Theme

One support too many — page 7

Essays 145 to 168 of 206 on this thread, in the same order.
A bigger top column attracts more moment, and only the joint stops it. The top storey of the edge column of a braced six-storey frame — 4 m storeys, a 254 UC 89 below the splice and a 203 UC 60 above — carrying a 9 m beam at every floor on partial-strength joints of 261 kN·m, with each of seven columns that might be chosen for it: the moment its floor's edge joint delivers at the design load of 60 kN/m (dark) and at the beams' collapse load (light), against what the column can carry at its top end, its plastic moment reduced for the axial force (line). 203×203 UC 46: 148 and 195 against 167; 203×203 UC 60: 171 and 225 against 230; 203×203 UC 71: 189 and 247 against 283; 203×203 UC 86: 205 and 261 against 347; 254×254 UC 73: 218 and 261 against 352; 254×254 UC 89: 232 and 261 against 435; 254×254 UC 107: 243 and 261 against 527. A stiffer column attracts more of the joint's moment until the joint's 261 kN·m caps it; the lightest column that carries what it attracts at collapse is the 203 × 203 UC 60. Connections

The column on the other side of the joint

A partial-strength joint is sold as a fuse: it caps the moment a beam can put into its support at the joint's own resistance. At an interior column that is true. At the edge of a frame the column is not a support that stays still; it is a spring in series with the joint, so the joint delivers less than its resistance in service and almost exactly what a rigid joint would. The column then carries three times the moment the simple-construction rule gave it, and at the top storey, where it stands alone and is lightest, it is weaker than the joint it was meant to be protected by.

A secondary holds more than it twists once its connection passes a few tens of kilonewton-metres per radian. The mid-span twist of the 8 m primary beam of 12 kN/m at 75 mm off its shear centre, with a 6 m 356 × 171 × 51 UB framing in at mid-span whose 60 kN reaction acts 60 mm off the shear centre, against the rotational stiffness of the secondary's connection on a logarithmic scale, in series with the secondary's own 3EI/L of 14,453 kN·m/rad. Dashed, the 6.25° with no secondary. On the deck's side the secondary is worse than none below 33 kN·m/rad and better above it: 9.12° at 10, 3.28 at 100, 0.47 at 1,000. On the far side its torque opposes the deck's (0.89° at 10); as a pair, the torques cancel (1.05° at 100). EN 1993-1-8 calls this secondary's connection nominally pinned below 2,409 kN·m/rad (dotted). Deflection

The secondary beam that twists what it holds

A secondary beam framing into a twisting primary at mid-span is the best restraint a primary can have — concentrated exactly where the twist is. It is also a load: its reaction arrives on the primary's web, off the shear centre, as a torque at exactly the same place. Which wins is decided by the connection, and the threshold is low: a fin plate stiffer than about 33 kN·m per radian, a seventieth of what still counts as a pin, makes the secondary hold far more than it twists. The bolts' free play is another matter, because the torque acts from the first millimetre and the restraint only once the play is taken up.

The arm goes in almost the same place whatever shape the wind is. The share of the tip drift removed by one outrigger on a 200 m core of bending stiffness 1.2 × 10¹⁰ kN·m² carrying 6,000 kN of wind in all, with an outrigger of 1.0 × 10⁸ kN·m per radian, against the outrigger's level as a share of the height, for the three profiles of the same total wind. uniform: best at 0.745 of the height, removing 45.6 per cent; power law: best at 0.749 of the height, removing 45.9 per cent; triangle: best at 0.757 of the height, removing 46.4 per cent. The curves lie almost on one another: the triangle, with three quarters of its load in the upper half against the uniform wind's half, moves the best level up by 1.2 per cent of the height. Structural form

The arm that ignores the shape of the wind

The outrigger arithmetic is usually done for a wind that is the same at every height, and real wind is not: it grows with height, and an earthquake's first mode loads a building as a triangle. The natural guess is that a load concentrated towards the top moves the best place for the arm. It barely does. Put the same total wind on a 200 m core as a uniform load, a power-law wind and a triangle, and the best level moves by just over one per cent of the height. What moves is the force in the arm — half as much again under the triangle — and how far the top goes, while the arm's own stiffness shifts its best level thirty times as far as the wind's shape does.

