Scale changes everything — page 6
The face that dents and the core that crushes
A sandwich panel carries bending as a couple between its faces, and that is a calculation about the whole panel. Put a local load on one face — a foot, a fixing, a dropped tool — and the face becomes a thin beam on a soft bed, spreading the load over a length the fourth root of their stiffnesses sets. Then either the face yields and dents, or the core crushes beneath it, and which comes first is decided by one thickness: below it the face gives, above it the core does, and a steel-faced roof panel is on the wrong side of it for anyone who walks on it.
A deck is a spring, not a wall
An open-section beam loaded off its shear centre twists, and the usual reassurance is that the deck fastened to its top flange will stop it. The deck resists the flange's rotation with a stiffness per metre of span, and that stiffness has to be compared with the beam's own. On an 8 m beam a screwed deck of ordinary stiffness removes a third of the twist; on a 16 m beam the same deck removes three quarters, because the beam's torsional stiffness falls with the square of its span and the deck's does not.
The soft zone that takes all the stretch
The metal beside a weld in heat-treated aluminium is weaker than the rest of the member and more ductile, and it is tempting to read the second fact as a consolation. It is not. A member welded across stretches only where it is weak, and the weak zone is sixty millimetres long; a two-metre 6082-T6 tie that would extend 140 mm before necking extends 12 mm once welded, and the parent metal never yields at all. What decides it is one ratio, the zone's ultimate strength over the parent's, and the ductility returns only when that ratio reaches one.
The storey that cannot see the building lean
A sway check made storey by storey asks each storey how much it drifts under a push and how much gravity sits on it, and reads a critical load factor for the storey from the two. For a frame whose storeys rack like a stack of shelves that is exact. For a building that bends — a braced core, a wall — it is wrong twice. Taking the least storey as the building's reads a critical factor of 3.9 for a building whose own is 5. And amplifying each storey by its own factor finds a 2 per cent second-order increase at the ground storey, where the truth is 20, because the ground storey hardly drifts and carries the lean of everything above it.
The pressure the roller leaves behind
A retaining wall is designed for the pressure of the soil it holds, a triangle growing with depth. The soil behind most walls was not tipped there. It was placed in layers and rolled, and each pass of the roller pushed the soil sideways against the wall harder than the soil's own weight ever could, and left most of that push locked in when it moved on. Behind a 3 m wall compacted by an ordinary vibrating roller the locked-in pressure is a constant 28 kPa from half a metre down, the thrust two and a half times the active triangle's and the moment at the base three and a half.
Two welds, and the one that decides
A member welded twice has two soft zones in series. If they were identical, both would reach their ultimate strength at the same load and the member would stretch twice as far as with one weld before either necked. They are never identical, and the flat top of an aluminium zone's stress–strain curve means that a second zone five per cent stronger than the first gives only sixty per cent of its stretch. Every weld added makes the member weaker, by the statistics of its weakest link, and more ductile, by less than it would if the welds matched.
The abutment that spreads before it turns
A fixed arch is fixed only if its abutments hold still, and they have two ways not to. Turning releases the springing moment, but slowly: an abutment has to be a hundred times the rib's EI/L to hold nine tenths of it, and a footing on stiff clay under a slender concrete rib already is. Spreading does the opposite. The rib's own shortening is worth 13.6 mm of spread, so an abutment that gives 7 mm a side under the thrust doubles every secondary moment in the arch — and a footing on dense sand gives 8.
The floors that fill up together
A column may be designed for less than the sum of its floors' imposed loads because the floors do not reach their worst day together — an argument that assumes each floor's load is independent of every other's. Let any two floors be correlated, and the reduction the averaging can pay for shrinks, and stops shrinking at a higher floor. At a correlation of 0.16 that floor reaches the 0.7 the storey rule falls to. One tenant on five floors halves what twenty floors can average away.
