Every prop has its own worst day
A braced excavation has no finished state worth analysing. It is dug in stages, a level of props goes in at each stage, and a prop's force is largely fixed the moment it is installed — so the force to design it for is the largest it sees during a sequence that appears on no calculation sheet, and which for the middle prop here is nearly two and a half times what the finished arrangement gives.