Below its ceiling, a row of braces is only its total. The critical moment of a beam 24 m long whose unbraced critical moment in uniform bending is 837 kN·m, held by one, two, three or five torsional braces equally spaced along it, against the braces' total rotational stiffness. At 4,336 kN·m/rad in all, the rows of two, three and five give 3,815, 3,726, 3,578 kN·m: how the stiffness is divided hardly matters, while one has already stopped. Each row then stops at its own ceiling, where the braces are stiff enough to be nodes and the beam buckles between them in one more half-wave than it has braces: 2,637 kN·m for one, 5,585 kN·m for two, 9,704 kN·m for three, 21,466 kN·m for five. The dashed line is 5,627 kN·m, the moment the beam is asked to carry; one and two cannot reach it however stiff they are. Stability

The stiffness a row of braces shares out

One torsional brace at midspan has a ceiling, the moment at which the beam gives up twisting it and buckles in two half-waves instead. A row of braces raises the ceiling with every brace added, and the stiffness each must have to reach its ceiling rises with the count — seventy-four times as much for eight braces as for one. That is the right answer to the wrong question. Asked for the moment the beam has to carry rather than for its ceiling, a row of braces needs very nearly the same total stiffness however many it is divided between, so each brace gets softer as the count goes up. The count has one job, which is to put the ceiling above the moment; the stiffness has the other.

A hanger that would push is a hanger that is not there. The force in each hanger of a tied arch of 100 m span and 17 m rise on 32 crossed hangers, carrying 60 kN/m of dead load over the span and 120 kN/m of live load over its left half, against the hanger's position along the tie. Solved as though every hanger could push (pale bars), 4 come out in compression, the worst at 185 kN. Solved with those hangers taken out until no remaining one is compressed (dark bars), 8 are slack — more than the linear solution has in compression, because each hanger that goes passes its share to its neighbours and some of them follow. Structural form

The deck that keeps the hangers in the truss

Crossing the hangers of a tied arch turns it from a frame that bends into a truss that does not, as long as every hanger is pulling. A hanger cannot push, and under a load on half the span some of them would have to. Solved as it really is — with those hangers taken out, and the ones that follow them — the arch keeps the linear answer exactly until the live load on half its span is about equal to its own dead weight, and past that the tie's moment doubles and then quadruples. The arch's own weight is the pretension nobody had to apply, and a heavier deck is a stiffer network.

The arch is only as strong as what holds its ends. Load against mid-span deflection, as a share of the thickness, for a slab strip 4,000 mm long and 200 mm thick, a metre wide, with its ends held by springs of 0.05, 0.5 and 5 times its own axial stiffness EA/L and rigidly; dashed is its flexural load, 30.0 kN/m. At 0.05 EA/L it peaks at 45.3 kN/m, 1.51 times the flexural load, at 0.67 of its thickness; at 0.50 EA/L it peaks at 74.8 kN/m, 2.49 times the flexural load, at 0.45 of its thickness; at 5.00 EA/L it peaks at 108.6 kN/m, 3.62 times the flexural load, at 0.28 of its thickness; held rigidly it peaks at 116.8 kN/m, 3.89 times the flexural load, at 0.24 of its thickness. A soft restraint lets the ends move out as the strip tries to arch, so the thrust builds slowly and the peak arrives later and lower. Internal forces

The edge that cannot hold the arch

A slab strip whose ends cannot move apart arches inside its own depth and carries nearly four times its flexural load. "Cannot move apart" is a stiffness, not a fact, and the arch needs a lot of it: half the gain takes end springs about half as stiff as the strip itself in compression, and nine tenths takes springs five times as stiff. An interior panel is held by the floor around it and gets the arch. An edge panel is held on its outer side by whatever runs along the edge, and a band of slab two metres wide between columns eight metres apart supplies a twentieth of what the strip needs. The arch is a property of where the panel is.

