the moment where a plate enters the overlap is the load times the gap between that line and the plate's centre. The thin arm, flexible under tension, has swung toward the line: its gap is 0.49 of the rigid one, e/2. The overlap has turned with it, and the thick arm, too stiff to follow, is left 1.34 of e/2 from the line. Peak stresses: 193 N/mm² in the thin plate and 121 in the thick one, against 330 and 98 if the joint could not turn. Connections

The thicker plate takes the bend

A lap joint's eccentricity puts a moment into both plates, and the rule is that each takes half of the load times the offset. That is true only while the joint cannot turn. Let it turn, and a thin plate lapped on a thick one straightens under its own tension and hands its share across: the thick plate ends up bending a third more than the rule says, the thin one half as much, and in the limit the thick plate would take the whole of it.

The same blow, three seats under the anvil. The movement of the block — the part of a 150 t hammer foundation, 30 t of it the anvil, that lies below the pad — after one blow of 18 kN·s on the anvil, over three periods of the whole foundation on soil (12.5 Hz, damping 0.47). Rigid seat: largest movement 0.86 mm at 16 ms; pad at 4.0 times: largest movement 1.14 mm at 13 ms; pad tuned to the foundation: largest movement 1.18 mm at 35 ms. On the pad at 4.0 times the block rides the anvil's ringing: a ripple at the anvil's own frequency on top of the foundation's swing, whose first crest lands near the swing's peak. On the tuned pad the block receives the blow as one slow push, peaks later and higher, and then goes on ringing long after the rigid seat has settled, because the mode in which anvil and block swing against each other is damped by the pad and hardly at all by the ground. Dynamics

The pad that makes the blow worse

A forge hammer's anvil sits on a pad on its foundation block, and the pad looks like isolation: a spring between the blow and everything below it. For the block it is the opposite. Every pad an anvil can sit on makes the block move more than a rigid seat would, by half again when the pad is tuned near the foundation, and what the pad buys instead is a smaller force under the anvil. The hope that a tuned pad could act as a tuned mass works only against a train of blows, and only at a softness the anvil cannot live with.

The date the joint is cast decides the sign. The moment at the pier after thirty years, for two 12 m pretensioned beams, 300 mm wide and 700 mm deep with a 160 mm slab, made continuous over the pier by a joint cast with the slab, against the beams' age when the joint and slab are cast; sagging positive, with its three parts dashed. Cast at 7 days the joint ends at +320 kN·m; at 28, +214; at 90, +59; at a year, −164. It exceeds the joint's cracking moment of 159 kN·m for any joint cast before about 45 days, and it changes sign at about 130 days. From 7 days to a year the prestress's share falls from +555 to +204, because an old beam has made most of its upward creep before it is joined; the differential shrinkage's grows from −57 to −285, because an old beam has finished its own shrinking and the slab's is then all difference; the dead load's eases from −178 to −83. The first two move the joint the same way as the beams age. Materials

The pier that bends the wrong way

Two precast beams are made continuous over a pier by a joint cast with the deck, and the joint is designed for the hogging moment a continuous beam has there. Thirty years later it is sagging, by more than the moment that cracks its underside, because the beams were still cambering upward when they were joined. Whether that happens is decided by two dates — when the beams were cast and when the joint was — and the deck's shrinkage, which pulls the other way, is not enough to stop it.

The bow the frames have to hold. A chord 24 m long, EI 2.52 × 10¹² N·mm², held by U-frames every 4 m, carrying 930 kN critical at 1548 kN, drawn with its sideways movement exaggerated; its critical load is 1.66 times the chord force. Dashed, the worst of the bows tried: four half-waves, each 12.0 mm high, a five-hundredth of its own length. Solid, the chord once the compression has grown the bow; each arrow is the force the frame there must supply, the largest 13.6 kN — 1.47 per cent of the chord force. Stability

What the frames hold is the bow

A row of U-frames is sized for a force, and the rules give that force as a percentage of the compression chord's force that nobody derives. Derived, it is not a property of the frames at all. It is the chord's initial bow, grown by how near the chord works to buckling — and it is least, not greatest, near the stiffness at which the chord stops using the frames. Stiff frames tend to a limit that is π²/500 of the chord force: the familiar two per cent, arriving from a bow of one five-hundredth.

A curved I-beam's flanges curl. The cross-section of an I-beam bent to a radius of 3.0 m, its flanges 300 mm wide and 15 mm thick, with the flanges' radial movement exaggerated 47 times; dashed, where the flanges would be if they did not bend across their width. It is bent the way that opens the curve, so the outer flange is in tension and the inner in compression. A tensioned flange round a curve is pulled toward the centre of curvature and a compressed one pushed away from it, so here both are pressed toward the web, and each outstand bends like a cantilever from the web, its tip moving 0.80 mm. Bent the other way, both would curl away from it by the same amount. The bars are the stress along the beam across each flange: the full value at the web, falling toward the tips to 0.72 of it, so that the flange works as if it were 89 per cent as wide. Sections and stress

The flange that curls away from its stress

Bend an I-beam into a curve and each flange, carrying its stress round the bend, is pressed sideways by that stress. The outstands bend like cantilevers from the web, and in bending they move to a different radius and shed the very stress that pushed them. At a tight radius only a strip beside the web works. But the flange's loss of width arrives slowly, and a stress nobody computes for a straight beam arrives at once: the flange bending across its own width, harder than it is stressed along the beam.

