Generator

Cambered against the wet load

Rendered here at the parameters it defaults to, with every essay that calls it — which is the same list as the blast radius of changing it.
Cambered against the wet load. A 12 m composite beam whose flexural rigidity rises from 94 to 260 kN·m² when the slab sets, so the first two loads are carried by the bare steel and the rest by the composite section. Fabricated with 25.3 mm of camber, it moves through -20.7, 0.0, 7.5, 12.7 mm as the four stages arrive — 0.0 mm on the day the slab is poured, and 12.7 mm at the end, which is one part in 947 of the span. The largest curvature it ever has is 25.3 mm of hog, and it has that with nothing on it. Every shape is drawn at the same exaggeration and the drawing is a diagram of a proportion: the vertical scale is 119484 times the horizontal.

Cambered against the wet load. A 12 m composite beam whose flexural rigidity rises from 94 to 260 kN·m² when the slab sets, so the first two loads are carried by the bare steel and the rest by the composite section. Fabricated with 25.3 mm of camber, it moves through -20.7, 0.0, 7.5, 12.7 mm as the four stages arrive — 0.0 mm on the day the slab is poured, and 12.7 mm at the end, which is one part in 947 of the span. The largest curvature it ever has is 25.3 mm of hog, and it has that with nothing on it. Every shape is drawn at the same exaggeration and the drawing is a diagram of a proportion: the vertical scale is 119484 times the horizontal.

5 essays call camber-stages. The drawing above is what it returns with no arguments at all; every call below passes it something, because a placement that passes nothing draws whichever member of the family the generator happens to default to rather than the one its essay argues about.

Where it is called

Changing this generator changes every one of these figures.

Four camber rules, and what each leaves on the finished beam. The same 12 m composite beam, cambered against four different things, followed through its own load history. Positive is a sag and negative a hog, and the point at the left of each line is the shape it was fabricated to. Cambering against the wet concrete leaves 12.7 mm of sag at the end and a flat beam on the day the slab is poured; cambering against the total load leaves the beam dead flat when fully loaded and hogged 37.9 mm — one part in 316 of the span — before anything is on it at all. Deflection

Built to the wrong shape on purpose

A cambered beam is fabricated curved upward so that load bends it down to something like straight. Nothing in the analysis changes, no stress anywhere is altered, and almost every mistake made with it is a bookkeeping mistake about which loads count.

The props decide where the stress ends up. Bottom-fibre stress in the steel of a 12 m composite beam carrying 6 kN/m of wet concrete and 9 kN/m afterwards. Unpropped, the bare steel takes the first stage alone and reaches 146 MPa; propped, the finished composite section takes everything and reaches 93 MPa — a ratio of 1.57. 62% of the unpropped beam's final stress was locked in before the slab was structural at all. The deflections differ by 1.73 times for the same reason, and no drawing of the finished beam distinguishes the two. Sections and stress

The section that changed while it was being loaded

A stress is computed from a moment and a section modulus. When part of the moment arrived while the section was a different shape, there is no single section modulus to divide by — the stresses add and the properties do not, and two identical finished beams can differ by half again in stress with nothing on the drawing to say which is which.

The gap is a sum of five things and only one of them is computed. What a 30 mm movement joint is asked to accommodate, by three combination rules. The top bar is every term at its extreme, added: 33.2 mm, which assumes the hottest day, the fullest floor, the whole of the shrinkage and the worst-placed wall arrive together. The chance of that is about 1.5%. The bottom bar treats them as independent and asks for 16.0 mm. The middle bar is the rule used for actions and almost never for movements — one term at its full value and the rest at their coincidence factors — and gives 25.5 mm. The segments across the top bar are the terms themselves, and the ordering is the finding: the largest is tolerance at 10.0 mm, which is not a structural quantity at all, and the smallest is deflection at 3.2 mm — the only one anybody computes carefully, and 10% of the total. Deflection

The gap nobody computed

A movement joint is sized by adding up everything the structure will do to it, and the deflection calculation — the only term anybody computes carefully — is usually the smallest one in the list. The largest is a construction tolerance, which is not a structural quantity at all, and the sum of the extremes is nearly twice what treating them as independent would ask for.

The check that depends on a date. Total deflection and the deflection occurring after the brittle finishes are built, for one 12 m beam, against the day those finishes go up. The total barely moves — the beam ends up where it ends up. The increment falls from 32 mm at a week to 14 mm at a year, because creep is fast at first and slow later and a partition built early inherits nearly all of it: 44% of the final creep has already happened by day 28. The span/500 limit is 24 mm and the span/250 limit is 48; this beam passes the first only after day 25. Camber subtracts from both terms of the difference and therefore changes the upper curve and not the lower one, which is the reason a cambered beam can satisfy every total-deflection check and still crack the wall. Deflection

The limit that depends on a date

Total deflection can nearly always be met, and on a long span it is met with camber. The limit that actually decides the member is the other one — the deflection occurring after the brittle finishes are built — and camber does nothing for it whatever, because it is subtracted from both terms of a difference. The same beam passes or fails on the day the partitions went up.

A weld is a force, and it is applied where the weld is. The bow a welded girder leaves the shop with, against how far its welds sit from the section's centroid. A weld cannot contract while the plate holds it, so it yields in tension and what is left when everything is cold is a locked-in force at about the yield stress: 312 kN for the 1.2 kJ/mm of heat drawn, over a shrinkage zone of 439 mm². Applied 210 mm off the centroid that is a moment, and a moment applied along a member is a curvature: the 12 m girder comes out bowed 12.5 mm, which is L/962 against a fabrication tolerance of L/1000. It also comes out 1.2 mm shorter. Welding symmetrically about the centroid puts the resultant on the neutral axis and the bow becomes 0.00 mm — the same heat, the same force, and no moment at all. Connections

The shape that came out of the shop

A weld cools by seven hundred degrees while the plate holds it, so it yields in tension and stays that way. What is left is a locked-in force of three hundred kilonewtons applied where the weld is, and if that is not on the centroid the member leaves the shop bent.

The library, page 1 of 7 — where camber-stages sits