Hung from its deck, the rib's bending is not amplified at all. The bending moment along a 60 m parabolic rib at a 12 m rise (EI 250,000 kN·m²) under 25 kN/m of dead load and 10 kN/m of live load on the left half. Standing free on pinned springings (solid) it peaks at 1,303 kN·m, against 576 at first order (dashed): the thrust amplifies the half-span bending 2.26 times. The same rib hung over a deck 0.10 times as stiff as the rib on vertical hangers (thick) peaks at 524 kN·m, 0.99 times its first-order 528, and the deck (thin) carries 59. The deck closes the thrust in tension, and the tension it carries straightens the deck as much as the thrust bends the rib. Stability

The rib that cannot lean on its own tie

A free arch rib under a half-span live load bends in the shape of its own buckling mode, and its thrust amplifies the bending more than twofold. Hang a deck from the same rib on vertical hangers and close the thrust in the deck, and the amplification disappears: the thrust and the tie's pull move together, so the couple they make keeps its lever arm, and the only second-order term left is the small difference between the rib's deflection and the deck's. The critical load rises sixteenfold, and the deck's share of the bending is simply its share of the stiffness.

In a V-shaped canyon the rings carry the water, and the top rings more than theirs. The water pressure down the crown of a dam 100 m high in a V-shaped canyon 200 m wide at the crest, 5 m thick at the crest and 25 m at the base, with its rings at 133.6° (dashed), divided between the horizontal ring at each depth (solid) and the vertical cantilever at the crown (thin) so that the two deflect alike. At 4 m below the crest the ring carries 195% of the water there — the cantilever, loaded from below and free at the top, leans on it; at 49 m the cantilever carries 11%; at 89 m, 6%. Over the whole reservoir the cantilever carries 10% of the water and the rings the rest. Equilibrium

The water the valley floor takes

An arch dam is not a stack of rings. At its crown it is also a vertical cantilever fixed into the valley floor, and the water at each depth is shared between the ring there and the cantilever in whatever proportion makes them bend alike. In a V-shaped canyon the short lower rings are stiff and carry nearly everything, and the top rings carry up to twice their own water because the cantilever leans on them. In a U-shaped canyon the cantilever takes half the reservoir and bends the heel into tension that the ring formula never sees.

A stiff building bridges the trough it stands in. The settlement of a building 30 m long centred on the trough, over a trough 30 mm deep whose inflection points are 15 m from its centre (dashed: the ground with no building), measured from the building's settlement under its own weight, for relative stiffnesses EI/(kₛ·B⁴) of 10⁻⁴, 10⁻³ and 10⁻². At 10⁻⁴ its deflection ratio is 95% of the ground's; at 10⁻³ its deflection ratio is 66% of the ground's; at 10⁻² its deflection ratio is 17% of the ground's. The stiff building settles almost as a rigid body and leaves the trough's curvature to the ground beneath it. Deflection

The building the trough cannot bend

A tunnel leaves a settlement trough, and damage criteria are applied to the trough's deflection ratio over the length of each building above it. But a building is not the ground: it has a bending stiffness, and it takes only as much of the ground's curvature as that stiffness lets it. One number decides how much — the building's stiffness over the soil's modulus times its length to the fourth — and over two decades of it a building goes from following the trough to bridging it. Because the length enters to the fourth power, the same building is stiff when short and soft when long.

The loads a portal can carry for ever. For a fixed-base portal 10 m wide and 5 m high, plastic moment 200 kNm in the columns and 200 in the beam, in the plane of the gravity load's peak V·L/Mp — the load comes and goes — and the wind's H·h/Mp — it reverses: the first-yield boundary (dotted), the shakedown boundary (solid), and the collapse boundary under the same two loads applied once (dashed). With little wind the shakedown boundary is the beam's own mechanism, which the wind does no work in, falling from 8 to 6.0 as the wind grows to H·h/Mp = 2.7; beyond that it is alternating plasticity at a column base, nearly level. The dot is 160 kN of gravity with 60 kN of wind and the ring its shakedown point, a factor of 0.88: the gravity load alone is at the beam's collapse load, and the wind takes 12% off what the pair can carry without doing any work in the beam's mechanism. Materials

The beam the wind walks without pushing

A fixed-base portal whose beam carries exactly its collapse load is safe under that load applied once. Add a wind that comes from either side — a wind that does no work at all in the beam's collapse mechanism — and the beam can no longer carry the load for ever: 12 per cent comes off, and above that the midspan gains fifteen milliradians every cycle while the frame does not sway. Each knee takes its worst moment from a different wind, and the beam assembles a mechanism no single storm drives.