The storey above the core decides
A building whose bending core runs to the roof shares one sway mode between its core and its frame, and the storey-by-storey stability check reads it wrongly twice. Stop the core five storeys short and the check becomes exact: the first storey of bare frame above the core reads the building's own critical factor to three figures, because the whole building buckles there and nowhere else. The check stays wrong below the core, and it goes wrong again when the frame above is more than about twice as stiff.
The reaction that is made of short waves
Run a wide-flanged girder continuously over a support and its worst moment moves to the support. That moment is made by a reaction, a reaction is made of short waves, and a short wave puts its stress next to the web. Over the support of two 20 m spans with a 3 m overhang the flange works over a third of its width, against four fifths at the sagging peak, so the stress at the web there is 4.2 times the sagging peak for a moment only 1.7 times as large — and how much flange works depends on what the support bears on.
Three kilopascals that halve a tube in bending
A long thin tube in bending flattens until its section can carry no more, at an oval of exactly two ninths of its radius. Put a pressure on it and nothing about that shape changes. What changes is how much bending it takes to get there — as the square root of one plus the pressure over the ring's own buckling pressure — and for a steel tube 1.2 m across with a 2.5 mm wall that unit is 4 kPa. Three kilopascals of suction halve its bending capacity; a fifth of an atmosphere inside doubles it and hands the tube to another failure entirely.
The arm that ignores the shape of the wind
The outrigger arithmetic is usually done for a wind that is the same at every height, and real wind is not: it grows with height, and an earthquake's first mode loads a building as a triangle. The natural guess is that a load concentrated towards the top moves the best place for the arm. It barely does. Put the same total wind on a 200 m core as a uniform load, a power-law wind and a triangle, and the best level moves by just over one per cent of the height. What moves is the force in the arm — half as much again under the triangle — and how far the top goes, while the arm's own stiffness shifts its best level thirty times as far as the wind's shape does.
The ends the ground was holding down
Winkler's springs pull as readily as they push, and on a long footing strip the linear answer quietly uses that: it has the ground holding the strip's ends down. Take the pull away and the correction under the column is modest — eight or nine per cent on the pressure and the moment — but the shape of the answer changes completely. A weightless strip longer than about eight metres keeps exactly eight metres of itself on the ground, whatever length was poured, and the rest rises off as straight cantilevers carrying nothing. The middle-third rule turns out to be a property of rigid footings: an eight-metre strip lifts at a fiftieth of the eccentricity the kern allows.
The camber that lowers the hook
A camber is built into a girder so that it ends up level in the finished structure, and nothing about it matters until then — except on the day it is lifted. A cambered girder hanging from its ends is a shallow arch, its centre of gravity two-thirds of the camber above the line through its lifting points, and it rolls about that line as though its hook were that much lower. On a long precast girder already close to its lifting limit, a hundred millimetres of camber takes the factor of safety against roll from 2.3 to 1.4. The camber grows while the girder waits in the yard, so the same girder becomes harder to lift every week it is stored. Pick it a fifth of its length in from each end and the camber drops out of the problem altogether.
The tank that sloshes the tower
On the ground a tank's liquid splits into a part that moves with the wall and a part that sloshes at its own long period, and the two answers can be added afterwards because they are orders apart. Lift the tank onto a tower and the tower's period moves up towards the sloshing period, the two masses stop being separate, and the system has two modes that belong to neither. Adding the ground answers then overstates the base shear by a third, treating the water as solid by as much again, the wave grows by half, and a flexible tower is worst with the tank about five-sixths full.
The roof that ponds on its girders
A flat roof's joists sit on girders, and the water fills the sum of both their sags. Two members each half-way to ponding on their own are unstable together, and long before that the growth of the water is far larger than either member's own amplification says. AISC's simplified rule turns out to be a line of constant growth, and a member sized to a deflection limit has a ponding parameter proportional to its span — so a bay sized to L/240 under 1.5 kN/m² meets the rule up to 6 m, doubles its water at 12 and ponds at 24.5.