At the tip it is the tension flange that swings. The buckled shape of a 3.00 m cantilever of 457 mm universal beam carrying a load at its tip at the shear centre, root built in: slope and warping held, seen from above: the sideways movement of the top flange and of the bottom flange along the length, scaled so the larger is one. The cantilever hogs, so its bottom flange is in compression, and that flange bows out furthest 0.58 of the way from the root, where it moves 0.15 — and has come back to 0.00 by the tip. The top flange, in tension, swings out to the full 1.00 at the tip. The section twists as it goes, so the flange that is doing the buckling is not the flange that moves most at the end. Critical moment at the root: 1266 kN·m. Stability

The flange that swings is in tension

A cantilever hogs, so its bottom flange is the one in compression and the one that buckles. At its tip the bottom flange barely moves: the section turns about it, and the flange that swings out is the top one, in tension. So the restraint that matters at a cantilever's tip is on the flange every rule for spans calls the wrong one — and the root, which a drawing shows as a single line, moves the critical moment by a factor of thirty-four.

The bolt that governs is worst at only one thing. The plate of a bracket of six M20 grade 8.8 bolts in three rows of two at 75 mm, loaded 150 mm to the side of the group and 150 mm in front of the column face, with the load at 60° from straight down, drawn at the group's capacity on the elliptical interaction, 227 kN. Each bolt's arrow is its shear in the plane of the plate and its disc grows with its tension, which comes from the load's distance in front of the column: bottom left 9 kN and 67 kN; middle left 33 kN and 76 kN; top left 74 kN and 84 kN; bottom right 40 kN and 35 kN; middle right 51 kN and 43 kN; top right 84 kN and 51 kN. The most shear is on the top right bolt and the most tension on the top left; the one that reaches its interaction first is the top left, and the next, the top right, is at 0.97 of its own. Connections

The bracket with no worst bolt

A bracket that stands out from its column is pulled off the column by the same load that twists it in its plane, so every bolt carries shear and tension at once. Straight down, one corner bolt is worst at both and the check is that bolt's. Tilt the load and the most sheared bolt and the most pulled bolt come apart; the one that fails is whichever of them its interaction reaches first, and at the angle where they swap the group has two worst bolts and no single one.

Between the two lines, a curve below both. The stress at which a plate of grade 355 steel of toughness 100 MPa√m, with an edge-crack factor of 1.12 fails, against the length of the crack in it on a logarithmic scale. Dashed: the fracture-mechanics line, the toughness over Y√(πa), and the yield stress; the usual check takes whichever is lower. Solid: Dugdale's strip-yield model, in which a thin strip ahead of the crack yields and the two mechanisms act together. The two dashed lines cross at the transition length, 20.1 mm, and there the strip-yield stress is 288 N/mm², 0.81 of both: the lower of the two simple answers overstates the plate by 23 per cent. At 20 mm the strip-yield stress is 289 N/mm² against 355 N/mm². Far from the crossing on either side the curve joins the line it approaches. Materials

The crack between the two checks

A cracked plate is checked twice: once for fracture, as if the steel could not yield, and once for yielding, as if the crack could not grow, and whichever answer is lower is taken. Each check is right far from the other. Where they cross — at a crack of twenty millimetres in an ordinary structural steel — the plate fails at four fifths of both, because a strip of yielded steel ahead of the crack is by then two and a half times as long as the crack itself, and neither check has a place for it.

The shear centre waits for a thick plate. Where the shear centre of a channel 300 mm deep with 100 mm flanges, all 10 mm thick sits, measured from the web towards the toes, against the thickness of a plate closing the toes as a fraction of the channel's own, on a logarithmic scale. Open, it is 33.3 mm outside the web. Closed by a plate as thick as the rest it is at the middle, 50.0 mm inside the web, towards the toes. With a plate a thousandth as thick it has moved 0.3 per cent of the way; a hundredth, 3 per cent; a tenth, 23 per cent. It is half way at 0.28 of the thickness and crosses the web at 0.22. Sections and stress

The plate that closes the circuit

Close a channel with a plate across its toes and its shear centre is expected to come in from the air beside the web to the middle of the box. It does — once the plate is about a quarter as thick as the channel. A plate a hundredth as thick moves it three per cent of the way while multiplying the torsion constant by eight, so the load keeps its lever, the section stops twisting, and the whole torque goes round the circuit as a shear flow through the thinnest plate in it.