A girder softer to short waves sheds a little of its support moment. For two continuous 20 m spans of a girder whose flanges are 6.0 m wide and 30 mm thick, 1.20 m apart on 24 mm of web — the flanges 97% of its stiffness — under a uniform load, each interior support 1.0 m long: the bending moment along the girder per unit load, sagging up — for a prismatic girder (dashed), which is what a global analysis gives with one effective width per span, and for the girder whose every wave of moment bends it with that wave's own effective flange (solid). The interior reaction falls by 0.88%, and because the support moment is the difference of two much larger moments, that becomes 4.6% of the support moment, 47.0 to 44.8; the sagging peak rises by 2.9%, 28.1 to 28.9. Sections and stress

The reaction moves one per cent and the moment five

Over the support of a wide-flanged continuous girder the flange works over a third of its width, so the girder there should be softer and shed moment into its spans. It does — but it is the reaction that the softness changes, by less than one per cent, and the support moment, a small difference of two large ones, moves by five. The stress spike over the support follows the reaction rather than the moment and eases by two. A prismatic analysis is right about the moments to a few per cent, and the spike stays a problem of the section.

The gaps that open after the arch is closed. For the 60 m fixed concrete rib rising 6 m under 60 kN/m, closed at 28 days with its abutments jacked apart to take up the day's gap: the gap between the rib and its springings that each movement opens after closure, in millimetres, against the years since, on a log scale — the rib's creep under its thrust, its shrinkage, and the ground consolidating under the thrust by 1.0 times its 8 mm immediate spread with 90% done at 10 years. After a hundred years they are 24.8, 16.2 and 8.0 mm, 48.9 in all, against the 13.6 mm the thrust shortened the rib on the day. The rib resists them while it creeps itself, so the gap it acts as if fixed against is 20.9 mm (fine dashes). Deflection

The jacks the arch forgets

Jack a fixed concrete arch's abutments apart before the crown is closed, by exactly the gap its thrust and its footings open on the day, and the springings start with no moment at all. A century later they carry 173 kN·m — half as much again as the 112 the jacks were set to remove. The thrust's own moment never relaxes; the jacks' correction does, as the rib creeps; and shrinkage and the ground's consolidation arrive after the jacks have gone. No single setting cancels movements that run on different clocks.

Heave puts the pile in tension where settlement put it in compression. For a 24 m pile 600 mm across carrying 200 kN, in clay whose top 18 m moves, by 100 mm at the surface: the axial force down the pile, compression positive, when the ground heaves (solid) and when it settles as far (dashed). Settling, the pile's compression peaks at 910 kN at 17.2 m and its toe carries 324 kN. Heaving, it is in tension below 8.9 m, peaking at 520 kN at 17.3 m, and its toe carries nothing: lifted, it parts from the soil beneath, so everything holding the pile down comes from the shaft below the plane. Internal forces

The pile the ground pulls apart

Clay that swells after its trees are felled rises past the piles in it, and the same compatibility that put a pile into compression in settling ground puts it into tension in heaving ground, at nearly the same depth. Nearly everything else changes. A lifted toe parts from the soil and holds nothing, so the shaft alone anchors the pile; the head load that added to the downdrag now subtracts from the tension; and the tension peaks 17 metres down, far below the short cage a lightly loaded pile is given. A house's piles in swelling clay are tension members nobody reinforced.

