Differential settlement — the series
-
The settlement that matters is the difference
A building that goes down half a metre uniformly is undamaged and needs a new front step. One that goes down a twentieth as far, unevenly, has cracked. The superstructure can even the difference out — and the only way it can do so is by carrying the difference itself, as a force.
-
The crack is a strain, not a slope
Angular distortion is what every table of settlement limits is written in, and it is a proxy. What cracks a building is a tensile strain in it, and reading the building as a deep beam says which of two mechanisms supplies it, why hogging is exactly twice as damaging as sagging, and why a horizontal stretch of a few millimetres takes half the capacity away before the settlement starts.
-
The building the trough cannot bend
A tunnel leaves a settlement trough, and damage criteria are applied to the trough's deflection ratio over the length of each building above it. But a building is not the ground: it has a bending stiffness, and it takes only as much of the ground's curvature as that stiffness lets it. One number decides how much — the building's stiffness over the soil's modulus times its length to the fourth — and over two decades of it a building goes from following the trough to bridging it. Because the length enters to the fourth power, the same building is stiff when short and soft when long.
-
The building the trough twists
A building that crosses a tunnel's settlement trough at an angle stands on ground that is warped as well as sagged. Its four corners do not settle into a plane, and beyond about twenty degrees of skew the warp is larger than the sag. Whether the building follows that warp or resists it depends on a property its bending never needed — whether its walls and floors close into a tube — and the same walls, closed or open, differ a thousandfold in their stiffness against it.