The building the trough cannot bend
A tunnel leaves a settlement trough, and damage criteria are applied to the trough's deflection ratio over the length of each building above it. But a building is not the ground: it has a bending stiffness, and it takes only as much of the ground's curvature as that stiffness lets it. One number decides how much — the building's stiffness over the soil's modulus times its length to the fourth — and over two decades of it a building goes from following the trough to bridging it. Because the length enters to the fourth power, the same building is stiff when short and soft when long.
The reaction moves one per cent and the moment five
Over the support of a wide-flanged continuous girder the flange works over a third of its width, so the girder there should be softer and shed moment into its spans. It does — but it is the reaction that the softness changes, by less than one per cent, and the support moment, a small difference of two large ones, moves by five. The stress spike over the support follows the reaction rather than the moment and eases by two. A prismatic analysis is right about the moments to a few per cent, and the spike stays a problem of the section.
The jacks the arch forgets
Jack a fixed concrete arch's abutments apart before the crown is closed, by exactly the gap its thrust and its footings open on the day, and the springings start with no moment at all. A century later they carry 173 kN·m — half as much again as the 112 the jacks were set to remove. The thrust's own moment never relaxes; the jacks' correction does, as the rib creeps; and shrinkage and the ground's consolidation arrive after the jacks have gone. No single setting cancels movements that run on different clocks.
The frames the deck pushes first
A half-through girder's U-frames are the ends of the cross-girders that carry its deck. Load the deck and every cross-girder sags, its ends rotate, and every frame's foot swings inward by millimetres before the compression chord has asked the frames for anything. It looks like a second imperfection on top of the chord's bow. It is a much weaker one: the frames all move together and the chord simply goes with them, so a 7.5 mm push adds 1.4 kN to frames that the bow loads with 13.6, and stiffer frames make it smaller, not larger. What the push leaves is mostly in the frames' own members, not in what they ask of the chord.
The arm connected late
An outrigger is often left unconnected until a concrete building is finished, so that the columns and the core can shorten by their different amounts without it. Most of their difference has not happened yet. Three-quarters of fifty years' differential shortening arrives after the frame tops out, and an arm connected then ends up carrying 3.5 MN of it — 60 per cent of what the design wind puts into the same arm, permanently, and in the same direction on both sides of the core. The connection date is the largest load the arm has, and a stiffer arm collects it faster than it collects the wind.
The building the trough twists
A building that crosses a tunnel's settlement trough at an angle stands on ground that is warped as well as sagged. Its four corners do not settle into a plane, and beyond about twenty degrees of skew the warp is larger than the sag. Whether the building follows that warp or resists it depends on a property its bending never needed — whether its walls and floors close into a tube — and the same walls, closed or open, differ a thousandfold in their stiffness against it.
The roof that drains towards its sag
The depth of water a ponding check takes as given is set by the drainage: an overflow's height above the roof, plus the head a storm needs to leave through it. Which head a roof can carry depends less on how stiff it is than on where the overflow sits. With the level fixed by a scupper in the parapet, a 12 by 9 m bay allows 85 mm of water and an 18 m square bay 39. With a drain at the middle of the bay, whose inlet goes down as the roof sags, the same bays allow 182 and 205 mm — more than a rigid roof would — because the water's surface follows the sag down instead of filling it.
The footing the storms press down
A footing strip under a column that a storm rocks one way and then the other was expected to dig itself a bowl: its ends loaded half the time, compacted, and left hanging over the hollow. On ground that unloads and reloads four times as stiffly as it first loads, the bowl appears and the strip fills it. The column settles 26% more over three storms and then stops; the footing rocks 22% less than it did in its first storm and is 64% stiffer than on springs that forget, because rocking unloads half the strip and ground that has carried the column unloads stiffly. The storms change the settlement and the stiffness, and leave the moments almost where they were.