One actuator, a tower and a floor. The peak amplification of a mode with 1 per cent damping under velocity feedback of gain 0.10, against the mode's frequency on a logarithmic scale, for control loops whose delay is 10, 25, 50 milliseconds. The dotted line is the mode without control, 50. With 10 ms: 4.6 at 0.2 Hz, 4.5 at 2 Hz and 5.0 at 8 Hz; with 25 ms: 4.6 at 0.2 Hz, 4.6 at 2 Hz and 19.0 at 8 Hz, unstable from 9.8 Hz; with 50 ms: 4.5 at 0.2 Hz, 5.3 at 2 Hz and unstable at 8 Hz, unstable from 4.9 Hz. A delay is a fixed time and a period is not, so the same loop that damps a tall building's sway is too late for a floor. Dynamics

The actuator that arrives late

A tuned mass damps a structure because its force arrives a quarter of a cycle behind the motion. Replace the mass with an actuator told to push against the structure's velocity, and the same quarter-cycle is fatal: the push that was damping becomes stiffness, the stiffness becomes a source of energy, and a gain that would have cut the response tenfold makes the structure vibrate by itself. The delay is a few hundredths of a second, which is nothing to a tower and everything to a floor.

Two quotients from one guessed shape. The critical load of a pin-ended column whose outer quarters keep 10% of the middle's flexural rigidity from four guessed shapes, each worked two ways: Rayleigh's quotient, strain energy of the guess's own curvature over the work of the load, and Timoshenko's, which uses the curvature the guess's bending moment would cause instead. The exact load is 3.225 EI₀/L². a half sine: 8.256 by Rayleigh and 3.745 by Timoshenko; its own sag shape: 8.041 by Rayleigh and 3.712 by Timoshenko; a mid-span sag: 8.875 by Rayleigh and 3.847 by Timoshenko; a parabola: 6.600 by Rayleigh and 3.492 by Timoshenko. Both are upper bounds, and from the same shape the second is never the worse of the two. Stability

The bound from underneath

Rayleigh's quotient turns a guessed shape into a buckling load that is always too high. Divide the same guess differently — use the curvature its bending moment would cause instead of its own — and a parabola that was 21.6 per cent high is 1.3 per cent high. Add one more number that needs no guess at all and the load is caught from below as well, which is the only side of it an amplifier can safely use.

The same riser, held three ways. The peak bending stress at each floor of a water-filled DN100 riser running the full height of the eight-storey building, under the same record, held three ways. Anchored against rotation at every floor it reaches 131 N/mm², at the lower floors where the drift is largest. Guided at every floor — held in line and free to turn — the same pipe never exceeds 3 N/mm². Guided everywhere but anchored at its base, it carries 77 N/mm² at the base and 21 N/mm² one floor up, and the guided values from there on. Dynamics

The pipe held at every floor

A riser runs the height of a building and is fixed at every floor, so each of its supports moves with a different floor. The floor spectrum prices the pipe's inertia, and for a pipe anchored at every floor the inertia is nearly irrelevant: the drift puts 131 N/mm² into a 100 mm riser at two thirds of a per cent, thirty times its inertia, and passes yield at 200 mm. Guide the same pipe instead of anchoring it and the drift almost vanishes — the pipe then feels only how much the drift changes from one storey to the next.

Weakest the day it is finished. The factor of safety against tipping of a 15,000 kN tower on a 10 m square base over soft clay (undrained strength 35 kPa, gaining 0.22 of the effective stress the tower puts into it, consolidating with a 90 per cent time of 7.1 years), through twelve years, for construction times of three months, one year and four years; its wind push grows as it rises. Built in three months, it bottoms out at 1.14 on the day it is finished; built in one year, it bottoms out at 1.33 on the day it is finished; built in four years, it bottoms out at 1.60 on the day it is finished. After that every curve climbs toward 1.93, the factor once the clay has consolidated. Had the finished weight arrived in an instant the factor would be 0.92; on ground that could not fail it would be 3.00. Equilibrium

The ground that arrives after the weight

A block's resistance to tipping on ground that can yield is a parabola in its weight, with its peak at half of what the ground can bear. On soft clay the ground's capacity is not fixed: it grows as the clay drains under the weight, and it grows years after the weight has arrived. A tower on such ground is at its weakest on the day it is finished — 1.33 against the 1.93 it will have once the clay has drained — and a silo filled in a week walks over the top of the parabola and down the far side, which is the other way a structure can be built.

A butt throat is strongest a little off square. The resultant a millimetre of throat can carry in S355 against the direction of the load, from straight across the weld (0°) to straight along it (90°). The fillet's falls throughout, from 385 to 314 N/mm². The butt's rises from 441 to 478 at 22.7°, because its cap limits only the normal stress and a little shear costs it nothing, and then falls to 314. So the butt's advantage over the fillet is 1.15 straight across, 1.29 at 22.7°, and none straight along. Connections

The shear that helps a butt weld

A partial-penetration butt throat pulled straight across its weld is capped at 0.9fu, which in S355 makes it 15 per cent stronger than a fillet throat. Add a little shear along the weld and the butt throat gets stronger, not weaker, because the cap limits only the normal stress — until the shear is 42 per cent of the pull, where it is 29 per cent stronger than the fillet and carries its largest resultant, 478 N/mm² against 441 straight across. Along a moment connection's web weld the mix of pull and shear sweeps through that peak, and in the direction that is all shear a single-sided throat is as good as two.

All themes