A building that crosses the trough at an angle stands on a warped surface. Plan of a 30 × 12 m building 10 m high, its walls 300 mm thick, over a trough 30 mm deep with its inflection 15 m from the tunnel's axis, its long axis 45° from square across the tunnel. The lines are the greenfield trough's settlement contours, 5, 10, 15, 20, 25 mm, parallel to the tunnel's axis (dashed). The corners settle A 27.4, B 18.4, C 27.4, D 18.4 mm, so they do not lie in a plane: A and C together settle 18.1 mm more than B and D. A building spanning square across the trough has no such warp, and one lying along it has none either; between the two, the trough twists the building as well as bending it. Deflection

The building the trough twists

A building that crosses a tunnel's settlement trough at an angle stands on ground that is warped as well as sagged. Its four corners do not settle into a plane, and beyond about twenty degrees of skew the warp is larger than the sag. Whether the building follows that warp or resists it depends on a property its bending never needed — whether its walls and floors close into a tube — and the same walls, closed or open, differ a thousandfold in their stiffness against it.

Three braces do more where the moment is. The 24 m plate girder, its minor-axis second moment 2.67 × 10⁸ mm⁴ and its warping constant 1.00 × 10¹⁴ mm⁶, under a uniform load, held by three torsional braces asked to bring its peak moment to 5,627 kN·m: above, the moment diagram; below it, the twist of the buckled girder with the braces equally spaced, 6.0 m apart, and clustered 4.0 m either side of midspan, each at the stiffness that just reaches the moment. Equally spaced the row needs 8,537 kN·m/rad in all; clustered, 6,325, 26 per cent less. The clustered braces sit where the girder twists most, and the bays they leave at the ends carry little moment. Stability

Three braces where the moment is

A row of torsional braces is spaced equally because that is how it is drawn, and under a uniform moment equal spacing is very nearly the best there is. Under a moment that peaks at midspan it is not. Moving the outer two of three braces toward the middle cuts the total stiffness a 24 m girder needs by a quarter under a uniform load and a third under a point load, and the bays it leaves at the ends cost nothing, because they carry so little of the moment.

A load between the posts racks the panel it stands in. Elevation of a Vierendeel girder of six 2 m panels, 1.5 m deep, its deck chord as stiff as its other chord and its posts, the load standing in the middle of its second panel; the racked shape exaggerated, the unloaded girder faint. The panel the load stands in carries most of its shear, and the deck chord there bends both as a Vierendeel chord and as a beam between its posts: 38 kN·m against 27 with the load at mid-span. The posts either side carry 56 and 11 kN·m, and the heaviest post 56. Structural form

The load that visits every panel

A Vierendeel girder checked for a load at mid-span is checked for one position of a load that, on a bridge, stands everywhere in turn. Crossing it, a 100 kN load puts 1.7 times the mid-span check's moment into the end panels' chords, loads the middle post that a central load leaves idle, and makes the deck chord a beam between its posts in every panel where its share of the shear is small. Equal chords stay the stiffest arrangement; a vehicle whose axles span a panel cannot stand in the middle of one.

Braces that cannot move can still be made stiffer where the moment is. The 24 m plate girder, its minor-axis second moment 2.67 × 10⁸ mm⁴ and its warping constant 1.00 × 10¹⁴ mm⁶, under a uniform load, held by braces at midspan and 6.0 m either side and asked to bring its peak moment to 5,627 kN·m: above, the moment diagram; below it, the twist of the buckled girder with the three braces equally stiff and with the middle one given 61 per cent of the row's stiffness, each row at the total that just reaches the moment; the ticks are drawn thicker for a stiffer brace. Equal, the row needs 8,537 kN·m/rad, 2,846 in each brace; graded, 7,067, 4,280 at midspan and 1,394 at each side, 17 per cent less. Stability

The braces that stay where the framing puts them

Three cross-frames on a girder usually go where the floor beams or the bridge's bays put them, and cannot be moved toward the moment. They can still be made unequal. Giving the middle one three-fifths of the row's stiffness saves a sixth of the total under a uniform load and more than a quarter under a point load — most of what moving them would save. Moved and graded together, they save no more than moved alone, because both are ways of making every brace twist by the same amount.

A stiff floor shares by stiffness, a soft one by distance. The share of a brace line's force that reaches its soft bay, against the other bay's stiffness over the soft bay's on a logarithmic scale, for a 48 by 24 m floor carrying 40 kN per metre of span, each brace line 960 kN, with a 6 m braced bay of 200 kN/mm at one end of each line and a 6 m bay 10 times as stiff — for three floors (dashed: a rigid floor, which shares by stiffness, and the tributary half). With the other bay ten times as stiff the rigid floor gives the soft bay 9%; the concrete slab 16%, the cracked slab 30% and the steel deck 37%. Structural form

The floor that feeds two bays

A brace line with a braced frame at one end and a core wall ten times as stiff at the other is analysed one of two ways. As a rigid floor, which shares the line's force between the bays by their stiffness and gives the frame 9%. Or as a flexible floor, which gives each bay the half of the line nearest it, 50%. Solved as a membrane, an uncracked concrete slab gives the frame 16%, the same slab cracked 30%, and a steel deck 37%. The floor does not send its shear to the nearer bay; a stiff floor sends it to the stiffer one. The frame's design force depends on which state the floor is in when the storey force arrives, by more than a factor of two.

The shear term cuts the beam's stiffness, not its share. For 20 storeys of two 6.0 m walls 0.35 m thick either side of a 2.4 m opening, coupling beams 0.35 m wide, 60 kN at every floor, against the coupling beams' depth: each beam's stiffness with its shear deformation counted over its stiffness in bending alone, the degree of coupling likewise, and the largest beam's shear likewise. At a depth of 0.6 m (span over depth 4.0) the stiffness is 0.85 of the bending figure, the coupling 0.977 and the shear 0.961; at 2 m (1.2), 0.33, 0.973 and 0.937. Where the shear term is large the beam is stiff enough that its stiffness has stopped deciding anything. Deflection

The coupling beam asked for shear

The coupling beams of a pair of shear walls are the stubbiest members in a building, and the shear term in their deflection is largest exactly there: a beam two metres deep over a 2.4 m opening is a third as stiff as bending alone says. The walls hardly notice. The pair's degree of coupling moves by under 3%, the beams' shears by under 7%, because a beam that stiff has stopped deciding how much of the overturning the walls carry as a couple. What decides it is the shear the beams can give. A 600 mm beam limited to 2 N/mm² starts to yield at 1.9 times the storey force; past the last yield the pair is two cantilevers again, and the beams supply rotation instead.

Stressed bay by bay, the beam keeps half its secondary moment. The secondary moment along a 4-span beam of 16 + 16 + 16 + 16 m prestressed with 2,400 kN on a parabolic tendon, straight between supports: stressed in one operation, stressed one bay at a time, and bay by bay after creep with a coefficient of 2.0. At the first interior support it is 350 kN·m stressed at once, 164 bay by bay and 307 after creep; at the next, 234, 160 and 216. Internal forces

The beam stressed one bay at a time

A long continuous beam is rarely stressed in one pull. It is cast and stressed a bay at a time, each new length of tendon coupled to the last, and at every stage the structure is a different beam. The secondary moments the finished beam carries are the sum of what each stage did to the beam that existed then — about half of what the one-stage analysis gives — and creep spends the following years taking most of the other half back.

Pinned bases: weaker, and nothing lost to repetition while gravity leads. For a portal 10 m wide and 5 m high, plastic moment 200 kNm in the columns and 200 in the beam, in the plane of the gravity load's peak V·L/Mp and the reversing wind's H·h/Mp: the shakedown boundary (solid) and the collapse boundary under the loads applied once (dashed), on fixed bases and on pinned ones. On pinned bases the two coincide wherever gravity leads, along the beam and combined mechanisms, until the wind reaches about H·h/Mp = 1.6; past that a knee alternates and shakedown falls inside collapse, meeting it again at H·h/Mp = 2 with the wind alone. On fixed bases collapse reaches 8 and 4 and shakedown sits inside it except where the beam's mechanism meets the gravity axis. The dot is 160 kN of gravity at midspan that comes and goes with 60 kN of wind that reverses: its shakedown factor is 0.88 on fixed bases and 0.73 on pinned ones, where it is also the collapse factor. Materials

The base that sends the wind to the knees

A fixed-base portal loses 12 per cent of its load to a wind that reverses, because each knee takes its worst moment from a different storm. Pin the bases and the loss disappears — not because the pinned frame is better, but because its collapse load already contains it. What the bases decide is where the moment goes, and a base that is merely weaker than its column can cost nothing at all, or be made into the part that yields every storm so that nothing else does.

A hat makes the top storeys look stiff. Each storey's own sway factor α up the height of a 20-storey building of a core to the roof and a racking frame (αH 1.0), its gravity scaled to an elastic critical factor of 5.0, under an equal lateral load at every floor: with no hat, with a hat truss at the roof holding the core's rotation with 10 times the core's EI/H, and with the same restraint at storey 10; the building's critical factor 5.0 as a vertical line. With no hat the top storeys read the least, 4.06 at the roof. With the hat the roof storey reads 15.47 and the least, 4.14, has moved down to storey 9. With the outrigger at mid-height the least is back at the top, 3.85. Stability

The hat that hides the lean

A hat truss on a core-and-frame building holds the top of the core, nearly doubles the building's critical load, and makes its top storeys look three or four times as stiff as they did. The storey check believes them. Under the hat the roof storey reads a sway factor of 15 and estimates 7 per cent of second-order drift; the building still buckles leaning, and the roof storey's true increase is 24 per cent. The hat turns the storey check from pessimistic to unsafe at exactly the storeys it was built to stiffen.

The single side's strongest direction is not the double side's. The resultant a millimetre of throat can carry in S355 against the direction of the load: a double-sided butt throat, a fillet throat, and a 20 mm plate's single-sided throat at penetrations of 0.5 and 0.7, counted plastically. The double-sided butt is strongest at 22.7°, 478 N/mm². The single side at 0.5 rises from 183 straight across to 314 straight along and is strongest along the weld; at 0.7 it rises from 291 to 357 at 40° and falls to 314, and from 38° to 88° it carries more than the fillet. Connections

The root that has to stretch for it

A partial-penetration weld made from one side carries its pull off the plates' line, and counted elastically it keeps a quarter of a double-sided weld at half penetration. Let the throat yield and it keeps 0.41 — but the same 0.41 at every direction up to the one where the double-sided weld is strongest, so that weld's peak advantage is never won back. What the yielding does instead is move the single side's own strongest direction out to 40° or beyond, where a deep single-sided throat outcarries a fillet. Every per cent of it is paid for with strain at the root, which is the tip of an unfused land.

What it costs depends on the load it must still carry. The steel in an eight-panel Pratt truss with a counter-diagonal in each interior panel, loaded by 10 at every bottom joint, sized to survive the loss of any one interior diagonal, against the share of the full load it must carry with the diagonal gone; the intact fully stressed design's 1,200 and the Pratt truss's 1,220 as level lines. At a third of the full load the robust truss needs 1,221, at a half 1,252, at two thirds 1,304, at the full load 1,555, and at four thirds — two thirds with the loss counted as sudden, doubled — 2,074. From about a half the interior diagonals grow in proportion to the load, each sized by its partner's loss; past the full load the chords grow too, because the damaged truss is then carrying more than the intact one was sized for. Deflection

The truss sized to lose a diagonal

A Pratt truss with a counter-diagonal in every interior panel, sized fully stressed, starves its middle counters to nothing and saves a little steel over the plain Pratt. Ask it to survive the loss of any one diagonal at the accidental two thirds of its load and the family of equal designs collapses to one: every counter comes back, sized by its partner's loss, and the truss needs 1,304 units of steel against 1,200 — 9 per cent for an alternative path the Pratt cannot have at any price. A lost chord can be survived too, by the panel's diagonals turned into a chord, for twice the steel. Four members in the end triangles cannot be survived at all.

All themes